UP STANDARD DETAIL REFERENCE DRAWINGS

DETAIL OF HEAVY WELDING BOSSES FOR THREADED CONNECTIONS AE-036175

N
AWAY AWAY
CONSTRUCTION-NOTES AND DETAILS FOR ISOMETRIC PIPING
INSULATION DETAILS FOR HOT PIPING
AD-036627
AA-036911

SHOP MATERIALS INSULATION DETAILS FOR COLD PIPING AA-036913

INSTALLATION OF JACK SCREWS FOR FLANGED JOINTS AC-036630

TOWARD TOWARD PT N.B.


NOTES
NO DESCRIPTION (INS) STOCK CODE QTY
1. MATERIAL SHOWN WITH A BROKEN LINE AND SPOOLS LISTED IN THE SAUDI ARAMCO
DOWN
PIPE FABRICATION LIST ARE NOT TO BE FURNISHED BY THE VENDOR.

2. PIPING DETAILS SHALL BE CUT AT ALL POINTS MARKED F.W. (FIELD WELD).

1 PIPE , CS API 5L-B-PSL2 , SMLS , BE , 10 PPPCPVSMBESTD5F 54.2 M 3. EACH FABRICATED SECTION SHALL BE CLEARLY MARKED WITH ITS CODE NUMBER.

STD , B36.10M , FBE INT COATED 4. UNLESS OTHERWISE NOTED. (A) ALL DIMENSIONS ARE TO C OR FACE OF FLANGES.

(B) BOLT HOLES ON FLANGES STRADDLE C . (C) WELDING ELBOWS ARE LONG RADIUS.

5. FABRICATION SHALL BE IN ACCORDANCE WITH SAUDI ARAMCO SPECIFICATION 01-SAMSS-10.


FLANGES 6. GASKET ALLOWANCE

7. PIPING MATERIAL IS
2 WN FLG , CS A105N , CL150 , FF , STD , 10 PFWC1B15FFSTD5V 10
B16.5 , FBE INT COATED PIPE SIZE SCHEDULE SPECIFICATION

REFER MTO REFER MTO REFER MTO

FIELD MATERIALS

PT N.B.
8. WELDING STRESS RELIEF - YES NO
X
NO DESCRIPTION (INS) STOCK CODE QTY RADIOGRAPHY % 100% X-RAY SPOT X-RAY 01-SAMSS-10 SHOP FIELD

GASKETS 9. TESTING SHOP HYDROSTATIC TEST - YES


THE SHOP HYDROSTATIC TEST SHALL BE CARRIED OUT ON PIECES HAVING ALL ENDS
NO

FLANGED.

3 GASKET , SYNTHETIC W/ CENTERING RING , 10 PGGNSC20115BL02 5


FULL FACE , 1/16" (1.6 MM) THK , 10. ALL PIPING MATERIAL IS IN ACCORDANCE WITH SAUDI ARAMCO ENGINEERING SPECIFICATION
SAES-L-105 CLASS 1LE0U . ALL EXCEPTIONS ARE NOTED ON THE ISOMETRIC.

CL150 , B16.5 , B16.21 11. INSULATION SHOWN ON DRAWING


REFER BELOW TABLE
12. REFER TO HYDROSTATIC TEST DIAGRAM FOR TEST LIMIT AND PRESSURE.
13. FOR SMALL BORE LINES (UPTO 1-1/2" ) DIMENSIONS, ROUTING & SUPPORTING SHALL BE FIELD ADJUSTED.

BOLTS 14. ALL DIMENSIONS AND COORDINATES ARE IN MM. CONTRACTOR TO FIELD VERIFY ALL DIMENSIONS PRIOR TO FABRICATION OF THE SPOOL.
15. FOR INTERNAL LINED PIPE, LINING SHALL BE DONE AFTER SPOOL FABRICATION & COMPLETION OF ALL HOT WORKS.
16. TIE-IN POINTS CO-ORDINATES TO BE VERIFIED BY CONTRACTOR IN FIELD.

4 STUD BOLT (CONT) , CR-MO A193-B7 , W/ 2 7/8 PB1BLCSACS16002 60 17. PAINTING / COATING SHALL BE IN ACCORDANCE WITH SAES-H-001/002 AND PROJECT APPROVED COATING MAP.

FOR CONT. SEE SF HVY HEX NUTS , A194-2H , B1.1 ,


18. SEAL WELDING REQUIREMENT OF THREADED JOINTS SHALL BE AS PER CL.NO.9 OF SAES-L-110.
19. WELDS SHALL BE RADIOGRAPHED AS PER SAES-W-012 (FOR LINES WITH DESIGN CODE ASME B31.8/B31.4) &
SHT 027

THIS DRAWING AND THE INFORMATION CONTAINED HEREIN ARE THE SOLE PROPERTY OF SAUDI ARAMCO. NO REPRODUCTION IN FULL, OR IN PART, SHALL BE OBTAINED FROM THIS DRAWING WITHOUT THE WRITTEN CONSENT OF SAUDI ARAMCO.
AS PER SAES-W-011 (FOR LINES WITH DESIGN CODE ASME B31.3).
CERAMIC-FLUOROPOLYMER COATED , DIA 20. CONSTRUCTION OF PLANT PIPING SHALL BE IN ACCORDANCE WITH SAES-L-350.
E 30321432 (IMP) X LEN (MET) - 115 mm Length 21. ALL INTERFACE CONNECTIONS WITH OTHER PROJECT (WHEREVER APPLICABLE), CO-ORDINATES AND ELEVATIONS
SHALL BE VERIFIED BY CONTRACTOR IN FIELD.
N 30970900 22. INTERNAL FBE LINING CONTRACTOR TO VERIFY AND CONFIRM THE BREAK UP FLANGES PRIOR TO THE SPOOL FABRICATION

EL +99987 PIPE SUPPORTS


23. PLANT COORDINATE SYSTEM HAS BEEN FOLLOWED AS PART OF BI-10-00930.
HIGH POINT OF PLANT DATUM ELEVATION 100.000m WHICH EQUALS 2.05m ABOVE MEAN SEA LEVEL

S5 SPOOLS TO BE FABRICATED BY VENDOR


FLG2 5 GUIDE FOR BARE PIPE 10 GL01-10 5 NO.
MARK NO. SIZE
WEIGHT NO.
MARK NO. SIZE
WEIGHT

GL01-10 PIECES LBS PIECES LBS

PIECE MARKS
89
FLG2 85 86 87 88 89
60 S5
00
1 GL01-10
11 1
10"N.B. 89
8
88 S5
REST FLG2
1716 GL01-10
1
FLG2 GAS3 BLT4 72
82 87 SPOOLS TO BE FABRICATED BY SAUDI ARAMCO
S5 NO.
MARK NO. SIZE
NO.
MARK NO. SIZE

3000 FLG2
PIECES PIECES

63 GL01-10
00
1
REST 12 S5
00
0 86 GL01-10
FLG2 GAS3 BLT4 FLG2
60
00
3002 1
REST 12
00
0 10"N.B.

FLG2 GAS3 BLT4 3003 85


60 REFERENCE DRAWINGS
00
REST 12 DRAWING CONTROL SHEET FOR J.O. 10-00930-0002 RD-086148
00
0 PIPING PLAN RA-685466.001
FLG2 GAS3 BLT4
P&ID NA-518622.008
3005 FLG2 GAS3 BLT4 LINE DESIGNATION TABLE RD-912750
FOR CONT. SEE HYDROSTATIC TEST DIAGRAM RA-901147-001
SHT 025 PROJECT PIPING MATERIAL SPECIFICATION RE-685500
E 30321432 PIPE SUPPORT STANDARD RE-901041
N 30915712
EL +99987

REVISION VALIDATION

THIS REVISION NO. 00 IS COVERED, FOR ALL APPROVAL AND CERTIFICATION


REQUIREMENTS, PER SAEP-334, UNDER DRAWING COMPLETION CERTIFICATE NO:

10-00930-0002-001

Worley DESIGN CERTIFICATION

ENGG./DATE
(DESIGN AGENCY)
CERTIFIED BY/DATE
REVIEW FOR KEY DRAWINGS
REQUIRED
CONST. AGENCY/DATE
(SAUDI ARAMCO)
OPERATIONS/DATE BY/DATE
OTHER

RAM WAB MKH AMM


04/07/23 04/07/23 04/07/23 04/07/23

07 May 2023 REV.NO. DATE REVISION DESCRIPTION

00 04/07/23 ISSUED FOR CONSTRUCTION

JOB ORDER/EWO NO.


THIS REVISION IS NOT TO BE USED FOR
10-00930-0002
ISSUED FOR CONSTRUCTION
CONSTRUCTION UNTIL CERTIFIED AND DATED

SAUDI ARABIAN OIL COMPANY


DRAWING TYPE
ISO 10"-OW-5063-1LE0U ISO
EQUALIZATION TANKS
CHEMICAL DESIGN OPERATING TEST PRESS. TEST RADIOGRAPHY % INSULATION TRACING PAINTING STRESS LINE ID
CLEANING TEMP. PRESS. TEMP. PRESS. (PSIG) MEDIUM SHOP FIELD THK. TYPE SYS NO. TERMINAL NORTH
(DEG. F) (PSIG) (DEG. F) (MM) SAUDI ARABIA
(PSIG) RAS TANURA
PLANT NO. INDEX DRAWING NUMBER SHT. NO. REV. NO.

NO 150 262 120 49 NOTE-12 WATER NOTE-19 NOTE-19 0 mm NO NOTE-17 SYS-02 OW-5063
060 L RB-901085 026 00
Saudi Aramco 2825 ENG. (05/05)

RESTRICTED
SA-TR-799 SMART CADD-03