You are on page 1of 7

Document No:

SKSA- JSA-23 – 171-001


Ras Tanura Refinery - INSTALL DIESEL PRODUCT Rev No:
00
WATER REMOVAL FACILITY AT RTR
Date:
05/10/2023
JOB SAFETY Plant No: BI No:
TASK: 3D LASER SCANNING & MODELLING 051 10-13173
ANALYSIS

CLIENT: CONTRACTOR:
SAUDI ARAMCO SURTECH
PROJECT: ADDRESS:
INSTALL DIESEL PRODUCT WATER REMOVAL FACILITY AT RTR KHOBAR, KSA
LOCATION: AREA IN-CHARGE:
Ras Tanura Refinery
SURTECH SAPMT SAPMT ARAMCO ARAMCO
Prepared by: Reviewed by: Reviewed by: Reviewed by: Approved by: Approved by: Approved by:

Signature: Signature: Signature: Signature: Signature: Signature: Signature:

HSE COORDINATOR HSE MANAGER PROJECT MANAGER SAPMT Safety PROJECT SGPD OPERATION
HUSSAIN RAFI GULZAR KARTHIKEYAN ENGINEER (SAFETY) AND FIELD
UDDIN AHMED GANESH
SERVICES
Date: 03/10/2023 Date:03/10/2023 Date:05/10/2023 Date: Date: Date: Date:

DOCUMENT VERSION HISTORY

Revision Number Revision Date Revision Description Revised By


Document No:
SKSA- JSA-23 – 171-001
Ras Tanura Refinery - INSTALL DIESEL PRODUCT Rev No:
00
WATER REMOVAL FACILITY AT RTR
Date:
05/10/2023
JOB SAFETY Plant No: BI No:
TASK: 3D LASER SCANNING & MODELLING 051 10-13173
ANALYSIS

HAZARDS IN EACH
STEP RESIDUAL
SEQUENCE OF HAZARD HAZARD CONTROLS (REQUIRED TO
S.no (WHAT COULD INJURY, ACTION BY RISK
BASIC STEPS CATEGORIES MINIMIZE/HAZARD)
LOSS, INTERUPTION, OR RATING
POLLUTION)
Equipment
1.1.1. Wear Personal Protective Equipment -
Operator, WPR
FRC, hard hats, safety glass, hand gloves.
& supervisor
1.1.2. Only drivers having a valid Saudi
1.1. Damages to equipment Arabia license are permitted to operate / drive
and properties.
M
transport equipment. L
1.1.3. Observe post speed limit when
entering Plant area.
1.1.4. Secure a work permit as required.
1.2.1. Activity Supervisor shall conduct tool
Equipment
Mobilize box talk every day before start work
1.2. Falling of equipment Operator, WPR
Equipment and describing team activities and precautions to
1 & supervisor L
Tools to Be Used M be taken
on Site 1.2.2. Obey and follow signs and warning
posted on the terminal premises.

1.3.1.The scanning equipment shall have


1.3. Ignition source
valid inspection tag Equipment
M 1.3.2.Adequate fire extinguishers shall be Operator, WPR L
available in the work site & supervisor

Equipment
1.4.1. Only trained personnel shall be
1.4. Electrical shock M permitted to work and use equipment.
Operator, WPR L
& supervisor

1|Page
Document No:
SKSA- JSA-23 – 171-001
Ras Tanura Refinery - INSTALL DIESEL PRODUCT Rev No:
00
WATER REMOVAL FACILITY AT RTR
Date:
05/10/2023
JOB SAFETY Plant No: BI No:
TASK: 3D LASER SCANNING & MODELLING 051 10-13173
ANALYSIS

2.1.1 Accompany plant operator while placing the


targets to identify hot surfaces and potential
trip/fall spots.
2.1 Hot Surfaces, trip/fall Equipment Operator,
M 2.1.2 Keep safe distance from heat surface to
WPR & supervisor
L
avoid accident.
2.1.3, Use proper gloves/PPE.

Surface Preparation & 2.2.1 Safe work practices to reduce worker


2 Placing paper targets exposure to heat.
2.2.2 Training employees to recognize and
prevent from heat.
Equipment Operator,
2.2 Heat exhaustion M 2.2.3. Conduct daily tool box meetings WPR & supervisor
L
2.2.4 Drink Water every 20 mins to avoid
dehydration
2.2.5 Take Rest in Car/ shaded area if exhausted
by heat

3.1.1 Hot Work Permit to be issued


Scanning with Leica
3.1.2 Battery replacement should be done at a safe Equipment Operator,
RTC 360 3D laser L
3.1 Use of 3D Laser area like control room, rest shelter or car parking WPR & supervisor
3 scanning and M
Scanning Machine
surveying with Total 3.1.3 Fence off with barricades/ warning tapes
Station minimum 15 m apart from the scanner axis, having

2|Page
Document No:
SKSA- JSA-23 – 171-001
Ras Tanura Refinery - INSTALL DIESEL PRODUCT Rev No:
00
WATER REMOVAL FACILITY AT RTR
Date:
05/10/2023
JOB SAFETY Plant No: BI No:
TASK: 3D LASER SCANNING & MODELLING 051 10-13173
ANALYSIS

warning stickers on them, to prevent other


workers from entering area with Targets fixed.

3.2.1 Only trained personnel shall be permitted to Equipment Operator,


3.2 Untrained Person M L
work and use equipment WPR & supervisor

M 3.3.1 Check the equipment condition and secure L


3.3 Non-Availability of Equipment Operator,
the area & equipment properly, until we obtain the
Permit WPR & supervisor
permit
M L
3.4.1 Periodic checkup will be done to check the Equipment Operator,
3.4 Faulty Equipment
equipment is in good condition. WPR & supervisor

M L
3.5.1 A standby battery will be there to avoid the Equipment Operator,
3.5 Failure of battery
battery failure WPR & supervisor

4.1.1. Protect the batteries from mechanical


4.1 Fire & chances of injury
influences and high ambient temperatures.
Equipment Operator,
4.1.2 Do not drop or immerse batteries
WPR & supervisor
4 Exposure of batteries M 4.1.3 Use proper PPEs L
4.1.4 Handle batteries with care
4.1.5 Make sure the batteries are in good
condition

3|Page
Document No:
SKSA- JSA-23 – 171-001
Ras Tanura Refinery - INSTALL DIESEL PRODUCT Rev No:
00
WATER REMOVAL FACILITY AT RTR
Date:
05/10/2023
JOB SAFETY Plant No: BI No:
TASK: 3D LASER SCANNING & MODELLING 051 10-13173
ANALYSIS

5.1.1 Remove all unnecessary materials from


the working area and maintain good
housekeeping during and after completion of the
5.1 Personnel injury by foreign work Equipment Operator,
5 Housekeeping M L
objects WPR & supervisor
5.1.2 Use proper PPEs especially the hand
protection such as gloves

6.1.1 Properly secure all equipment and


6.1 May causes last minute materials.
Demobilized and
injury, damages to Equipment Operator,
6 Clearing of The Area M 6.1.2 Work in a safe and organized way. L
equipment/material and exiting WPR & supervisor
Prior to Hand Over 6.1.3 All left over waste must be dump in
facilities.
designated area.

SAFETY EQUIPMENT/SYSTEM REQUIRED TO DO JOB


PERSONAL PROTECTIVE
EQUIPMENT FIRE PREVENTION AND FIRE FIGHTING BARRIGADE AND SIGNS EQUIPMENT TRAINING
Protecting clothing
Safety shoes
Hard Hat
N/A N/A N/A Safety induction
Safety Glass
Hand gloves
Dust Mask
4|Page
Document No:
SKSA- JSA-23 – 171-001
Ras Tanura Refinery - INSTALL DIESEL PRODUCT Rev No:
00
WATER REMOVAL FACILITY AT RTR
Date:
05/10/2023
JOB SAFETY Plant No: BI No:
TASK: 3D LASER SCANNING & MODELLING 051 10-13173
ANALYSIS

References:
· Heat Stress management Plan (HSMP)
· G.I. 2.100 Work Permit System
· G.I.2.709 Use of Portable Gas Monitors
· GI 6.007 Reporting of Contractor on Job
Injuries/Occupational Illnesses
· Safety Hand book
· SA CSM- Saudi Aramco Construction
Safety Manual
· QSBP DOIM Volume X52.1 Safety.
· SMS 3.03 Per-Job Safety Meeting
· SMS 6.01 Hot Work Permit
· SMS 6.11 Job Safety Analysis
· SMS 6.14 Personnel Protective
Equipment (PPE)
· Scope of work - 3D Scanning

Emergency Contact number:

1. Rescue - 997
2. Road security - 996
3. Civil security office -999
4. Traffic - 993
5. Firefighting-
998
6. Project Engineer (Irfan 0507749697)
5|Page
Document No:
SKSA- JSA-23 – 171-001
Ras Tanura Refinery - INSTALL DIESEL PRODUCT Rev No:
00
WATER REMOVAL FACILITY AT RTR
Date:
05/10/2023
JOB SAFETY Plant No: BI No:
TASK: 3D LASER SCANNING & MODELLING 051 10-13173
ANALYSIS

6|Page