You are on page 1of 2

TECHNICAL DATA & BILL OF QUANTITY

FOR CREMATORIUM
Common Parameters Considered
1 Earthquake Resistant RCC framed structure
2 Foundation depth considered 2.5m for buildings
3 Building Height - 9.0 metre
Sl No. CPWD BUILT-UP UNIT Rate per Amount
PAR 2021 DESCRIPTION AREA Sqm
Ref.

1.00.00 Non-Residential Building


1.01.00 Crematorium
Basic Building Rate based on PAR 2021 , including services as 200 Sqm. 39293 7,858,595
A mentioned in (Sheet : Bldg PAR)
1.3.4 Every 0.30 mt. deeper foundations over normal depth of 1.20 metre 120 Sqm. 800 96,000
B (on G.F. area only )

Total Cost of civil portion building ₹ 7,954,595


(A+B+C)
PAR per Sqm at present date(CPWD Cost Index 107) Total Amount (civil portion) ₹ 8,511,417

Notes:

1 Rates are considered as per CPWD Plinth Area Rates 2021 (PAR 2021).
2 No cost indices have been considered above PAR 2021, cost engineering may verify rates before further processing.
PLINTH AREA RATE CALCULATIONS FOR DIFFERENT CATEGORIES OF BUILDINGS

Specification as per of PAR 2021


S. No. as Description
Non Residential
per PAR Unit
(G+1)

1.0 RCC FRAMED STRUCTURE


( Specifications as per Annexure – I)

1.1 RCC Frame Structure upto 6 Storeys Sqm. 27090.0


1.1.1 Floor ht. 3.60m
1.1.2 Floor ht.3.0m

1.3 EXTRA FOR


1.3.1.1 Extra for every additional storey over six storeys upto twelve storeys
Sqm. 0.0
(For RCC Framed Structures only)

1.3.2 Every 0.3 mt. Additional height of floor above normal floor height Rs. 4440.0
1.3.5 of 3.35 mt./2.90
Making Strongermts.
foundations to take load of one additional floor at
Rs. 1600.0
a later date
1.3.8 Stronger Structural members to take heavy load above 500 kg per
Rs. 0.0
sqm upto 1000 kg per sqm

1.5 FIRE FIGHTING


1.5.1 With wet riser system Rs. 0.0

1.6 FIRE ALARM SYSTEM


1.6.1 Manual Fire Alarm System Rs.
1.6.2 Automatic Fire Alarm System Rs. 0.0
2.0 SERVICES
2.1 Internal Water Supply & Sanitary installations Rs. 0.00

2.2 External service connections


2.2.1 Electrical External service connections Rs. 1015.88
2.2.2 Civil External service connections Rs. 338.63

2.3 Internal electric installations Rs. 3386.25

2.4 EXTRA FOR


2.4.1 Power wiring & plugs Rs. 1083.60

2.4.2 Lightning Conductors Rs. 67.73

2.4.3 Telephone conduits Rs. 0.00

2.4.4 Third Party Quality assurance Rs. 270.90

Sub Total = 39292.98

39293

3.0 LIFTS
3.1 Passenger Lifts
3.1.2 Passenger Lifts (8 person) Rs. 0.00
3.1.4 Passenger Lifts (13 person) Rs. 0.00
3.1.8 Passenger Lift (Bed Lift 20 person) Rs.
3.2 Goods Lifts
Rs.
Lift Per Block Rs. 0.00

1.8.1 Stilt portion of a multi-storey up to floor height of 3.60 meter ( on


Sqm 0.0
stilt area only)
1.3.4 Every 0.30 mt. deeper foundations over normal depth of 1.20 metre
Sqm 800.0
(on G.F. area only )
1.3.6 R.C.C. Raft foundation(ground floor only ) Sqm 0.0
1.3.7 R.C.C. Pile foundation upto a depth of 15 mts
Sqm 0.0
(ground floor only )

Total 800.0