Professional Documents
Culture Documents
Installation Manual
(1 of 1)
Yard/Customer : Astilleros Balenciaga
Hull no. : NB448-NB453
Customer reference :
Order No. : 53026-28 & 53031-33
Document name : UPY-B31026-01MI
Revision :F
Author : TB
Date First Issue : 05.02.2014
Comments : Mov exp.tank
Introduction Installation Manual 1
PRODUCT, Layout 6
Document Summary
The Installation Manual describes issue for installation and commission of the system delivered by
Ulmatec Pyro.
ULMATEC PYRO AS
Gamlem, 6280 Søvik, Norway
Tel.: +47 70 20 98 70 Pyro@ulmatec.no www.ulmatec.no Reg. No. 966 300 345
UPY-D11001-01SX (B) Pyro Energy Management System - Introduction To Installation Manual.Docx Page 1 of 8
CONTENTS
1 Abbreviations .................................................................................................................................. 3
2 Ulmatec Pyro ................................................................................................................................... 3
2.1 Office Address ......................................................................................................................... 3
2.2 Mail & Web Address ................................................................................................................ 3
2.3 Telephone & Fax ...................................................................................................................... 3
2.4 VAT Identification Number ...................................................................................................... 3
3 Installation Disciplines ..................................................................................................................... 4
3.1 Installation of the system ........................................................................................................ 4
3.2 Commission ............................................................................................................................. 4
4 Mechanical Mounting ..................................................................................................................... 5
4.1 Environmental Specification.................................................................................................... 5
4.2 Mechanical Mounting ............................................................................................................. 5
4.3 Welding ................................................................................................................................... 5
4.4 Installation mechanical............................................................................................................ 6
4.4.1 Foundation mechanical equipment. ............................................................................... 6
4.4.2 Metric bolt tightening torque.......................................................................................... 6
5 Piping ............................................................................................................................................... 7
5.1 Piping Specification ................................................................................................................. 7
5.2 Air Ventilation Pipes ................................................................................................................ 7
5.3 Pipes from safety valves .......................................................................................................... 7
5.4 Exhaust Pipe. ........................................................................................................................... 7
6 Electric Installation .......................................................................................................................... 8
6.1 Cable types .............................................................................................................................. 8
6.2 Cable entry .............................................................................................................................. 8
6.3 Cable routing ........................................................................................................................... 8
ULMATEC PYRO AS
Gamlem, 6280 Søvik, Norway
Tel.: +47 70 20 98 70 Pyro@ulmatec.no www.ulmatec.no Reg. No. 966 300 345
UPY-D11001-01SX (B) Pyro Energy Management System - Introduction To Installation Manual.Docx Page 2 of 8
1 Abbreviations
UPY Ulmatec Pyro AS
2 Ulmatec Pyro
Ulmatec Pyro AS
Gamlem
6280 Søvik
NORWAY
Mail: pyro@ulmatec.no
Web: www.ulmatec.no
Telephone : +47 70 20 98 70
Fax : +47 70 20 98 90
ULMATEC PYRO AS
Gamlem, 6280 Søvik, Norway
Tel.: +47 70 20 98 70 Pyro@ulmatec.no www.ulmatec.no Reg. No. 966 300 345
UPY-D11001-01SX (B) Pyro Energy Management System - Introduction To Installation Manual.Docx Page 3 of 8
3 Installation Disciplines
Installation of the system delivered by Ulmatec Pyro is normally arranged by the customer or
the ship yard.
3.2 Commission
ULMATEC PYRO AS
Gamlem, 6280 Søvik, Norway
Tel.: +47 70 20 98 70 Pyro@ulmatec.no www.ulmatec.no Reg. No. 966 300 345
UPY-D11001-01SX (B) Pyro Energy Management System - Introduction To Installation Manual.Docx Page 4 of 8
4 Mechanical Mounting
The classification societies has requirement regarding IP protection, humidity, vibration and
EMC for different area on the ship. For information on location of the product, see product
layout for each item.
Information regarding size, weight and foundation is specified in the product layout drawing.
Note that the control cabinet required at least 10 cm free space on all side to meet the
temperature requirement specified for each item.
4.3 Welding
When welding on or near the equipment that includes electric components the welding earth
cable shall be connected directly to the work piece. Make sure that the earth connection has
good electric connection.
ULMATEC PYRO AS
Gamlem, 6280 Søvik, Norway
Tel.: +47 70 20 98 70 Pyro@ulmatec.no www.ulmatec.no Reg. No. 966 300 345
UPY-D11001-01SX (B) Pyro Energy Management System - Introduction To Installation Manual.Docx Page 5 of 8
4.4 Installation mechanical
- The requirement for the foundation for item is specified on the layout drawing.
- The alignment should be checked and if necessary be adjusted by shimming under the
appropriated position.
- To fasten the unit use bolt size according to the holes specified on the layout drawing.
- Use grade 8.8 bolt and nut.
- Use washer.
- Use torque tools
Bolt & Nut size [Nm] Bolt & Nut with grade 8.8
M8 18
M10 35
M12 60
M14 95
M16 150
M18 200
M20 300
M22 390
M24 500
M27 720
M30 980
M33 1320
ULMATEC PYRO AS
Gamlem, 6280 Søvik, Norway
Tel.: +47 70 20 98 70 Pyro@ulmatec.no www.ulmatec.no Reg. No. 966 300 345
UPY-D11001-01SX (B) Pyro Energy Management System - Introduction To Installation Manual.Docx Page 6 of 8
5 Piping
Notice that air ventilation pipes from tanks shall be routed without any traps. The pipe should
if possible be mounted in a location where the temperature is above +5 degree.
The pipes from safety valves shall be routed to a safe area. The pipe should if possible be
mounted in a location where the temperature is above +5 degree.
We recommend that the spark arrestor is mounted on the upper part of the exhaust pipe.
Note that the spark arrestor must be mounted on a location where maintenance can be easily
done.
The exhaust pipe shall be mounted in such way that the pipe always rises upward.
ULMATEC PYRO AS
Gamlem, 6280 Søvik, Norway
Tel.: +47 70 20 98 70 Pyro@ulmatec.no www.ulmatec.no Reg. No. 966 300 345
UPY-D11001-01SX (B) Pyro Energy Management System - Introduction To Installation Manual.Docx Page 7 of 8
6 Electric Installation
Information regarding cable, conductors and wiring types is specified in the project specific
documentation. For more specific cable requirement see cable specification.
The cable entry on the on the control cabinet is located on the bottom of the cabinet.
Cable glands are normally included in the scope of supply from Ulmatec.
The cables shall be fixed to the dedicated earth rail located inside the cabinet. The project
specific diagram specifies cable screen requirements. Cable screen is to be earthed to the
dedicated earth rail. The cable screen shall in this case be connected to the earth rail with a
360 degree connection. We propose to use cooper patent straps.
For easier connection many cables can be bundled together.
Note that communication cables (serial, LAN, CAN and IO) shall be routed with a distance of
at least 40 cm from power cables. If a communication cable is crossing a power cable this
shall be done with a 90 degrees angle.
Note that the cable manufacture specified maximum bending radius for each cable types.
This is particular important for LAN cables.
ULMATEC PYRO AS
Gamlem, 6280 Søvik, Norway
Tel.: +47 70 20 98 70 Pyro@ulmatec.no www.ulmatec.no Reg. No. 966 300 345
UPY-D11001-01SX (B) Pyro Energy Management System - Introduction To Installation Manual.Docx Page 8 of 8
Index divider: Section 2 N
Index divider: Section 3 N
Index divider: Section 6 N
Index divider: Section 10
Document Type: Document Name:
SYSTEM –
Harbour Acceptance Test (HAT) UPY-D11001-01SH
Document Title: Date First Issue: Revision:
HAT – Pyro Energy Management System 14.01.2013
Author:
Arne Skotte -
Ulmatec Pyro AS, Project Information:
Project No:
…………………………………………………………………………….
Yard:
…………………………………………………………………………….
Hull Number:
…………………………………………………………………………….
Customer Reference:
…………………………………………………………………………….
Location:
…………………………………………………………………………….
Test Date:
…………………………………………………………………………….
Ulmatec Pyro AS
Service Engineer: …………………………………………………………………………….
Yard / Customer:
(Optional) …………………………………………………………………………….
Classification Society:
(Optional) …………………………………………………………………………….
Ship Owner:
(Optional) …………………………………………………………………………….
ULMATEC PYRO AS
Gamlem, 6280 Søvik, Norway
Tel.: +47 70 20 98 70 Pyro@ulmatec.no www.ulmatec.no Reg. No. 966 300 345
UPY-D11001-01SH (-) Pyro Energy Management System - HAT.Docx Page 1 of 33
CONTENTS
2 ABBREVIATIONS ...................................................................................................................................... 4
3 GENERAL INFORMATION, SYSTEM HAT ......................................................................................... 5
3.1 PURPOSE SYSTEM HAT ............................................................................................................................. 5
3.2 TEST REQUIREMENT................................................................................................................................... 5
3.3 HAT COMMISSION TEST............................................................................................................................ 5
3.4 TEST CONFIGURATION ............................................................................................................................... 5
4 INSTALLATION ........................................................................................................................................ 6
4.1 PRE-COMMISSION ...................................................................................................................................... 6
4.1.1 Arrangement Drawing..................................................................................................................... 6
4.1.2 System Liquid .................................................................................................................................. 6
4.1.3 Comments and signature:................................................................................................................ 6
5 HEAT DISTRIBUTION, CENTRAL HEATING .................................................................................... 7
5.1 PRE-COMMISSION ...................................................................................................................................... 7
5.1.1 Expansion tank no.1 ........................................................................................................................ 7
5.1.2 Expansion tank no.2 ........................................................................................................................ 7
5.1.3 Expansion tank no.3 ........................................................................................................................ 7
5.1.4 Circulation pump............................................................................................................................. 8
5.1.5 Flow Control Unit ........................................................................................................................... 9
5.1.6 Control System, Central Heat Distribution. .................................................................................. 10
5.1.7 Comments and signature:.............................................................................................................. 11
5.2 COMMISSION ........................................................................................................................................... 12
5.2.1 Heat Distribution, Central Heating............................................................................................... 12
5.2.2 Comments and signature:.............................................................................................................. 13
6 HEAT GENERATOR, FUEL FIRED HEATER ................................................................................... 14
6.1 PRE-COMMISSION .................................................................................................................................... 14
6.1.1 Mounting Fuel Fired Heater ......................................................................................................... 14
6.1.2 Technical Installation Fuel Fired Heater...................................................................................... 14
6.1.3 Circulation pump (Local unit) ...................................................................................................... 14
6.1.4 Control System, Fuel Fired Heater ............................................................................................... 15
6.1.5 Comments and signature:.............................................................................................................. 17
6.2 COMMISSION ........................................................................................................................................... 18
6.2.1 Heat Generator, Fuel Fired Heater .............................................................................................. 18
6.2.2 Comments and signature:.............................................................................................................. 20
7 HEAT GENERATOR, EXHAUST GAS ECONOMISER .................................................................... 21
7.1 PRE-COMMISSION .................................................................................................................................... 21
7.1.1 Mounting Exhaust Gas Economiser .............................................................................................. 21
7.1.2 Technical Installation Exhaust Gas Economiser........................................................................... 21
7.1.3 Circulation pump (Optional) ......................................................................................................... 21
7.1.4 Dumping pump (Optional) ............................................................................................................ 22
7.1.5 Control System, Exhaust Gas Economiser .................................................................................... 22
7.1.6 Comments and signature:.............................................................................................................. 24
7.2 COMMISSION ........................................................................................................................................... 25
7.2.1 Heat Generator, Exhaust Gas Economiser ................................................................................... 25
7.2.2 Comments and signature:.............................................................................................................. 26
8 HEAT CONSUMER, TANK HEATING ................................................................................................ 27
8.1 PRE-COMMISSION .................................................................................................................................... 27
8.1.1 Expansion tank .............................................................................................................................. 27
8.1.2 Circulation pump........................................................................................................................... 27
8.1.3 Heat Exchanger ............................................................................................................................. 27
8.1.4 Bypass Valve ................................................................................................................................. 28
ULMATEC PYRO AS
Gamlem, 6280 Søvik, Norway
Tel.: +47 70 20 98 70 Pyro@ulmatec.no www.ulmatec.no Reg. No. 966 300 345
UPY-D11001-01SH (-) Pyro Energy Management System - HAT.Docx Page 2 of 33
8.1.5 Heating Coil & Valve Unit ............................................................................................................ 28
8.1.6 Control System, Tank Heating System........................................................................................... 29
8.1.7 Comments and signature:.............................................................................................................. 30
8.2 COMMISSION ........................................................................................................................................... 31
8.2.1 Heat Consumer, Tank Heating ...................................................................................................... 31
8.2.2 Comments and signature:.............................................................................................................. 32
9 SOFTWARE BACKUP ............................................................................................................................ 32
9.1.1 Order Software backup ................................................................................................................. 32
10 PUNCH LIST ............................................................................................................................................. 33
ULMATEC PYRO AS
Gamlem, 6280 Søvik, Norway
Tel.: +47 70 20 98 70 Pyro@ulmatec.no www.ulmatec.no Reg. No. 966 300 345
UPY-D11001-01SH (-) Pyro Energy Management System - HAT.Docx Page 3 of 33
2 Abbreviations
HAT Harbour Acceptance Test
FAT Factory Acceptance Test
UPY Ulmatec Pyro AS
DNV Det Norske Veritas
HMI Human Machine Interface
S/N Serial Number
ULMATEC PYRO AS
Gamlem, 6280 Søvik, Norway
Tel.: +47 70 20 98 70 Pyro@ulmatec.no www.ulmatec.no Reg. No. 966 300 345
UPY-D11001-01SH (-) Pyro Energy Management System - HAT.Docx Page 4 of 33
3 General information, System HAT
For each product the HAT is divided into a Pre-commission (assisted by Ulmatec service engineer) and a
Quayside test.
The HAT (quayside) test shall be verified by the Ulmatec service engineer and the customer for each test:
• If a test is not valid it shall be marked “NA” (Not Applicable).
• Any other comments shall be marked in the “Comment Field”.
• If a comment requires any correction it shall be noted on the “punch list”.
ULMATEC PYRO AS
Gamlem, 6280 Søvik, Norway
Tel.: +47 70 20 98 70 Pyro@ulmatec.no www.ulmatec.no Reg. No. 966 300 345
UPY-D11001-01SH (-) Pyro Energy Management System - HAT.Docx Page 5 of 33
4 Installation
4.1 Pre-Commission
………………………………………………………………………………………………………………….
………………………………………………………………………………………………………………….
………………………………………………………………………………………………………………….
Signature:
ULMATEC PYRO AS
Gamlem, 6280 Søvik, Norway
Tel.: +47 70 20 98 70 Pyro@ulmatec.no www.ulmatec.no Reg. No. 966 300 345
UPY-D11001-01SH (-) Pyro Energy Management System - HAT.Docx Page 6 of 33
5 Heat Distribution, Central Heating
This chapter describes all activities specified for Heat Distribution, Central Heating.
5.1 Pre-Commission
5.1.1 Expansion tank no.1
Checkpoints:
Description Verified √,
Not Applicable NA
Specify location:
----------------------------------------------------------------------------
Check for visual damage.
Mounted so that service is possible.
Unit mounted according to specification.
Measure system pressure at the location of the expansion tank : Bar
Note: Open system to atmosphere. ---------------
Add air pressure to the expansion tank (system pressure + 0,2Bar): Bar
---------------
ULMATEC PYRO AS
Gamlem, 6280 Søvik, Norway
Tel.: +47 70 20 98 70 Pyro@ulmatec.no www.ulmatec.no Reg. No. 966 300 345
UPY-D11001-01SH (-) Pyro Energy Management System - HAT.Docx Page 7 of 33
5.1.4 Circulation pump
Checkpoints:
Description Verified √,
Not Applicable NA
Specify location:
----------------------------------------------------------------------------
Check for visual damage.
Mounted so that service is possible.
Unit fasten to the foundation according to specification.
Bled the pump before operating.
Observe that there is no leakage from the unit or the piping.
Verify that the pump runs in the correct direction.
Verify the pressure before the pump is correct : Bar
------------------
Verify the pressure after the pump is correct : Bar
------------------
When circulation pump 1 running : Bar
Verify that the flow through the pump is correct according to the specific pump curve. ------------
Note: that the differential pressure through the non-return valve is typical 0.1-0.3 Bar.
When circulation pump 2 running : Bar
Verify that the flow through the pump is correct according to the specific pump curve. ------------
Note: that the differential pressure through the non-return valve is typical 0.1-0.3 Bar.
When circulation pump 3 running : Bar
Verify that the flow through the pump is correct according to the specific pump curve. ------------
Note: that the differential pressure through the non-return valve is typical 0.1-0.3 Bar.
When circulation pump 1 and 2 running : Bar
Verify that the flow through the pump is correct according to the specific pump curve. ------------
Note: that the differential pressure through the non-return valve is typical 0.1-0.3 Bar.
When circulation pump 1,2 and 3 running : Bar
Verify that the flow through the pump is correct according to the specific pump curve. ------------
Note: that the differential pressure through the non-return valve is typical 0.1-0.3 Bar.
ULMATEC PYRO AS
Gamlem, 6280 Søvik, Norway
Tel.: +47 70 20 98 70 Pyro@ulmatec.no www.ulmatec.no Reg. No. 966 300 345
UPY-D11001-01SH (-) Pyro Energy Management System - HAT.Docx Page 8 of 33
5.1.5 Flow Control Unit
Checkpoints:
Description Verified √,
Not Applicable NA
Check for visual damage.
Mounted so that service is possible.
Unit fasten to the foundation according to specification.
Observe that there is no leakage from the unit or the piping.
Observe that the temperature sensor for flow to consumer number 1 is mounted.
Observe that the temperature sensor for flow to consumer number 2 is mounted.
Observe that the temperature sensor for flow to consumer number 3 is mounted.
Observe that the temperature sensor for flow to consumer number 4 is mounted.
Observe that the temperature sensor for flow to consumer number 5 is mounted.
Observe that the temperature sensor for flow to consumer number 6 is mounted.
Observe that the temperature sensor for flow to consumer number 7 is mounted.
Observe that the temperature sensor for flow to consumer number 8 is mounted.
Observe that the temperature sensor for flow from recovery number 1 is mounted.
Observe that the temperature sensor for flow from recovery number 2 is mounted.
Observe that the temperature sensor for flow from recovery number 3 is mounted.
Observe that the temperature sensor for flow from recovery number 4 is mounted.
Observe that the temperature sensor for flow from recovery number 5 is mounted.
Observe that the temperature sensor for flow from recovery number 6 is mounted.
Observe that the temperature sensor for flow from recovery number 7 is mounted.
Observe that the temperature sensor for flow from recovery number 8 is mounted.
ULMATEC PYRO AS
Gamlem, 6280 Søvik, Norway
Tel.: +47 70 20 98 70 Pyro@ulmatec.no www.ulmatec.no Reg. No. 966 300 345
UPY-D11001-01SH (-) Pyro Energy Management System - HAT.Docx Page 9 of 33
5.1.6 Control System, Central Heat Distribution.
………………………………………………………………………………………………………………….
………………………………………………………………………………………………………………….
………………………………………………………………………………………………………………….
………………………………………………………………………………………………………………….
Signature:
ULMATEC PYRO AS
Gamlem, 6280 Søvik, Norway
Tel.: +47 70 20 98 70 Pyro@ulmatec.no www.ulmatec.no Reg. No. 966 300 345
UPY-D11001-01SH (-) Pyro Energy Management System - HAT.Docx Page 11 of 33
5.2 Commission
ULMATEC PYRO AS
Gamlem, 6280 Søvik, Norway
Tel.: +47 70 20 98 70 Pyro@ulmatec.no www.ulmatec.no Reg. No. 966 300 345
UPY-D11001-01SH (-) Pyro Energy Management System - HAT.Docx Page 12 of 33
5.2.1.5 System demonstration, Failure modes – Control system
Checkpoints:
Description Verified √,
Not Applicable NA
Disconnect the power supply to the control voltage and observe that the system shut
down and external alarm is activated.
Disconnect the power supply to the main voltage and observe that the system shut
down and external alarm is activated.
Disconnect LAN interface to the HMI and observe that the external alarm is activated.
Disconnect CAN interface to the consumer flow control unit and observe that the
internal and external alarm is activated.
Disconnect CAN interface to the recovery flow control unit and observe that the
internal and external alarm is activated.
………………………………………………………………………………………………………………….
………………………………………………………………………………………………………………….
………………………………………………………………………………………………………………….
………………………………………………………………………………………………………………….
Signature:
ULMATEC PYRO AS
Gamlem, 6280 Søvik, Norway
Tel.: +47 70 20 98 70 Pyro@ulmatec.no www.ulmatec.no Reg. No. 966 300 345
UPY-D11001-01SH (-) Pyro Energy Management System - HAT.Docx Page 13 of 33
6 Heat Generator, Fuel Fired Heater
This chapter is a guideline for the system HAT implementation for Fuel Fired Heater.
6.1 Pre-Commission
6.1.1 Mounting Fuel Fired Heater
Checkpoints:
Description Verified √,
Not Applicable NA
Check for visual damage.
Service space, possible to disassemble sanitary heat water coil.
Service space, possible to disassemble electric heating element.
Service space, possible to disassemble steam coil.
Unit mounted according to specification.
ULMATEC PYRO AS
Gamlem, 6280 Søvik, Norway
Tel.: +47 70 20 98 70 Pyro@ulmatec.no www.ulmatec.no Reg. No. 966 300 345
UPY-D11001-01SH (-) Pyro Energy Management System - HAT.Docx Page 14 of 33
6.1.4 Control System, Fuel Fired Heater
ULMATEC PYRO AS
Gamlem, 6280 Søvik, Norway
Tel.: +47 70 20 98 70 Pyro@ulmatec.no www.ulmatec.no Reg. No. 966 300 345
UPY-D11001-01SH (-) Pyro Energy Management System - HAT.Docx Page 15 of 33
6.1.4.7 Fuel transfer pump
Checkpoints:
Description Verified √,
Not Applicable NA
Operate the pump and observe that the rotation direction is correct.
ULMATEC PYRO AS
Gamlem, 6280 Søvik, Norway
Tel.: +47 70 20 98 70 Pyro@ulmatec.no www.ulmatec.no Reg. No. 966 300 345
UPY-D11001-01SH (-) Pyro Energy Management System - HAT.Docx Page 16 of 33
6.1.4.12 System Operation – Pump Menu
Checkpoints:
Description Verified √,
Not Applicable NA
Valid for system with flow control unit.
For each circulation pump adjust following:
- Start requirement, differential pressure in Bar.
See order documentation (lowest pressure pump curve): ________Bar
- Stop requirement,
Default value equal 10%.
Adjusted during commission to: _____ %
Position of by-pass valve on flow control unit _____ %
-
Valid for system without flow control unit.
For each circulation pump adjust following:
- Start requirement, differential pressure in Bar.
See order documentation (lowest pressure pump curve): ________Bar
………………………………………………………………………………………………………………….
………………………………………………………………………………………………………………….
………………………………………………………………………………………………………………….
………………………………………………………………………………………………………………….
Signature:
ULMATEC PYRO AS
Gamlem, 6280 Søvik, Norway
Tel.: +47 70 20 98 70 Pyro@ulmatec.no www.ulmatec.no Reg. No. 966 300 345
UPY-D11001-01SH (-) Pyro Energy Management System - HAT.Docx Page 17 of 33
6.2 Commission
6.2.1 Heat Generator, Fuel Fired Heater
ULMATEC PYRO AS
Gamlem, 6280 Søvik, Norway
Tel.: +47 70 20 98 70 Pyro@ulmatec.no www.ulmatec.no Reg. No. 966 300 345
UPY-D11001-01SH (-) Pyro Energy Management System - HAT.Docx Page 18 of 33
6.2.1.6 Safety Function – Flame Control - when starting
Checkpoints:
Description Verified √,
Not Applicable NA
Before starting up, withdraw the photocell from socket (false flame failure). Photocell
shall be kept in dark. Activate electric heating.
Start the oil burner.
Flame ignites.
Power supply shall be cut after a delay of 5 sec.
The "FLAME FAILURE", lights up.
External and internal alarm is issued.
Note: The electric heating element shall still be on.
Refit the photocell in socket and fuel fired heater is restarted by pushing
“Reset Burner Control”.
Alternatively the water level pressure switch could be checked with a pressure pump
on the test- flange connection.
External alarm is issued.
Remove the water low level alarm level to normal value, and the heater restarts.
ULMATEC PYRO AS
Gamlem, 6280 Søvik, Norway
Tel.: +47 70 20 98 70 Pyro@ulmatec.no www.ulmatec.no Reg. No. 966 300 345
UPY-D11001-01SH (-) Pyro Energy Management System - HAT.Docx Page 19 of 33
6.2.1.9 System demonstration, Failure modes – Control system
Checkpoints:
Description Verified √,
Not Applicable NA
Activate the emergency stop and observe fuel oil burner shutdown and external alarm
is activated.
Switch off the protection circuit to the electric heating element and observe that the
internal and external alarm is activated.
Switch off the protection circuit to the burner motor and observe fuel oil burner
shutdown (burner will try to restart) and external alarm is activated.
Switch off the protection circuit to each circulation pump and observe that the internal
and external alarm is activated.
Switch off the protection circuit to the sanitary hot water circulation pump and observe
that the internal and external alarm is activated.
Switch off the protection circuit to each fuel transfer pump and observe that the
internal and external alarm is activated.
Switch off the protection circuit to each fuel heating and observe that the internal and
external alarm is activated.
………………………………………………………………………………………………………………….
………………………………………………………………………………………………………………….
………………………………………………………………………………………………………………….
………………………………………………………………………………………………………………….
Signature:
ULMATEC PYRO AS
Gamlem, 6280 Søvik, Norway
Tel.: +47 70 20 98 70 Pyro@ulmatec.no www.ulmatec.no Reg. No. 966 300 345
UPY-D11001-01SH (-) Pyro Energy Management System - HAT.Docx Page 20 of 33
7 Heat Generator, Exhaust Gas Economiser
This chapter is a guideline for the system HAT implementation for Exhaust Gas Economiser
7.1 Pre-Commission
7.1.1 Mounting Exhaust Gas Economiser
Checkpoints:
Description Verified √,
Not Applicable NA
Check for visual damage.
Service space, possible to access the exhaust gas damper air valve or CAN motor
Service space, possible to access inspection holes for cleaning and inspection.
Unit mounted according to specification.
ULMATEC PYRO AS
Gamlem, 6280 Søvik, Norway
Tel.: +47 70 20 98 70 Pyro@ulmatec.no www.ulmatec.no Reg. No. 966 300 345
UPY-D11001-01SH (-) Pyro Energy Management System - HAT.Docx Page 21 of 33
7.1.4 Dumping pump (Optional)
Checkpoints:
Description Verified √,
Not Applicable NA
Specify location:
----------------------------------------------------------------------------
Check for visual damage.
Mounted so that service is possible.
Unit fasten to the foundation according to specification.
Bled the pump before operating.
Observe that there is no leakage from the unit or the piping.
Verify that the pump runs in the correct direction.
Verify the pressure before the pump is correct : Bar
------------------
Verify the pressure after the pump is correct : Bar
------------------
ULMATEC PYRO AS
Gamlem, 6280 Søvik, Norway
Tel.: +47 70 20 98 70 Pyro@ulmatec.no www.ulmatec.no Reg. No. 966 300 345
UPY-D11001-01SH (-) Pyro Energy Management System - HAT.Docx Page 22 of 33
7.1.5.4 Supply Circulation Pump (Optional)
Checkpoints:
Description Verified √,
Not Applicable NA
Adjust the setting for the frequency inverter according to the order related
documentation.
Verify that the motor frequency is constant when the input frequency is alternated.
- Stop requirement,
Default value equal 10%.
Adjusted during commission to: _____ %
Position of by-pass valve on flow control unit _____ %
ULMATEC PYRO AS
Gamlem, 6280 Søvik, Norway
Tel.: +47 70 20 98 70 Pyro@ulmatec.no www.ulmatec.no Reg. No. 966 300 345
UPY-D11001-01SH (-) Pyro Energy Management System - HAT.Docx Page 23 of 33
7.1.6 Comments and signature:
Comments:
………………………………………………………………………………………………………………….
………………………………………………………………………………………………………………….
………………………………………………………………………………………………………………….
………………………………………………………………………………………………………………….
Signature:
ULMATEC PYRO AS
Gamlem, 6280 Søvik, Norway
Tel.: +47 70 20 98 70 Pyro@ulmatec.no www.ulmatec.no Reg. No. 966 300 345
UPY-D11001-01SH (-) Pyro Energy Management System - HAT.Docx Page 24 of 33
7.2 Commission
7.2.1 Heat Generator, Exhaust Gas Economiser
Alternatively the water level pressure switch could be checked with a pressure pump
on the test- flange connection.
External alarm is issued.
Remove the water low level alarm level to normal value, and the exhaust gas
economiser start operate as normal.
ULMATEC PYRO AS
Gamlem, 6280 Søvik, Norway
Tel.: +47 70 20 98 70 Pyro@ulmatec.no www.ulmatec.no Reg. No. 966 300 345
UPY-D11001-01SH (-) Pyro Energy Management System - HAT.Docx Page 25 of 33
7.2.1.5 System demonstration, Failure modes – Control system
Checkpoints:
Description Verified √,
Not Applicable NA
Activate the emergency stop and observe that the exhaust economiser is set to bypass
position.
Switch off the protection circuit to each circulation pump and observe that the internal
and external alarm is activated.
Switch off the protection circuit to each dumping pump and observe that the internal
and external alarm is activated.
………………………………………………………………………………………………………………….
………………………………………………………………………………………………………………….
………………………………………………………………………………………………………………….
………………………………………………………………………………………………………………….
Signature:
ULMATEC PYRO AS
Gamlem, 6280 Søvik, Norway
Tel.: +47 70 20 98 70 Pyro@ulmatec.no www.ulmatec.no Reg. No. 966 300 345
UPY-D11001-01SH (-) Pyro Energy Management System - HAT.Docx Page 26 of 33
8 Heat Consumer, Tank Heating
This chapter describes all activities specified for Heat Consumer, Tank Heating.
8.1 Pre-Commission
8.1.1 Expansion tank
Checkpoints:
Description Verified √,
Not Applicable NA
Check for visual damage.
Mounted so that service is possible.
Unit mounted according to specification.
Measure system pressure at the location of the expansion tank : Bar
Note: Open system to atmosphere. ---------------
Add air pressure to the expansion tank (system pressure + 0,2Bar): Bar
---------------
ULMATEC PYRO AS
Gamlem, 6280 Søvik, Norway
Tel.: +47 70 20 98 70 Pyro@ulmatec.no www.ulmatec.no Reg. No. 966 300 345
UPY-D11001-01SH (-) Pyro Energy Management System - HAT.Docx Page 27 of 33
8.1.4 Bypass Valve
Checkpoints:
Description Verified √,
Not Applicable NA
Verify that the bypass valve is correct mounted.
ULMATEC PYRO AS
Gamlem, 6280 Søvik, Norway
Tel.: +47 70 20 98 70 Pyro@ulmatec.no www.ulmatec.no Reg. No. 966 300 345
UPY-D11001-01SH (-) Pyro Energy Management System - HAT.Docx Page 28 of 33
8.1.6 Control System, Tank Heating System.
ULMATEC PYRO AS
Gamlem, 6280 Søvik, Norway
Tel.: +47 70 20 98 70 Pyro@ulmatec.no www.ulmatec.no Reg. No. 966 300 345
UPY-D11001-01SH (-) Pyro Energy Management System - HAT.Docx Page 29 of 33
8.1.6.5 System operation, Auto Control.
Checkpoints:
Description Verified √,
Not Applicable NA
One tank is set to AUTO control.
Start only one of the circulation pumps from the HMI.
Observe that the corresponding valve is operating according to the temperature set
point.
………………………………………………………………………………………………………………….
………………………………………………………………………………………………………………….
………………………………………………………………………………………………………………….
………………………………………………………………………………………………………………….
Signature:
ULMATEC PYRO AS
Gamlem, 6280 Søvik, Norway
Tel.: +47 70 20 98 70 Pyro@ulmatec.no www.ulmatec.no Reg. No. 966 300 345
UPY-D11001-01SH (-) Pyro Energy Management System - HAT.Docx Page 30 of 33
8.2 Commission
ULMATEC PYRO AS
Gamlem, 6280 Søvik, Norway
Tel.: +47 70 20 98 70 Pyro@ulmatec.no www.ulmatec.no Reg. No. 966 300 345
UPY-D11001-01SH (-) Pyro Energy Management System - HAT.Docx Page 31 of 33
8.2.2 Comments and signature:
Comments:
………………………………………………………………………………………………………………….
………………………………………………………………………………………………………………….
………………………………………………………………………………………………………………….
………………………………………………………………………………………………………………….
Signature:
9 Software backup
9.1.1 Order Software backup
Checkpoints:
Description Verified √,
Not Applicable NA
Create a backup of all software that has been changed during commission.
Create a backup of all SW configuration files.
The SW backup shall be returned to technical department.
ULMATEC PYRO AS
Gamlem, 6280 Søvik, Norway
Tel.: +47 70 20 98 70 Pyro@ulmatec.no www.ulmatec.no Reg. No. 966 300 345
UPY-D11001-01SH (-) Pyro Energy Management System - HAT.Docx Page 32 of 33
10 PUNCH LIST
All action that required correction shall be noted in the punch list
Punch Punch Description:
Number
10
ULMATEC PYRO AS
Gamlem, 6280 Søvik, Norway
Tel.: +47 70 20 98 70 Pyro@ulmatec.no www.ulmatec.no Reg. No. 966 300 345
UPY-D11001-01SH (-) Pyro Energy Management System - HAT.Docx Page 33 of 33
Index divider: Section 11
Document Type: Document Name:
SYSTEM -
Cable Specification UPY-D11001-01SC
Document Title: Date First Issue: Revision:
Pyro Energy Management System 22.02.2013
Author:
Arne Skotte A
Revision History
Revision: Description: Date: Sign:
A First Issue 22.02.2013 ASK
Document Summary
The document specified the cable types that are delivered by the customer.
For information regarding cable screen termination and wiring see order specified cable diagram.
ULMATEC PYRO AS
Gamlem NO-6280 Søvik
Tel.: +47 70 20 98 70 pyro@ulmatec.no www.ulmatec.no
UPY-D11001-01SC (A) Pyro Energy Management System - Cable Specification.Docx Page 1 of 6
CONTENTS
1 ABBREVIATIONS............................................................................................................................................ 3
2 GENERAL CABLE REQUIREMENT ........................................................................................................... 3
3 ETHERNET INTERFACE CABLES.............................................................................................................. 4
4 CAN FIELDBUS CABLES............................................................................................................................... 4
5 SERIAL INTERFACE CABLES. .................................................................................................................... 5
6 ANALOGUE INTERFACE CABLES . ........................................................................................................... 5
7 DIGITAL INTERFACE CABLES. ................................................................................................................. 5
8 POWER CABLES. ............................................................................................................................................ 6
9 POWER CABLES FEED FROM FREQUENCY INVERTER. ................................................................... 6
ULMATEC PYRO AS
Gamlem NO-6280 Søvik
Tel.: +47 70 20 98 70 pyro@ulmatec.no www.ulmatec.no
UPY-D11001-01SC (A) Pyro Energy Management System - Cable Specification.Docx Page 2 of 6
1 Abbreviations
UPY Ulmatec Pyro AS
DNV Det Norske Veritas
The cable shall meet the requirement from the classification Societies regarding:
- Flame retardant
- UV resistant
- Halogen free
- Smoke density of burning cables.
Approval
- The cable shall meet the requirement from one of the member in
IACS (International Association Classification Societies LTD)
ULMATEC PYRO AS
Gamlem NO-6280 Søvik
Tel.: +47 70 20 98 70 pyro@ulmatec.no www.ulmatec.no
UPY-D11001-01SC (A) Pyro Energy Management System - Cable Specification.Docx Page 3 of 6
3 Ethernet interface cables.
Cable Technical Specification:
- Bandwidth: 100MHz
- Shielding: Overall 360 degrees + individual continuous shielding.
- Transmission performance: Class F
- Impedance: 100Ohm
Cable label used on cable diagram for the specified cable:
- LAN Ethernet Interface Cables
Maximum cable length:
- Maximum cable length: 90m
Example of cable with type approval:
- Manufacture: Nexan Cable Solutions
- Type designation: LANmark-7, Maritime
- Approval: Det Norske Veritas
Other requirement:
- Cable colour specification: TIA/EIA 568B
ULMATEC PYRO AS
Gamlem NO-6280 Søvik
Tel.: +47 70 20 98 70 pyro@ulmatec.no www.ulmatec.no
UPY-D11001-01SC (A) Pyro Energy Management System - Cable Specification.Docx Page 4 of 6
5 Serial Interface cables.
Cable Technical Specification:
- Shielding: Overall 360 degrees
- Nominal Capacitance: <42 pF/m
- Resistance: < 100Ohm
- Cable Type: STP (Shielded Twisted Pair)
Cable label used on cable diagram for the specified cable:
- SIF Serial Interface Cables
Maximum cable length:
- Maximum cable length: 1200m
Example of cable with type approval:
- Manufacture: No recommendation.
- Type designation: TCX….., TFOU……
- Approval: One of the member in IACS (International Association Classification Societies LTD)
Other requirement:
ULMATEC PYRO AS
Gamlem NO-6280 Søvik
Tel.: +47 70 20 98 70 pyro@ulmatec.no www.ulmatec.no
UPY-D11001-01SC (A) Pyro Energy Management System - Cable Specification.Docx Page 5 of 6
8 Power cables.
Cable Technical Specification:
- Shielding: Overall 360 degrees
- Rated Voltage: See order specified cable diagram
Cable label used on cable diagram for the specified cable:
- PWR Power Cables
Maximum cable length:
- Maximum cable length: To be calculated by the customer
Example of cable with type approval:
- Manufacture: Draka
- Type designation: TXOI…..
- Approval: One of the member in IACS (International Association Classification Societies LTD)
Other requirement:
ULMATEC PYRO AS
Gamlem NO-6280 Søvik
Tel.: +47 70 20 98 70 pyro@ulmatec.no www.ulmatec.no
UPY-D11001-01SC (A) Pyro Energy Management System - Cable Specification.Docx Page 6 of 6
Document Type: Document Name:
SYSTEM -
Piping Specification UPY-D11001-01SP
Document Title: Date First Issue: Revision:
Pyro Energy Management System 13.05.2013
Author:
Arne Skotte A
Revision History
Revision: Description: Date: Sign:
A First Issue 13.05.2013 ASK
Document Summary
The document specified the flange standard used where the customer shall connect an external pipe to
the products delivered by Ulmatec Pyro.
ULMATEC PYRO AS
Gamlem, 6280 Søvik, Norway
Tel.: +47 70 20 98 70 Pyro@ulmatec.no www.ulmatec.no Reg. No. 966 300 345
UPY-D11001-01SP (A) Pyro Energy Management System - Piping Specification.Docx Page 1 of 6
CONTENTS
1 Abbreviations .................................................................................................................................. 3
2 Norwegian Standard NS2527 PN16 (Water Connection) ................................................................ 3
2.1 Flange Size: DN15, DN20, DN25, DN32, DN40, DN50, DN65 .................................................. 3
2.2 Flange Size: DN80, DN100, DN125, DN150 ............................................................................. 4
2.3 Flange Size: DN200, DN250, DN300 ........................................................................................ 4
3 Norwegian Standard NS2548 (Exhaust Connection) ....................................................................... 5
3.1 Flange Size: DN200, DN250, DN300 ........................................................................................ 5
3.2 Flange Size: DN350, DN400 ..................................................................................................... 5
3.3 Flange Size: DN500, DN600 ..................................................................................................... 6
3.4 Flange Size: DN700, DN800 ..................................................................................................... 6
ULMATEC PYRO AS
Gamlem, 6280 Søvik, Norway
Tel.: +47 70 20 98 70 Pyro@ulmatec.no www.ulmatec.no Reg. No. 966 300 345
UPY-D11001-01SP (A) Pyro Energy Management System - Piping Specification.Docx Page 2 of 6
1 Abbreviations
UPY Ulmatec Pyro AS
DNV Det Norske Veritas
2.1 Flange Size: DN15, DN20, DN25, DN32, DN40, DN50, DN65
ULMATEC PYRO AS
Gamlem, 6280 Søvik, Norway
Tel.: +47 70 20 98 70 Pyro@ulmatec.no www.ulmatec.no Reg. No. 966 300 345
UPY-D11001-01SP (A) Pyro Energy Management System - Piping Specification.Docx Page 3 of 6
2.2 Flange Size: DN80, DN100, DN125, DN150
ULMATEC PYRO AS
Gamlem, 6280 Søvik, Norway
Tel.: +47 70 20 98 70 Pyro@ulmatec.no www.ulmatec.no Reg. No. 966 300 345
UPY-D11001-01SP (A) Pyro Energy Management System - Piping Specification.Docx Page 4 of 6
3 Norwegian Standard NS2548 (Exhaust Connection)
ULMATEC PYRO AS
Gamlem, 6280 Søvik, Norway
Tel.: +47 70 20 98 70 Pyro@ulmatec.no www.ulmatec.no Reg. No. 966 300 345
UPY-D11001-01SP (A) Pyro Energy Management System - Piping Specification.Docx Page 5 of 6
3.3 Flange Size: DN500, DN600
ULMATEC PYRO AS
Gamlem, 6280 Søvik, Norway
Tel.: +47 70 20 98 70 Pyro@ulmatec.no www.ulmatec.no Reg. No. 966 300 345
UPY-D11001-01SP (A) Pyro Energy Management System - Piping Specification.Docx Page 6 of 6
Index divider: Section 12
Document Type: Document Name:
SYSTEM -
Preservation & Handling & Installation UPY-D11001-01ST
Document Title: Date First Issue: Revision:
Pyro Energy Management System 27.01.2014
Author:
Arne Skotte A
Revision History
Revision: Description: Date: Sign:
A First Issue 27.01.2014 ASK
Document Summary
ULMATEC PYRO AS
Gamlem, 6280 Søvik, Norway
Tel.: +47 70 20 98 70 Pyro@ulmatec.no www.ulmatec.no Reg. No. 966 300 345
UPY-D11001-01ST (A) Pyro Energy Management System -Preservation_Handling_Installation.Docx Page 1 of 5
CONTENTS
1 Abbreviations .................................................................................................................................. 3
2 Preservation and storage ................................................................................................................ 3
2.1 Visual inspections .................................................................................................................... 3
2.2 Preservation ............................................................................................................................ 3
3 Handling and Transportation .......................................................................................................... 4
3.1 Packing..................................................................................................................................... 4
3.2 Transportation ......................................................................................................................... 4
3.3 Inspection ................................................................................................................................ 4
3.4 Storing ..................................................................................................................................... 4
4 Lifting Procedure ............................................................................................................................. 5
4.1 Lifting Checklist........................................................................................................................ 5
4.2 Lifting procedure, mechanical item......................................................................................... 5
4.3 Lifting procedure, control cabinet. .......................................................................................... 5
ULMATEC PYRO AS
Gamlem, 6280 Søvik, Norway
Tel.: +47 70 20 98 70 Pyro@ulmatec.no www.ulmatec.no Reg. No. 966 300 345
UPY-D11001-01ST (A) Pyro Energy Management System -Preservation_Handling_Installation.Docx Page 2 of 5
1 Abbreviations
UPY Ulmatec Pyro AS
A visual inspection should be performed before storage. The inspection will reveal damage
and/or irregularities of the control system and the main mechanical components which should
be taken in consideration before storage.
2.2 Preservation
Make sure that the control units and junction boxes are dry. Any visible moisture or fluids
shall be removed. All units shall be clean before storage. Any leakage or other reason for
liquid inside the cabinet shall be investigated and repaired.
If the units shall be stored for more than 3 mounts we recommend add silica gel inside the
control cabinet and the junction boxes. The silica gel shall be replaced with new one every
third mounts.
Cabinet doors and hatches shall be closed and secured before storage.
As an additional protection we recommend to protect the unit with cardboard and foil wish is
fixed with tape.
ULMATEC PYRO AS
Gamlem, 6280 Søvik, Norway
Tel.: +47 70 20 98 70 Pyro@ulmatec.no www.ulmatec.no Reg. No. 966 300 345
UPY-D11001-01ST (A) Pyro Energy Management System -Preservation_Handling_Installation.Docx Page 3 of 5
3 Handling and Transportation
3.1 Packing
The equipment is packed in wooden case cover with plastic foiled or in cartons. The packing is
designed for long distance transportation with truck, sea and air.
3.2 Transportation
The equipment shall remain packed until installation. Shock and vibration shall be avoided.
Mechanical equipment shall be fastening to the floor by suitable straps attached to the unit
foundation. Control cabinet shall either be secured to the floor/deck by suitable straps or placed in
basket or a container for transportation.
3.3 Inspection
3.4 Storing
ULMATEC PYRO AS
Gamlem, 6280 Søvik, Norway
Tel.: +47 70 20 98 70 Pyro@ulmatec.no www.ulmatec.no Reg. No. 966 300 345
UPY-D11001-01ST (A) Pyro Energy Management System -Preservation_Handling_Installation.Docx Page 4 of 5
4 Lifting Procedure
- Attach the legged sling to the lifting points (see layout drawing).
- Make sure that the sling angle is 45 degrees or greater.
- Alternatively fork lift or a basket can be used.
- Attach the legged sling to the lifting points (see layout drawing).
- All front doors must be closed and locked.
- Make sure that the sling angle is 45 degrees or greater.
- Alternatively fork lift or a basket can be used.
ULMATEC PYRO AS
Gamlem, 6280 Søvik, Norway
Tel.: +47 70 20 98 70 Pyro@ulmatec.no www.ulmatec.no Reg. No. 966 300 345
UPY-D11001-01ST (A) Pyro Energy Management System -Preservation_Handling_Installation.Docx Page 5 of 5