S. No Particulars Plinth Area (Sqm) Rate per Sqm (In Rs.) Amount (Rupees)
Civil Work
1.1 RCC framed Structure with floor height 3.6 M
217.39 25800 5608558.80
1.5 Every 0.30m deeper foundations over normal depth of 1.20m (on G.F
area only)depth -1.80m 217.39 =(200 x 0.60)/0.3 = 400.00 86954
1.6.1 Floor height upto 3.35 m including water proofing 0.00 31000 0
3 Water Tank
3.1 Provision for overhead water storage tanks (sintex or Equivalent)
including staging in built-up section Itrs 10000 150 1500000
10 SUB-STATION EQUIPMENT
10.1 Supplying, installation, testing and commissioning of 33 kV/0.433 kV
or 1 1 kV/0.433 k V substation equipments comprising HT panel, dry
type transformers, HT cable, bus trunking from transformer to LT
panel, LT panel, automatic power factor correction panel, active
harmonic filters, TVSS
(transient voltage suppression system), SPD (surge protection 63.00 9000 PerkVA 567000
system), essential panel, earthing, required inter-connections,
substation safety equipments including LT cabling from sub station
to the buildings fed by the sub station.
Computerization of Offices
12 Tentative 200000
14 STP/ETP PLANT
14.1 Supplying, installation, testing and commissioning of STP/ETP of
appropriate technology including civil works (except plant room),
tertiary treatment etc. for the building/ campus
Plant size upto 50000 LPD 20000 LPD 75000 Per Thousand Ltr 1500000
Sub Total - II 10488221
Total Part A ₹ 2,14,24,911
Executive Engineer
Jr. Engineer Assistant Executive Engineer
R&B Division -II Kargil