ITEM

ITEM DESCRIPTION UNIT NUMBER Plan (%)


NO.
1 GENERAL ITEM LS 1
2 SUPPLY OF TRANSMISSION PIPES KM 57.517
INSTALLATION OF TRANSMISSION PIPES KM 57.517
3 PIPE CIVIL WORK (EXCAVATION only) KM 57.517
PIPE WELDING KM 57.517
CONSTRUCTION OF 100 m3 GROUND RC
4 No 1
CIRCULAR BOOSTER RESERVIOR
CONSTRUCTION OF 1000 m3 GROUND RC
5 No 1
CIRCULAR SERVICE RESERVIOR
6 CONSTRUCTION OF GENERATOR HOUSE No 2
CONSTRUCTION OF BOOSTER STATION PUMP
7 No 1
HOUSE
8 CONSTRUCTION OF GUARD HOUSE No 3
CONSTRUCTION OF WATER WATER POINTS
9 No 25
POINTS
10 CONSTRUCTION OF CATTLE TROUGHS No 15
11 FENCEING WORK No 5
REHABILITATION OF EXISTING 100M3 RC
12 No 1
RESERVOIRS AT ELGOF
13 CONSTRUCTION OF OPERATORS DWELLING No 1
SUPPLY, INSTALLATION, TESTING AND
14 LS 1
COMMISSIONING OF ELECTROMECHANICAL
15 ACCESSES ROAD TO 1000M3 LS 1
16 CONSTRUCTION OF TOILET LS 1
AVERAGE STATUS
CURRENT
STATUS %
70.0%
43.1%
25.0%
53.1%
25.9%
98.0%

70.0%
48.0%
99.0%
66.7%
56.0%
13.3%
20.0%
0.0%

98.0%

0.0%

100.0%
15.0%
50.1%