UP STANDARD DETAIL REFERENCE DRAWINGS

DETAIL OF HEAVY WELDING BOSSES FOR THREADED CONNECTIONS AE-036175

N
AWAY AWAY
CONSTRUCTION-NOTES AND DETAILS FOR ISOMETRIC PIPING
INSULATION DETAILS FOR HOT PIPING
AD-036627
AA-036911

SHOP MATERIALS INSULATION DETAILS FOR COLD PIPING AA-036913

INSTALLATION OF JACK SCREWS FOR FLANGED JOINTS AC-036630

TOWARD TOWARD PT N.B.


NOTES
NO DESCRIPTION (INS) STOCK CODE QTY
1. MATERIAL SHOWN WITH A BROKEN LINE AND SPOOLS LISTED IN THE SAUDI ARAMCO
DOWN
PIPE FABRICATION LIST ARE NOT TO BE FURNISHED BY THE VENDOR.

2. PIPING DETAILS SHALL BE CUT AT ALL POINTS MARKED F.W. (FIELD WELD).

1 PIPE , CS API 5L-B-PSL2 , SMLS , BE , 10 PPPCPVSMBESTD5F 32.3 M 3. EACH FABRICATED SECTION SHALL BE CLEARLY MARKED WITH ITS CODE NUMBER.

STD , B36.10M , FBE INT COATED 4. UNLESS OTHERWISE NOTED. (A) ALL DIMENSIONS ARE TO C OR FACE OF FLANGES.

(B) BOLT HOLES ON FLANGES STRADDLE C . (C) WELDING ELBOWS ARE LONG RADIUS.

5. FABRICATION SHALL BE IN ACCORDANCE WITH SAUDI ARAMCO SPECIFICATION 01-SAMSS-10.


FITTINGS 6. GASKET ALLOWANCE

7. PIPING MATERIAL IS
2 WELDOLET , CS A105N , STD , BE , HDR/BRN 10X2 PLWC1B00STDB20K 1
, SP-97 , FBE INT COATED PIPE SIZE SCHEDULE SPECIFICATION

REFER MTO REFER MTO REFER MTO

FLANGES
3 WN FLG , CS A105N , CL150 , FF , STD , 10 PFWC1B15FFSTD5V 6
B16.5 , FBE INT COATED
4 WN FLG , CS A105N , CL150 , FF , STD , 2 PFWC1B15FFSTD5V 1 8. WELDING STRESS RELIEF - YES NO
X
B16.5 , FBE INT COATED RADIOGRAPHY % 100% X-RAY SPOT X-RAY 01-SAMSS-10 SHOP FIELD

9. TESTING SHOP HYDROSTATIC TEST - YES NO


THE SHOP HYDROSTATIC TEST SHALL BE CARRIED OUT ON PIECES HAVING ALL ENDS
FLANGED.

FIELD MATERIALS 10. ALL PIPING MATERIAL IS IN ACCORDANCE WITH SAUDI ARAMCO ENGINEERING SPECIFICATION
SAES-L-105 CLASS 1LE0U . ALL EXCEPTIONS ARE NOTED ON THE ISOMETRIC.

REFER BELOW TABLE


PT N.B. 11. INSULATION SHOWN ON DRAWING
12. REFER TO HYDROSTATIC TEST DIAGRAM FOR TEST LIMIT AND PRESSURE.

NO DESCRIPTION (INS) STOCK CODE QTY 13. FOR SMALL BORE LINES (UPTO 1-1/2" ) DIMENSIONS, ROUTING & SUPPORTING SHALL BE FIELD ADJUSTED.
14. ALL DIMENSIONS AND COORDINATES ARE IN MM. CONTRACTOR TO FIELD VERIFY ALL DIMENSIONS PRIOR TO FABRICATION OF THE SPOOL.
15. FOR INTERNAL LINED PIPE, LINING SHALL BE DONE AFTER SPOOL FABRICATION & COMPLETION OF ALL HOT WORKS.

GASKETS 16. TIE-IN POINTS CO-ORDINATES TO BE VERIFIED BY CONTRACTOR IN FIELD.


17. PAINTING / COATING SHALL BE IN ACCORDANCE WITH SAES-H-001/002 AND PROJECT APPROVED COATING MAP.
18. SEAL WELDING REQUIREMENT OF THREADED JOINTS SHALL BE AS PER CL.NO.9 OF SAES-L-110.
5 GASKET , SYNTHETIC W/ CENTERING RING , 10 PGGNSC20115BL02 3 19. WELDS SHALL BE RADIOGRAPHED AS PER SAES-W-012 (FOR LINES WITH DESIGN CODE ASME B31.8/B31.4) &

THIS DRAWING AND THE INFORMATION CONTAINED HEREIN ARE THE SOLE PROPERTY OF SAUDI ARAMCO. NO REPRODUCTION IN FULL, OR IN PART, SHALL BE OBTAINED FROM THIS DRAWING WITHOUT THE WRITTEN CONSENT OF SAUDI ARAMCO.
AS PER SAES-W-011 (FOR LINES WITH DESIGN CODE ASME B31.3).

FOR CONT. SEE FULL FACE , 1/16" (1.6 MM) THK , 20. CONSTRUCTION OF PLANT PIPING SHALL BE IN ACCORDANCE WITH SAES-L-350.

SHT 025 CL150 , B16.5 , B16.21 21. ALL INTERFACE CONNECTIONS WITH OTHER PROJECT (WHEREVER APPLICABLE), CO-ORDINATES AND ELEVATIONS
SHALL BE VERIFIED BY CONTRACTOR IN FIELD.
22. INTERNAL FBE LINING CONTRACTOR TO VERIFY AND CONFIRM THE BREAK UP FLANGES PRIOR TO THE SPOOL FABRICATION

E 30321432 6 GASKET , SYNTHETIC W/ CENTERING RING , 2 PGGNSC20115BL02 2 23. PLANT COORDINATE SYSTEM HAS BEEN FOLLOWED AS PART OF BI-10-00930.

N 30855704 FULL FACE , 1/16" (1.6 MM) THK , HIGH POINT OF PLANT DATUM ELEVATION 100.000m WHICH EQUALS 2.05m ABOVE MEAN SEA LEVEL

CL150 , B16.5 , B16.21 SPOOLS TO BE FABRICATED BY VENDOR


EL +99987 NO. WEIGHT NO. WEIGHT
MARK NO. SIZE MARK NO. SIZE
PIECES LBS PIECES LBS

BOLTS
12
1 00
0 7 STUD BOLT (CONT) , CR-MO A193-B7 , W/ 2 7/8 PB1BLCSACS16002 36
60 SF HVY HEX NUTS , A194-2H , B1.1 ,
FLG3 00
CERAMIC-FLUOROPOLYMER COATED , DIA
30 FLG3 GAS5 BLT7 (IMP) X LEN (MET) - 115 mm Length
14
8 STUD BOLT (CONT) , CR-MO A193-B7 , W/ 2 5/8 PB1BLCSACS16002 8
SF HVY HEX NUTS , A194-2H , B1.1 ,
REST
12 CERAMIC-FLUOROPOLYMER COATED , DIA
1 00
0 S11 (IMP) X LEN (MET) - 80 mm Length
S11 FLG3 GAS5 BLT7
FLG3 60 SPOOLS TO BE FABRICATED BY SAUDI ARAMCO
00 GL01-10
GL01-10 VALVES / IN-LINE ITEMS NO.
MARK NO. SIZE
NO.
MARK NO. SIZE
PIECES PIECES
30
16 9 GATE VALVE , CS A216-WCB , CL150 , FF , 2 PVGC2S15FF8ABWV 1
REST
79 REST B16.5 , B16.10 DIMS , API 600, OS&Y ,
85 BB , B61/B62 BRONZE TRIM (LESS THAN
24 3000 16% ZINC) , INT FBE LND BODY , HW
78 1
10 BLIND FLG , CS A105N , CL150 , FF , 2 PFBC1B15FF0005V 1
541 S11 B16.5 , FBE INT COATED
FLG3 GL01-10
35 PIPE SUPPORTS
2 8 10"N.B.
237
10X2"N.B. 11 GUIDE FOR BARE PIPE 10 GL01-10 3
9 178 77 REFERENCE DRAWINGS
STEM WEST PIECE MARKS
DRAWING CONTROL SHEET FOR J.O. 10-00930-0002 RD-086148
77 78 79 PIPING PLAN RA-685466.001
10
FLG4 GAS6 BLT8 P&ID NA-518622.008
LINE DESIGNATION TABLE RD-912750
GAS6 BLT8
HYDROSTATIC TEST DIAGRAM RA-901147-001
PROJECT PIPING MATERIAL SPECIFICATION RE-685500
FOR CONT. SEE PIPE SUPPORT STANDARD RE-901041
SHT 023
E 30321432
N 30822817 FLG3 GAS5 BLT7
EL +99987

REVISION VALIDATION

THIS REVISION NO. 00 IS COVERED, FOR ALL APPROVAL AND CERTIFICATION


REQUIREMENTS, PER SAEP-334, UNDER DRAWING COMPLETION CERTIFICATE NO:

10-00930-0002-001

Worley DESIGN CERTIFICATION

ENGG./DATE
(DESIGN AGENCY)
CERTIFIED BY/DATE
REVIEW FOR KEY DRAWINGS
REQUIRED
CONST. AGENCY/DATE
(SAUDI ARAMCO)
OPERATIONS/DATE BY/DATE
OTHER

RAM WAB MKH AMM


04/07/23 04/07/23 04/07/23 04/07/23

07 May 2023 REV.NO. DATE REVISION DESCRIPTION

00 04/07/23 ISSUED FOR CONSTRUCTION

JOB ORDER/EWO NO.


THIS REVISION IS NOT TO BE USED FOR
10-00930-0002
ISSUED FOR CONSTRUCTION
CONSTRUCTION UNTIL CERTIFIED AND DATED

SAUDI ARABIAN OIL COMPANY


DRAWING TYPE
ISO 10"-OW-5063-1LE0U ISO
EQUALIZATION TANKS
CHEMICAL DESIGN OPERATING TEST PRESS. TEST RADIOGRAPHY % INSULATION TRACING PAINTING STRESS LINE ID
CLEANING TEMP. PRESS. TEMP. PRESS. (PSIG) MEDIUM SHOP FIELD THK. TYPE SYS NO. TERMINAL NORTH
(DEG. F) (PSIG) (DEG. F) (MM) SAUDI ARABIA
(PSIG) RAS TANURA
PLANT NO. INDEX DRAWING NUMBER SHT. NO. REV. NO.

NO 150 262 120 49 NOTE-12 WATER NOTE-19 NOTE-19 0 mm NO NOTE-17 SYS-02 OW-5063
060 L RB-901085 024 00
Saudi Aramco 2825 ENG. (05/05)

RESTRICTED