2 Sharp Edges
5 Manual Handling
7 Housekeeping
1 Loading and Moving traffic Personnel harm Ensure the suitable 3 C H Effective and Site 1 C M OSHAD
unloading of communication between the continuous Engineer/ COP 2.0
Page No. 1 of 12
TASK RISK ASSESSMENT
Date: Performer Dept:
Brief Description
TASK DETAILS CIVIL
Location / Equipment
Tag ID
Name: Mr Saeed Mr Mujahid Mr Mahmood Review date: TRA No:
TRA TEAM Designation: HSEO QA/QC Project Engr
MEMEBERS Rev #: 00
Company: UltraMax UltraMax UltraMax
materials/ Falling objects Asset Damage supplier / delivery team and supervision to be Authorised PPE,
equipment using Tilting of site team. ensured always. Supervisor OSHAD
boom truck/ equipment Ensure the flagman and rigger COP 4.0
Flashing lights shall
mobile crane or for the unloading trailers, First Aid,
Overhead be placed suitably to
fork lift. The trailer must be barricaded OSHAD
Utilities warn drivers during COP 17.0
(Mobilization/ while offloading the
night Safety
De-mobilization materials..
All personnel will signage
of equipment
Lifting gear must be secured wear the Mandatory and
and materials)
with a safety latch PPE (Safety Helmet, Signals,
To avoid anyone to stand Safety Glasses, OSHAD
under the suspended load Coverall, and safety COP 21.0
shoes) along with PPE Permit to
The ground should be even
specific to their task. work
Utilities should be identified
systems,
Crane operations must be OSHAD
controlled with a certified COP 22.0
rigger Barricading
Lifting plan must be of Hazards
conducted and submitted.
Wind speed must be checked
Out riggers must be fully
extended
Outriggers must be placed on
an even hard surface
Support Pads must be
installed
Page No. 2 of 12
TASK RISK ASSESSMENT
Date: Performer Dept:
Brief Description
TASK DETAILS CIVIL
Location / Equipment
Tag ID
Name: Mr Saeed Mr Mujahid Mr Mahmood Review date: TRA No:
TRA TEAM Designation: HSEO QA/QC Project Engr
MEMEBERS Rev #: 00
Company: UltraMax UltraMax UltraMax
Sharp Edges Manual Handling. Personal Injury TBT will be conducted prior to 3 C M Effective and continuous Site 1 B L OSHAD
2 Cuts and bruises activity supervision to be ensured Engineer/ COP 2.0
Unskilled workers
always. Authorised PPE,
Poor PPEs. Adequate PPE required for
Supervisor OSHAD
the task will be used such as Ensure the first aid facility
Poor Training / Worker COP 4.0
Gloves, Goggles, Coveralls etc. on site First Aid,
Ensure the training about OSHAD
sharp object using. COP 21.0
Homemade tolls strictly OSHAD
COP 22.0
Page No. 3 of 12
TASK RISK ASSESSMENT
Date: Performer Dept:
Brief Description
TASK DETAILS CIVIL
Location / Equipment
Tag ID
Name: Mr Saeed Mr Mujahid Mr Mahmood Review date: TRA No:
TRA TEAM Designation: HSEO QA/QC Project Engr
MEMEBERS Rev #: 00
Company: UltraMax UltraMax UltraMax
prohibited. Barricading
Sharp edge tolls shall Keep in of Hazards,
the store at designated place
once the work of sharp tool
has been finished.
Ensure close supervision.
Ensure the exclusion zone
while using the sharp edge
materials or tools to stop the
unauthorized access into the
workplace.
3 Using of hand Broken tools Personnel harm T.B.T will be conducted before 2 B M First Aid box should Site 1 B L OSHAD
tools starting the task. be present with Engineer/ COP 2.0
Wrong tools for
Certified First Aiders Authorized Personal
the job Ensure the workers are
Supervisor Protective,
trained about the sharp edge Equipment,
tools. OSHAD
Tools will be inspected before, COP 4.0
after and whenever required. First Aid and
Medical
Tools will be placed or kept in
Emergency
proper manner after usage
Treatment
Usage of mandatory PPE will
be in place (hard hat, coverall,
eye goggles, safety shoes etc.)
Page No. 4 of 12
TASK RISK ASSESSMENT
Date: Performer Dept:
Brief Description
TASK DETAILS CIVIL
Location / Equipment
Tag ID
Name: Mr Saeed Mr Mujahid Mr Mahmood Review date: TRA No:
TRA TEAM Designation: HSEO QA/QC Project Engr
MEMEBERS Rev #: 00
Company: UltraMax UltraMax UltraMax
4 Using of • Untrained • Fire • Ensure the low voltage and 3 B M • Mandatory and Site 1 B L OSHAD
Power operator optional PPE’s shall Engineer/ COP 2.0
Personal harm inspection of mixer prior to
Tools be used at all times. Authorized PPE,
• Damaged
Property
use for mixing the cement and
• Continuous Supervisor OSHAD
equipment sand for tile work.
damage monitoring is COP 4.0
• Poor Electrocution
• Toll box meeting is to be required First Aid,
housekeeping conducted prior to activity OSHAD
COP 17.0
• Electrical hazard • Equipment must be inspected
Safety
and colour coded.
Noise signage and
Flying Particles • Only trained personnel to be Signals,
allowed to operate power OSHAD
Entaglment
tools COP 21.0
Permit to
Damaged tools must be
work
replaced systems,
All powered tools must be OSHAD
double insulated COP 22.0
Barricading
• Face Shield must be worn
of Hazards,
Ear Plugs must be used OSHAD
RPM (Round Per Minute of COP 28.0
the disc must be equal or Hot Work
Operations
more than the machine.
Guards must be provided and
Page No. 5 of 12
TASK RISK ASSESSMENT
Date: Performer Dept:
Brief Description
TASK DETAILS CIVIL
Location / Equipment
Tag ID
Name: Mr Saeed Mr Mujahid Mr Mahmood Review date: TRA No:
TRA TEAM Designation: HSEO QA/QC Project Engr
MEMEBERS Rev #: 00
Company: UltraMax UltraMax UltraMax
Page No. 7 of 12
TASK RISK ASSESSMENT
Date: Performer Dept:
Brief Description
TASK DETAILS CIVIL
Location / Equipment
Tag ID
Name: Mr Saeed Mr Mujahid Mr Mahmood Review date: TRA No:
TRA TEAM Designation: HSEO QA/QC Project Engr
MEMEBERS Rev #: 00
Company: UltraMax UltraMax UltraMax
Page No. 9 of 12
TASK RISK ASSESSMENT
Date: Performer Dept:
Brief Description
TASK DETAILS CIVIL
Location / Equipment
Tag ID
Name: Mr Saeed Mr Mujahid Mr Mahmood Review date: TRA No:
TRA TEAM Designation: HSEO QA/QC Project Engr
MEMEBERS Rev #: 00
Company: UltraMax UltraMax UltraMax
Page No. 10 of 12
TASK RISK ASSESSMENT
Date: Performer Dept:
Brief Description
TASK DETAILS CIVIL
Location / Equipment
Tag ID
Name: Mr Saeed Mr Mujahid Mr Mahmood Review date: TRA No:
TRA TEAM Designation: HSEO QA/QC Project Engr
MEMEBERS Rev #: 00
Company: UltraMax UltraMax UltraMax
Page No. 11 of 12
TASK RISK ASSESSMENT
Date: Performer Dept:
Brief Description
TASK DETAILS CIVIL
Location / Equipment
Tag ID
Name: Mr Saeed Mr Mujahid Mr Mahmood Review date: TRA No:
TRA TEAM Designation: HSEO QA/QC Project Engr
MEMEBERS Rev #: 00
Company: UltraMax UltraMax UltraMax
Sign:
Sign: Sign:
Page No. 12 of 12