SERVICE REPORT

DATE CONDUCTED : JULY 8, 2023


CLIENT : DNATA CALL CENTER

SCOPE OF WORKS DONE:

1. ANNUAL Electrical System Maintenance


2. Bolt Tightening of all panels
3. Cleaning of Panels using brush and vacuum
4. Current reading of Main and Distribution Panels

RESULTS:

CB
PANEL ID L1 L2 L3 REMARKS
RATING

MDP 2000 389 402 339 - All panels have not reached 80% of load
on the distribution
- Panel ACU 1 on time of reading has low L3
ACU 1 200 14.9 15.97 5.88 reading due to single phase load present in
the system
- Panel PPA on time of reading has low L3
ACU 2 200 9.59 21.9 19.3 reading due to single phase load present in
the system
ACU 3 200 17.15 25.45 9.26  
LP-2B 100 9.47 7.37 7.46  
PP-2A 125 8.99 5.9 7.35  
PP-2B 125 2.65 3.11 2  
UPS 2A 125 2.75 8.18 2.29  
UPS 2B 125 5.44 7.55 7.6  
DP2 225 1.02 18.44 18.2  
PP2 - AC 600 39.3 27.5 7.55  
LPA 160 25.89 20.7 23.43  
PPA 400 87.92 74.47 44.36  
DBN-1 100 1.34 1.88 1.71  
DB-UPS1 150 4.06 1.48 3.65  
DB-UPS2 150 6 2.46 3.05  
XMER
400 40 54.3 31.94
INPUT  

Comments / Recommendations:
1. Full Load current can be read using the MDP Circuit Breaker as shown below. This is to ensure
that the load does not reach 80% of the Breaker Reading.
2. Since the load is only on a minimum, it is expected that the breakers on the main and the
distribution does not heat up and is working perfectly.
3. During the time of the cleaning, it is noted that the wire gutter was also used as the splicing box
during construction.
4. Next PMS is scheduled October.

Prepared by:

Graham Nash C. Langomez


Project Manager