Professional Documents
Culture Documents
ANNEX 1
Schematic Diagram of
_________________________________Subproject
Qs 0.118 LPS
SPRING BOX
11 (elev = 750 m) (PUROK /SITIO__ 1
710 m.
j
9 F6
i 10 (elev = 730 m)
100 m. HH = 12
RESERVOIR
(elev = 735 m) 38
735 60 m.
h RH=.73
6 (elev = 733 m)
733
25 f 31
320 m. 240 m.
e
(elev = 709 m) 7 (elev = 710 m) RH=6.84 25
HH = 6 8 31 HH = 6 d
F5 g 200 m. F4 (elev = 720 m) 4 20 m. 5 F3
F3
720 (elev = 719 m)
HH = 10
(PUROK/SITIO____ 2
D=31
c 1,200 m.
19
RH=3.57 10 m. 705
(elev = 704 m) 2 b 3 F2
704 (elev = 703.5 m)
Preparation of schematic diagram as basis for pipeline design: HH = 6
Steps:
1. Locate tapstand and name it F1…n starting from farthest
to the reservoir and or water source.
2. Determine the number of nodes and name it in numbers a 500 m.
starting from farthest to the reservoir and or water source. D=31
3. Determine the number of sections and name it in letters
starting from farthest to the reservoir and or water source. (PUROK/SITIO 3
4. Indicate the number of HH per tapstand, the elevation of
the nodes, the length of the sections from survey results. HH = 10
5. Design for the pipe diameter of the sections (see pipeline analysis) 1 (elev = 700 m)
and indicate final pipe sizes in the schematic diagram. 700
F1
RH-1.2m
Rhwhole system=12.88m
KALAHI-CIDSS
Planning and Design WS
Schematic Diagram/Project Area Map
ANNEX 1
Prepare a map showing the area to be served and the location of the source(s) of water. It should be drawn to a
convenient scale or with measurements of distance between important structures along roads and pathways.
Include elevation. Indicate houses, schools, churches, markets, existing water systems, public faucets, reservoir
and other important land features.
Legend
House
School
Church
Public faucet
Existing pipeline
Proposed pipeline
R Reservoir
Gate valve
Check Valve
Reducer
Clinic
Contours
º123 Elevations
S Spring Box
KALAHI-CIDSS
Detailed Estimates
ANNEX 1a
FORMAT OF DETAILED COST ESTIMATES
The presentation of the materials, labor and equipment in details is helpful when implementing the subproject by community force
account.
ITEM RESERVOIR ( 8 cu.m. )
A. MATERIALS
1) Computation of Quantities and Costing
Particular Compu Material Quantity Unit TOTAL
Description Specs. Factor ted Compu- Say Unit Cost Cost
Volume ted (P) (P)
Concrete Class "A" (1:2:4) 3.26 cu.m
Plaster (1:2) 0.3 cu.m
Portland cement 40 kg. 38 bag 140.00 5,320.00
Sand 0.5 2.13 cu.m 250.00 532.50
Gravel 1 3.3 cu.m 350.00 1,155.00
Sahara compound D.C. 35 pack 22.00 770.00
RSB 10 mm x 6 m D.C. 41 pc. 70.00 2,870.00
12 mm x 6 m D.C. 23 pc. 77.00 1,771.00
G.I. wire Gauge # 16 D.C. 3 kg. 43.00 129.00
Marine plywood 1/4" x 4' x 8' D.C. 18 sheet 375.00 6,750.00
Rough lumber 2" x 2" x 8' D.C. 50 pc. 53.00 2,650.00
Common nails #4 D.C. 25 kg. 30.00 750.00
# 1-1/2 D.C. 3 kg. 35.00 105.00
TOTAL 22,802.50
B. LABOUR COST
Productivity rate ( Excavation ) 1.6 cu.m./m-day
Productivity rate ( Concrete works ) 0.14 cu.m./m-day
Particular Quantity Gang Activity Duration Rate Total
Description Manpower Required Output Compu- Say per Day Labour
ted Cost
Excavation 3.76
Supervisor 1 12.8 0.29375 1 250.00 250.00
Laborer 8 1 150.00 1,200.00
Form works
Supervisor 1 6 250.00 1,500.00
Carpenter 2 6 225.00 2,700.00
Laborer 8 6 150.00 7,200.00
Steel works
Supervisor 1 3 250.00 750.00
Steelperson 2 3 225.00 1,350.00
Laborer 8 3 150.00 3,600.00
Concrete works 3.26
Supervisor 1 1.4 2.328571429 3 250.00 750.00
Mason 2 3 225.00 1,350.00
Laborer 8 3 150.00 3,600.00
TOTAL 13 24,250.00
KALAHI-CIDSS PROJECT 3 of 7
Detailed Estimates
A. MATERIALS
1) Computation of Quantities and Costing
Particular Compu Material Quantity Unit TOTAL
Description Specs. Factor ted Compu- Say Unit Cost Cost
Volume ted (P) (P)
Concrete Class "A" (1:2:4) 0.224
Portland cement 40 kg. 9 2.016 2.5 bag 140.00 350.00
Sand 0.5 0.112 0.15 cu.m 250.00 37.50
Gravel 1 0.224 0.25 cu.m 350.00 87.50
Sahara compund D.C. 2 pack 22.00 44.00
RSB 10 mm x 6 m D.C. 6 pc. 70.00 420.00
G.I. Tie wire Gauge # 16 D.C. 0.5 kg. 43.00 21.50
Forms Re-use from reservoir construction
Common nail Re-use from reservoir construction
TOTAL 960.50
B. LABOUR COST
Particular Quantity Gang Activity Duration Rate Total
Description Manpower Required Output Compu- Say per Day Labour
ted Cost
Form works
Supervisor 1 1 250.00 250.00
Carpenter 1 1 225.00 225.00
Laborer 4 1 150.00 600.00
Steel works
Supervisor 1 1 250.00 250.00
Steelperson 1 1 225.00 225.00
Laborer 4 1 150.00 600.00
Concrete works
Supervisor 1 2 250.00 500.00
Mason 1 2 225.00 450.00
Laborer 4 2 150.00 1,200.00
Removal of old pipe,
installation of new
Supervisor 1 1 250.00 250.00
Mason 1 1 225.00 225.00
Laborer 4 1 150.00 600.00
Ditching
Supervisor 1 1 250.00 250.00
Laborer 4 1 150.00 600.00
TOTAL 6 6,225.00
KALAHI-CIDSS PROJECT 4 of 7
Detailed Estimates
ITEM PIPELINE
A. MATERIALS
1) Computation of Quantities and Costing
Particular Pipeline Section Quantity Unit Total
Unit Section/ Length Compu- Cost Cost
Description Specs. Location ted Say
(m) (P) (P)
Pipes and fittings
G.I. Pipe, sched. 40 31 mm x 6 m pc. a 500 83.33 84 550.00 46,200.00
G.I. Union patente 31 mm pc. a 7.33 8 88.00 704.00
G.I. Coupling 31 mm pc. a 75 32.00 2,400.00
G.I. Tee 31 x 31 mm pc. a 1 42.00 42.00
G.I. Reducer Bushing 31 x 13 mm pc. a 1 30.00 30.00
G.I. Plug 31 mm pc. a 1 20.00 20.00
G.I. Pipe, sched. 40 13 mm x 6 m pc. a 0.5 184.00 92.00
G.I. Coupling 13 mm pc. a 1 12.00 12.00
G.I. Elbow, 90 degrees 13 mm pc. a 2 15.00 30.00
Brass Gate valve 13 mm pc. a 1 65.00 65.00
KALAHI-CIDSS PROJECT 5 of 7
Detailed Estimates
KALAHI-CIDSS PROJECT 6 of 7
Detailed Estimates
B. LABOUR COST
Particular Quantity Gang Activity Duration Rate Total
Description Manpower Required Output Compu- Say per Day Labour
ted Cost
Pipe Threading 559.5
Supervisor 1 200 2.7975 3 250.00 750.00
Plumber 2 3 225.00 1,350.00
Laborer 8 3 150.00 3,600.00
Excavation, Laying
& Installation and
Backfilling 559.5
Supervisor 1 60 9.325 10 250.00 2,500.00
Plumber 2 10 225.00 4,500.00
Laborer 8 10 150.00 12,000.00
TOTAL 13 24,700.00
KALAHI-CIDSS PROJECT 7 of 7
Detailed Estimates
A. MATERIALS
1) Computation of Quantities and Costing
Particular Compu Material Quantity Unit TOTAL
Description Specs. Factor ted Compu- Say Unit Cost Cost
Volume ted (P) (P)
Concrete Class "A" (1:2:4) 0.48
Portland cement 40 kg. D.C. 5 bag 140.00 700.00
Sand D.C. 0.25 cu.m. 250.00 62.50
Gravel D.C. 0.5 cu.m. 350.00 175.00
G.I. Wire Gauge # 4 D.C. 1 roll 1,500.00 1,500.00
Gauge # 16 D.C. 2 kg. 43.00 86.00
RSB 12 mm x 6 m D.C. 10 pc. 77.00 770.00
16 mm x 6 m D.C. 8 pc. 103.00 824.00
Steel angle bar 1-1/2 x 1-1/2 D.C. 2 pc. 250.00 500.00
x 1/8 x 6 m
TOTAL 4,617.50
B. LABOUR COST
Particular Quantity Gang Activity Duration Rate Total
Description Manpower Required Output Compu- Say per Day Labour
ted Cost
(suspended)
Form & steel works
Supervisor 1 1 250.00 250.00
Laborer 6 1 150.00 900.00
Concrete casting
Supervisor 1 1 250.00 250.00
Laborer 6 1 150.00 900.00
Installation
Supervisor 1 3 250.00 750.00
Laborer 6 3 150.00 2,700.00
Instn. (submerged)
Supervisor 1 1 250.00 250.00
Laborer 6 1 150.00 900.00
TOTAL 6 6,900.00
KALAHI-CIDSS PROJECT 8 of 7
Detailed Estimates
A. MATERIALS
1) Computation of Quantities and Costing
Particular Compu Material Quantity Unit TOTAL
Description Specs. Factor ted Compu- Say Unit Cost Cost
Volume ted (P) (P)
Concrete Class "B" (1:2.5:5) 1.218
Portland cement 40 kg. 7.5 9.135 9.5 bag 140.00 1,330.00
Sand 0.5 0.609 0.7 cu.m. 250.00 175.00
Gravel 1 1.218 1.3 cu.m. 350.00 455.00
RSB 10 mm x 6 m D.C. 15 pc. 70.00 1,050.00
G.I. wire Gauge # 16 D.C. 1.5 kg. 43.00 64.50
Forms Re-use from reservoir construction
Common nails Re-use from reservoir construction
TOTAL 3,074.50
B. LABOUR COST
Particular Quantity Gang Activity Duration Rate Total
Description Manpower Required Output Compu- Say per Day Labour
ted Cost
Concrete 1.218
Supervisor 1 1.5 0.812 1 250.00 250.00
Mason 1 1 225.00 225.00
Laborer 4 1 150.00 600.00
Form, Steelwork,
Excavation
Supervisor 1 3 250.00 750.00
Carpenter 1 3 225.00 675.00
Laborer 4 3 150.00 1,800.00
TOTAL 4 4,300.00
KALAHI-CIDSS PROJECT 9 of 7
IMPLEMENTATION SCHEDULE WS
Noted:
Approved by: _____________________________ _____________________
BSPMC Chairperson Deputy Area Coordinator Regional Infrastructure Engineer
Note: Attach Material Records Sheet if physical accomplishment lags behind financial disbursements.
ANNEX 1
Design criteria
The pipeline must be designed to handle the maximum hour demand or Peak Flow (PF)=2.5ADD of the area to be served
Minimun pressure at the remotest end of the system should be 3.0 meters (Approx. 4.26 psi) and 7.0 meters at the
mainline
Maximum Velocity of flow in the pipes:
a. Main pipes… 3.0 meters per second
b. Distribution pipes… 1.5 meters per second
Water flow per tapstand ranges from 0.125 lps to 0.225 lps
Column Description:
Column Description
a Pipe section under consideration
b-c Node section under consideration
d Length of pipe section under consideration (meter)
e Number of household served
f Computed Peak Flow (liter per second)
g Difference in elevation between nodes under consideration (meter)
h Computed Pipe Diameter (mm), using the Darcy Weisbach Formula
i Nominal Diameter available in the market (mm)
j Headloss per 100 meters (refer to table 9.1 or 9.2)
k Actual Headloss
Formula:
Column f:
Where:
PF = Peak flow.
GRF = Growth rate factor (1+GR)^life span
N = Total number of household served by the pipe section.
PCWC = Per capita water consumption.
Column h:
HF = (8)(f)(L)(Q)^2/D^5(g)(pi)^2
D^5 =(8)(f)(L)(Q)^2/HF(g)(pi)^2
Where:
Simplifying:
Column j:
Column k:
The total headloss is less than the elevation head and therefore accept adjusted size but there are still critical nodes
Pipeline Section Household Peak Node Pipe Pipe Headloss Actual Hydraulic
Section Node Length Served Flow Elev. Diameter Diameter per Headloss Gradeline Available Total
from to Difference Option 100 m. Pipe Point Ground Head per Residual
(m) (no.) (lps) (m) (mm) (mm) (m) (m) Elevation Elevation Elevation section Head
a b c d e f g h i j k masl masl masl
a 1 2 500 10 ### 4 #VALUE! 31 0.4525 2.2625 700.00 701.74 699.50 1.7375 12.879
c 2 4 1200 16 ### 16 #VALUE! 31 1.036 12.432 704.00 707.57 708.00 3.568 11.1415
e 4 6 240 26 ### 13 #VALUE! 31 2.5655 6.1572 720.00 726.84 720.00 6.8428 7.5735
h 6 9 60 38 ### 2 #VALUE! 38 2.1155 1.2693 733.00 733.73 733.00 0.7307 0.7307
9 Reservoir 735.00 735.00 732.00 0 0
740.00
Reservoir
730.00
720.00
710.00
P ip e Elevatio n masl Hyd rau lic Grad elin e P o in t Elevatio n masl
700.00
Gro u n d Elevatio n masl
690.00 F1
680.00
1 2 3 4 5
Contract I.D. :
Furnishing Labor, Materials and Equipment
Project Name: Rental for the CONSTRUCTION/
REHABILITATION/ IMPROVEMENT of
Agumaymayan Water Supply System at Brgy.
Agumaymayan, Boac, Marinduque
no
of CALENDAR DAYS
Item No. DESCRIPTION wt % day 9 18 27 39
s
###
#########
######
######
######
######
######
### #########
######
I (a) #REF! #REF! 20
0 0 0 0 0
II (b) Mobilization / Demobilization 1.26% 5
0 0 0 0
III (c ) Project Billboard/ Signboard 0.51% 4
###
IV (d) #REF! #REF! 1
0 0 0 0 0
V(e) Excavation Works 2.95% 5
Quarterly Accomplishment #REF! #REF! #REF! #REF!
100%
Cumulative Quarterly Accomplishment #REF! #REF! #REF! #REF!
Quarterly Cash Flow 22,481.18 19,683.52 421,846.86 535,152.00
Cumulative Quarterly Cashflow 22,481.18 42,164.70 464,011.56 999,163.56
Contract I.D. :
Furnishing Labor, Materials and Equipment
Project Name: Rental for the CONSTRUCTION/
REHABILITATION/ IMPROVEMENT of
Agumaymayan Water Supply System at Brgy.
Agumaymayan, Boac, Marinduque
P E R T C P M
Business Name : SKYSCRAPER CONSTRUCTION AND ENGINEERING SERVICES
Business Address: Brgy. 1, Buenavista, Marinduque
no
of CALENDAR DAYS
Item No. DESCRIPTION wt % day 9 18 27 39
s
I (a) #REF! #REF! 20
GENERAL REQUIREMENTS / MOBILIZATION and DEMOBILIZATION
II (b) Mobilization / Demobilization 1.26% 5
Furnishing Labor, Materials and Equipment Rental for the CONSTRUCTION/ REHABILITATION/ IMPROVEMENT of Agumaymayan Water Supply Sy
Project Name:
Agumaymayan, Boac, Marinduque
Item no of CALENDAR
DESCRIPTION wt %
No. days 14 28
#########
Mobilization / Demobilization 1.26% 6
0
Project Billboard/ Signboard 0.51% 1
0 0 0 0 0 0 0
Excavation Works 2.95% 7
0 0 0 0 0 0 0 0 0 0 0 0 0
Concrete Works 20.40% 29
0 0 0 0 0 0
Formworks 4.25% 6
Furnishing Labor, Materials and Equipment Rental for the CONSTRUCTION/ REHABILITATION/ IMPROVEMENT of Agumaymayan Water Supply Sy
Project Name:
Agumaymayan, Boac, Marinduque
P E R T C P M
Business Name : SKYSCRAPER CONSTRUCTION AND ENGINEERING SERVICES
Business Address: Brgy. 1, Buenavista, Marinduque
Item no of CALENDAR
DESCRIPTION wt %
No. days
14 28
(a) Mobilization / Demobilization 1.26% 6 GENERAL REQUIREMENTS / MOBILIZATION and DEMOBILIZATION
( e) Formworks 4.25% 6
DELIVERY OF MATERIALS
( f) Pipelines & Fittings 70.63% 12
Furnishing Labor, Materials and Equipment Rental for the CONSTRUCTION/ REHABILITATION/ IMPROVEMENT of Agumaymayan Water Supply Sy
Project Name:
Brgy. Agumaymayan, Boac, Marinduque
Item CALENDAR
DESCRIPTION
No.
14 28
1 Minor Tools
Furnishing Labor, Materials and Equipment Rental for the CONSTRUCTION/ REHABILITATION/ IMPROVEMENT of Agumaymayan Water Supply
Project Name:
System at Brgy. Agumaymayan, Boac, Marinduque
MANPOWER SCHEDULE
Business Name : SKYSCRAPER CONSTRUCTION AND ENGINEERING SERVICES
Business Address: Brgy. 1, Buenavista, Marinduque
Item CALENDAR
DESCRIPTION
No. 14 28
###
1 PROJECT MANAGER
###
2 PROJECT ENGINEER
###
3 MATERIAL ENGINEER
4 PROJECT SUPERVISOR
###
5 FOREMAN
###
6 SKILLED
### ###
7 UNSKILLED
CALENDAR DAYS
28 42 55
0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0
0 0 0 0 0 0 0 0 0 0 0 0
C P M
CALENDAR DAYS
28 42 55
d f
29CD 12CD
DELIVERY OF MATERIALS
ATION SCHEDULE
CALENDAR DAYS
28 42 55
EMENT of Agumaymayan Water Supply
SCHEDULE
CALENDAR DAYS
28 42 55
PROGRAM OF WORKS
Furnishing Labor, Materials and Equipment Rental for the CONSTRUCTION/ REHABILITATION/
Project Title
IMPROVEMENT of Agumaymayan Water Supply System at Brgy. Agumaymayan, Boac, Marinduque
SUMMARY OF ESTIMATES
Item No. DESCRIPTION AMOUNT
Summary of Work
Formworks 42,511.74
999,163.56
Total of Amounts in Words
NINE HUNDRED NINETY-NINE THOUSAND ONE HUNDRED SIXTY-THREE PESOS AND 56/100
Equipment Rental
Various Tools and Equipment 10,000.00 10,000.00
sub-total 10,000.00
Direct Labor
Foreman 1.00 day 1.00 500.00 500.00
Skilled 1.00 day 1.00 450.00 450.00
Unskilled 1.00 day 2.00 400.00 800.00
sub-total 1,750.00
Equipment Rental
Minor Tools (10% of Labor Cost) 175.00
sub-total 175.00
Materials
4'x8' Tarpaulin 32.00 sq.ft 25.00 800.00
8pcs-2"x2"x12' cocolumber 32.00 bd.ft 35.00 1,120.00
CW nails (assorted) 2.00 kg 100.00 200.00
sub-total 2,120.00
Direct Labor
Project Supervisor 5.00 days 1.00 600.00 3,000.00
Foreman 7.00 days 1.00 500.00 3,500.00
Skilled 7.00 days 2.00 450.00 6,300.00
Unskilled 7.00 days 3.00 400.00 8,400.00
sub-total 21,200.00
Materials
Minor Tools (10% of Labor Cost) 2,120.00
sub-total 2,120.00
Direct Labor
Project Supervisor 17.00 days 1.00 600.00 10,200.00
Foreman 29.00 days 1.00 500.00 14,500.00
Skilled 29.00 days 3.00 450.00 39,150.00
Unskilled 29.00 days 5.00 400.00 58,000.00
sub-total 121,850.00
Equipment Rental
Minor Tools (10% of Labor Cost) 12,185.00
sub-total 12,185.00
Materials
Sand 0.50 Cu.m. 1,200.00 600.00
Gravel 1.00 Cu.m. 1,200.00 1,200.00
Cement 8.00 bags 275.00 2,200.00
Tire wire #16 11.00 kls 100.00 1,100.00
16mm dia. RSB 6.00 pcs 430.00 2,580.00
10mm dia. RSB 92.00 pcs 200.00 18,400.00
Consumables (5% of Material Cost) 1,304.00
sub-total 27,384.00
Direct Labor
Project Supervisor 6.00 days 1.00 600.00 3,600.00
Foreman 6.00 days 1.00 500.00 3,000.00
Skilled 6.00 days 3.00 450.00 8,100.00
Unskilled 6.00 days 3.00 400.00 7,200.00
sub-total 21,900.00
Equipment Rental
Minor Tools (10% of Labor Cost) 2,190.00
sub-total 2,190.00
Materials
2"x2"x12' cocolumber(10 pcs) 40.00 bd.ft 35.00 1,400.00
2"x3"x12' cocolumber(10 pcs) 60.00 bd.ft 40.00 2,400.00
CW Nail (assorted) 9.00 kg 100.00 900.00
Hacksaw Blade 4.00 pcs 120.00 480.00
1/4" Marine plywood 8.00 pcs 550.00 4,400.00
sub-total 9,580.00
Direct Labor
Project Supervisor 8.00 days 1.00 600.00 4,800.00
Foreman 12.00 days 1.00 500.00 6,000.00
Skilled 12.00 days 3.00 450.00 16,200.00
Unskilled 12.00 days 4.00 400.00 19,200.00
sub-total 46,200.00
Equipment Rental
Minor Tools (10% of Labor Cost) 4,620.00
sub-total 4,620.00
Materials
Teflon Tape 3.00 box 350.00 1,050.00
Gate Valve 2" dia 5.00 pcs. 2,400.00 12,000.00
2" dia. G.I. Union Patente 5.00 pcs. 412.00 2,060.00
2" dia. G.I. Tee 5.00 pcs. 250.00 1,250.00
2" dia. HDPE coupling 36.00 pcs. 570.00 20,520.00
2" dia. HDPE Pipe SDR 11 (60 ln.m) 36.00 rolls 12,700.00 457,200.00
2" dia. Male threaded adaptor 5.00 pcs. 400.00 2,000.00
Cable Wire #16 mm dia. 60.00 m 200.00 12,000.00
sub-total 508,080.00
Furnishing Labor, Materials and Equipment Rental for the CONSTRUCTION/ REHABILITATION/
Project Name:
IMPROVEMENT of Agumaymayan Water Supply System at Brgy. Agumaymayan, Boac, Marinduque
SUMMARY SHEET
DESCRIPTION UNIT PRICE / RENTAL
MATERIALS
4'x8' Tarpaulin 25.00 /sq.ft
2"x2"x12' cocolumber 35.00 /bd.ft
CW nails (assorted) 100.00 /kg
Sand 1,200.00 /Cu.m.
Gravel 1,200.00 /Cu.m.
Cement 275.00 /bags
Tire wire #16 100.00 /kg
16mm dia. RSB 430.00 /pcs.
10mm dia. RSB 200.00 /pcs.
2"x3"x12' cocolumber 40.00 /bd.ft
CW Nail (assorted) 100.00 /kg
Hacksaw Blade 120.00 /pcs.
1/4" Marine plywood 550.00 /pcs.
Teflon Tape 350.00 /box
Gate Valve 2" dia 2,400.00 /pcs.
2" dia. G.I. Union Patente 412.00 /pcs.
2" dia. G.I. Tee 250.00 /pcs.
2" dia. HDPE coupling 570.00 /pcs.
2" dia. HDPE Pipe SDR 11 (60 ln.m) 12,700.00 /roll
2" dia. Male threaded adaptor 400.00 /pcs.
Cable Wire #16 mm dia. 200.00 /pcs
Consumables
EQUIPMENT
Minor Tools
Various Tools and Equipment
LABOR
Project Supervisor 600.00 /day
Foreman 500.00 /day
Skilled 450.00 /day
Unskilled 400.00 /day
SCOPE OF WORK:
Submitted by:
MAY 5, 2023
(Date)