Professional Documents
Culture Documents
SPARK STAR-54 Final 132KV Tripping Due To 33KV Clearnce
SPARK STAR-54 Final 132KV Tripping Due To 33KV Clearnce
Frequent tripping of 132Kv line due to 33 KV Clearance issue and its solution
SITUATION:
One of the 132 KV Line was tripping during hot summer due to phase clearance issue with
33KV Line.
Observations:
1. This line was equipped with 132KV Panther conductor and passed above 33KV line.
2. During hot summer and due to electrical clearance issue, this line was tripping
frequently.
3. The discom wing owner of 33KV line was requested to lower the line to the allowable
zone, but tripping still persisted with hot summer.
4. The 132KV line was re-strung to raise till allowable distance, but problem could not
be resolved.
5. Finally, solution was temporarily considered with use of insulation sleeve upon the 33
KV line before the decision of diversion of this 33KV line under 132 KV system.
6. The problem was solved temporarily.
7. Use of insulation sleeve could also be considered as the practice for such solution as
this helps techno-economically instead of putting money on diversion or construction
of new system.
8. On studying the response, use of insulation sleeve was taken as the permanent
solution on this system.
9. Then onwards no tripping had been observed even with of all severe situations.
Technical Analysis:
11. All the above methods had been attempted except the use of insulation PVC.
12. Now calculation with PVC insulation
Thumb rule PVC thickness is 16 times equivalent to air. Let us provide min. 2 inch pvc
thickness= 2x16 = 32 inch = 2. 75 ft >2.6 ft reqd. Now extra 1 ft could be attended by
lowering.
But this method is also technically not feasible due to the issue of wrapping 2-inch
thickness PVC.
13. Finally, it was enquired upon the special insulated sleeves from the market and found
with such with lightweight and lesser thickness of 1inch.
14. This sleeve was put on 33 KV conductor and then found with of no problem.