Professional Documents
Culture Documents
Total Amount
Bill No. Item Description Unit Number (Birr)
1.2 Maintain full Services for whole duration of the Project LS 1.00 2,100,000.00 2,100,000.00
1.3 Progress photograph and Reporting LS 1.00 150,000.00 150,000.00
1.4 Provision and survey labour for the Engineer LS 1.00 650,000.00 650,000.00
65,000.00
1.5 Establishment of site sign boards as per the specifiation No. 2.00 130,000.00
1.6 Independent testing of concrete and geotechnical as 75,000.00
required by the Engineer LS 4.00 300,000.00
2,400,000.00
1.7 Mobilization to site all machineries, material, personnel etc. LS 1.00 2,400,000.00
1.8 Transport to site and to tranch all pipes, fittings and 380,000.00
LS 1.00 380,000.00
including lining pipes to tranch etc.
Demobilization from site all machineries, material personal 2,900,000.00
1.9 LS 1.00 2,900,000.00
etc.
1.10 Surveying of all the pipe routes and submitt to the clienet for 300,000.00
approval before supply of Electro Mechanical Equipments
and excavation and supply of pipes LS 1.00 300,000.00
2.2 From 500M3 SR to Moyale Booster Station to Moyale 250m3 Service Reservoir
Item Description Unit Quantity Rate in Birr Amount in Birr
Supply of HDPE Pipe to PN 10, PN12.5 and PN 16 PE100, with outer sizes as
2.2.1 indicated in the table here below -
2.2.2 HDPE OD225 PN10 PE100 m 33281 2,600.00 86,530,600.00
2.2.3 HDPE OD225 PN12.5 PE100 m 953 3,350.00 3,192,550.00
2.2.4 HDPE OD225 PN16 PE100 m 6,616.00 3,450.00 22,825,200.00
Sub-Total - 2.2 40,850 112,548,350.00
2.3 From 500M3 SR to Elgof Village
Item Description Unit Quantity Rate in Birr Amount in Birr
2.3.1 HDPE OD 75 m 3,800.00 430.00 1,634,000.00
2.3.2 HDPE OD 90 m 1,100.00 410.00 451,000.00
2.3.3 HDPE OD 110 m 850.00 720.00 612,000.00
2.3.4 HDPE OD 125 m 1,800.00 740.00 1,332,000.00
2.3.5 HDPE OD 140 m 400.00 950.00 380,000.00
2.3.6 HDPE OD 160 m 3800.00 1000.00 3,800,000.00
Sub-Total - 2.3 11,750 8,209,000.00
Supply and Installation of HDPE fittings for HDPE BUTT WELD for
2.4
Transmission Main
2.4.1
2.4.1 DCI All Flanged Tee DN 225 * DN 160 * DN 225 PN 16 No 2 25,000.00 50,000.00
2.4.2 HDPE Stright Reducer OD 225 X OD 180 No 2 13,430.00 26,860.00
2.4.3 Stright Reducer OD 225 X OD 160 No 1 12,000.00 12,000.00
2.4.4 HDPE Stub Flange With Backling Ring OD 225 PN 16 No 4 11,000.00 44,000.00
2.4.5 HDPE Stub Flange With Backling Ring OD 160 PN 16 No 2 10,000.00 20,000.00
2.4.6 Gate Valve PN 16 -
2.4.7 DN 225 No 4 28,000.00 112,000.00
2.4.8 DN 160 No 4 27,000.00 108,000.00
2.4.9 DN 90 No 3 12,000.00 36,000.00
2.4.10 DN 75 No 6 10,500.00 63,000.00
HDPE Bends PE 100 PN 16 -
45o -
2.4.11 DN 225 No 20 6,000.00 120,000.00
2.4.12 DN 160 No 2 7,800.00 15,600.00
90o -
2.4.13 DN 225 No 6 12,000.00 72,000.00
2.4.14 Bolt , Nut & washer , M-30 No 600 1,200.00 720,000.00
2.4.15 Bolt , Nut & washer , M-24 No 1000 1,400.00 1,400,000.00
2.4.16 Dia. 225mm*2" flanged Saddle clamp No 10 8,000.00 80,000.00
Airvalve & Washout Fitting
2.4.17 For OD 225 PN 16 Line
2.4.18 DCI All Flanged Tee OD 225 * DN 50 * OD 225 PN 16 No 44 12,800.00 563,200.00
2.4.19 Double Flanged Spigot pipe with Puddle 1 m Length No 11 19,000.00 209,000.00
2.4.20 Flanged Spigot pipe OD 225 1m Length No 4 20,200.00 80,800.00
2.4.21 Dismantling Joint OD 225 PN 16 No 8 18,100.00 144,800.00
2.4.22 Double orfice Airvalve DN 50 PN 16 No 44 13,000.00 572,000.00
2.4.23 HDPE Stub Flange With Backling Ring OD 225 PN 16 No 74 5,300.00 392,200.00
2.4.24 DCI All Flanged Tee OD 225 * DN 80 * OD 225 PN 16 No 30 1,700.00 51,000.00
2.4.25 Gate Valve DN 80 PN 16 No 30 3,200.00 96,000.00
2.4.26 GS Pipe DN 80 All Flanged Pcs 30 2,100.00 63,000.00
2.4.27 Flap Check Valve DN 80 No 30 13,000.00 390,000.00
Sub-Total - 2.4 5,441,460.00
2,400.00
123,150.43
29,248.23
16,933.18
130,077.64
55,417.69
73,002.76
-
37,165.04
-
351,302.26
426,023.53
8,340.85
497,746.09
108,624.75
-
12,864.82
302,950.06
4,079.36
5,203.26
33.92
-
1,551.15
722,418.75
1,338,936.75
15,866.55
-
137,444.68
13,800.00
7,772.30
32,546.90
92,732.28
63,231.59
32,000.00
36,615.26
3,000.00
23,596.50
30,512.72
11,000.00
-
-
42,000.00
72,000.00
66,000.00
75,000.00
42,180.00
84,000.00
168,000.00
81,000.00
18,600.00
24,750.00
22,500.00
-
60,300.00
42,150.00
51,000.00
51,000.00
64,500.00
48,000.00
45,000.00
18,450.00
-
-
74,400.00
126,450.00
48,300.00
25,800.00
324,000.00
25,500.00
75,000.00
42,000.00
24,300.00
27,000.00
123,000.00
48,000.00
6,785,369.30
BILL 5 CONSTRUCTION OF 500 m3 BOOSTER STATION
ITEM DESCRIPTION UNIT QNTY UNIT PRICE
Birr
BILL 5: CONSTRUCTION OF 500 m3 RESERVOIR
5.1 EARTH WORK
Site Clr m2 60.00 40.00
5.1.1 Bulk excavation in normal soil to a depth not exceeding 1m m3 153.94 540.00
5.1.2 Ditto but in soft rock formation m3 30.79 450.00
5.1.3 Ditto but in hard rock formation m3 15.39 1100.00
5.1.4 Cart away all excavated material, deposit to appropriate distance not exceeding 1 km m3 200.12 320.00
5.1.5 Provide and fill with suitable selected granular material not exceeding 50cm m3 76.97 720.00
5.1.6 Provide and fill hard core with hard basaltic or equivalent stone, well compacted and blinded with m2 535.00
crushed stone to a finished thickness of 25 cm under the reservoir and valve chamber 132.73
2,400.00
83,126.54
13,854.42
16,933.18
64,038.22
55,417.69
71,011.77
-
30,528.43
-
351,302.26
426,023.53
8,340.85
497,746.09
108,624.75
-
7,504.48
198,810.98
4,040.87
5,154.18
33.60
-
1,551.15
722,418.75
1,338,936.75
15,866.55
-
71,176.71
9,600.00
5,634.92
37,384.95
117,074.50
11,443.75
42,600.00
52,888.71
6,400.00
38,649.44
48,861.03
10,080.00
-
-
6,200.00
14,500.00
40,200.00
40,200.00
14,060.00
21,400.00
13,050.00
17,000.00
6,200.00
8,250.00
7,500.00
-
20,100.00
14,050.00
17,000.00
17,000.00
21,500.00
16,000.00
15,000.00
6,150.00
-
-
24,800.00
42,150.00
32,200.00
8,600.00
644,000.00
8,500.00
14,500.00
14,000.00
8,100.00
7,500.00
15,000.00
1,300.00
5,611,469.06
Unit Quantity Unit Rate Amount
Item No. Description
(Birr) (Birr)
6 Reservoirs
6.1 Moyale Elevated Reservoirs (250 m3) #2
6.1.1 Excavation for structure
6.1.1.1 Topsoil stripping to 250 mm depth m3 28 750.00 21,000.00
6.1.1.2 Normal material to depth n.e. 2.0 m m 3
196 800.00 156,800.00
6.1.1.3 Normal material to depth 2.0 to 4.0 m m3 101 800.00 80,800.00
6.1.1.4 Extra over for excavation in rock m 3
163 950.00 154,850.00
6.1.1.5 Disposal of surplus excavated material as
directed by the Engineer m3 325 180.00 58,500.00
6.1.2 Filling to stated depth or thickness including
compacting 0.00
6.1.2.1 300 mm thick selected granular material m2 111 720.00 79,920.00
6.1.2.2 250 mm thick hard-core m2 111 780.00 86,580.00
6.1.3 Structural works 0.00
6.1.3.1 Provide and place in-situ-concrete class C-15/
blinding concrete 100 mm thick m3 12 3,800.00 45,600.00
6.1.3.2 Ditto, but C-20/ mass concrete 1300mm thick for
base slab m3 144 5,400.00 777,600.00
6.1.3.3 Ditto, but C-35/ reinforced concrete 250 mm
thick for shaft walls m3 44 7,500.00 330,000.00
6.1.3.4 Ditto, but C-35/ reinforced concrete for sloping
reservoir floor and horizontal base slab
m3 16 7,500.00 120,000.00
6.1.3.5 Ditto, but C-35/ reinforced concrete 200 mm
thick for shaft walls (inside reservoir) m3 27 7,500.00 202,500.00
6.1.3.6 Ditto, but C-35/ reinforced concrete 225 mm
thick for reservoir vertical walls m3 6 7,500.00 45,000.00
6.1.3.7 Ditto, but C-35/ reinforced concrete 200 mm
thick for reservoir roof slab m3 15 7,500.00 112,500.00
6.1.3.8 High yield reinforcement steel to specifications
kg 10800 135.00 1,458,000.00
6.1.3.9 "Expandit" supercast rearguard "R" PVC water
stop m 30 850.00 25,500.00
6.1.4 Form work 0.00
6.1.4.1 F1 Finish - plane vertical forms to floor slabs m2 55 530.00 29,150.00
6.1.4.2 F2 Finish -plane horizontal soffit of suspended
slab m2 6 530.00 3,180.00
Carried forward 3,787,480.00
B/F
6.1.4.3 F2 Finish to curved vertical forms to walls m2 166 530.00 87,980.00
6.1.4.4 F2 Finish -plane vertical forms to columns m 2
1060 530.00 561,800.00
6.1.4.5 F2 Finish to curved vertical forms to shaft
m2 26 530.00 13,780.00
5-16
Unit Quantity Unit Rate Amount
Item No. Description
(Birr) (Birr)
6.1.4.6 F3 Finish -plane horizontal to soffit of suspended
slab m2 15 530.00 7,950.00
6.1.4.7 F3 Finish to curved vertical forms to walls m2 161 530.00 85,330.00
6.1.4.8 F3 Finish to curved vertical forms to shaft
m2 35 530.00 18,550.00
6.1.4.9 F2 Finish plane horizontal forms to 250 step
round the reservoir m2 12 530.00 6,360.00
6.1.5 Pipe Laying 0.00
6.1.6.1 Laying DN 225 mm DCI inlet pipe including
excavation and backfilling m 38 5,082.00 193,116.00
6.1.5.2 Laying DN 225 mm DCI outlet pipe including
excavation and backfilling m 32 5,082.00 162,624.00
6.1.5.3 Laying DN 200 mm DCI drain pipe including
excavation and backfilling m 40 5,082.00 203,280.00
6.1.6 Surface Finishing 0.00
6.1.6.1 U2 Finish to vertical walls to reservoir (including
for ribbed finish) m2 116 70.00 8,120.00
6.1.6.2 U2 finish to reservoir roof m 2
15 70.00 1,050.00
6.1.6.3 U3 finish to reservoir floor slab m2 6 70.00 420.00
6.1.6.4 Waterproof sheeting of 500 gauge polythene to
upper surfaces inclined at an angle n.e. 30
degree to the horizontal; between floor slab and
blinding m2 111 1,400.00 155,400.00
6.1.6.5 2 layers bituminous ply on bituminous paint at
wall/roof slab interface (250mm wide) m 30 1,200.00 36,000.00
6.1.7 Pipe work 0.00
6.1.7.1 Install 200 nominal bore inlet pipe stack and
fittings as detailed LS 4,200.00 4,200.00
6.1.7.2 Install 200 nominal bore outlet pipe stack and
fittings as detailed LS 4,200.00 4,200.00
6.1.7.3 Install 200 nominal bore overflow pipe stack and
fittings as detailed LS 4,200.00 4,200.00
6.1.8 Miscellaneous work 0.00
6.1.8.1 Open grid flooring at upper platform level m2 3 680.00 2,040.00
6.1.8.2 Approved hinged manhole cover to fit
726x762mm opening (including for frame) nr 2 12,500.00 25,000.00
Carried forward 1,581,400.00
5-17
Name of Project:-Construction of Moyale Supply Civil Works
7.1.4 Extra over for bulk excavation in soft rock m3 19.2 800.00 15,360.00
7.1.5 Cart away all excavated material, deposit to appropriate m3 33.60 540.00 18,144.00
distance not excedding 1 km
7.1.6 250 mm thick hard trachyte stone hard core m2 76.97 500.00 38,485.00
7.1.7 Provide and fill hard core with hard basaltic or m 3
132.73 1,800.00 238,914.00
equivalent stone, well compacted and blinded with
7.2 crushed
Concretestone
and masonary work
7.2.2 50 mm thick lean concrete with mix ratio (1:3:6) under m2 132.73 2,500.00 331,825.00
the reservoir base slab and valve chamber
7.2.3 Reinforced concrete type C-25 filled into form work and
vibrated around reinforcement bar mix ratio should be
1:2:3
7.2.4 In base slab m3 7.98 7,500.00 59,850.00
7.2.5 In concrete wall m3 7.98 7,500.00 59,850.00
7.2.6 In top slab m3 7.98 7,500.00 59,850.00
7.2.7 Valve box m3 14.48 7,500.00 108,600.00
7.2.8 Provide and fix formwork
7.2.9 In base slab m2 9.90 3,500.00 34,650.00
7.2.10 To wall m2 9.9 3,500.00 34,650.00
7.2.11 To top slab m2 9.90 3,500.00 34,650.00
total of sheet 1,046,748.00
7.30 Provide, cut, bend and fix in position reinforced steel
bar. All according to structural drawing. Price should
include tying wires.
7.3.1 Diameter 8 mm deformed bar kg 11.5 135.00 1,551.15
7.3.2 Diameter 10 mm deformed bar kg 900.0 135.00 121,500.00
7.4 Accesssories and finishing
7.4.1 Provide and install access internal and external ladder Ls 1.0 18,000.00 18,000.00
constructed out of 1 1/2'' dia GS pipe and hooked to the
wall as per the drawing; including safety cages
4.13 Install DN 225 DCI double flanged pipe L=5.0m No 3 35,500.00 106,500.00
4.14 Install DN 225 DCI double flanged pipe L=5.0 m No 2 35,500.00 71,000.00
4.15 Install DN 225 DCI 90o degree double flanged bend No 3 21,240.00 63,720.00
9.1.1 Site clearing up to adepth of 20cm to remove top vegitative soil m2 18.00 40.00 720.00
9.1.2 Excavation work up to a depth of 50 cm to reduce level for placing hard core m3 8.00 540.00 4320.00
9.1.5 cart away surplus excavated material to a distance not exceeding 1kmfrom the site m3 8.00 680.00 5440.00
Filling and spread under hard core with selected site material & compact in layers not exceeding to a
thickness of 15cm as per the recommendation of the supervising Engineer m3 3.00 260.00 780.00
9.1.6
9.2 Masonry work 0.00
25 cm thick basaltic or equivalent stone Hard core well rolled, consolidated & blinded with crushed
m2 18.00 3500.00 63000.00
9.2.1 stone
Hard stone masonry work for foundation bedded with cemement sand mortar 1:3 in ratio m3 4.00 1700.00 6800.00
9.2.2
9.2.3 Hard stone masonry work for stand bedded with cemement sand mortar 1:3 in ratio m3 2.00 1600.00 3200.00
9.2.4 15 cm wide dressed stone open channel drainage to soak away pit m2 10.00 650.00 6500.00
9.3.1 15cm thick mass concrete over hard core as shown in the drawing m2 18.00 1360.00 24480.00
m2
10.1.1 Site clearing up to adepth of 20cm to remove top vegitative soil 100 40.00 4,000.00
Excavation work up to a depth of 50 cm to reduce level for m3
10.1.2 placing hard core 150 550.00 82,500.00
10.1.3 Excavation in soft rock formation m3 1 850.00 850.00
10.1.4 Ditto but in hard rock farmation m3 0.8 1100.00 880.00
cart away surplus excavated material to a distance not
10.1.5 m3 100 65.00
exceeding 1kmfrom the site 6,500.00
Filling and spread under hard core with selected site material &
compact in layers not exceeding to a thickness of 15cm as per
10.1.6 the recommendation of the supervising Engineer m3 30 640.00 19,200.00
10.2 Standard Masonary works including finishing works -
Construction of Camel, cows, sheeps and goats cattle troughs as
10.3 No. 3 18,000.00
per the drawings 54,000.00
Supply and installation of all pipe works as per the standard
10.3.1 ls 1 19,000.00
drawings 19,000.00
Total for Bill No 10 186,930.00
Grand Total of 5 Cattle Troughs 934,650.00
BILL No.11: FENCEING WORK
Item No. Item Description Unit Quantity Unit Rate Total Amount
11.1 AT TWO BORE HOLES (Birr) (Birr)
Excavation for foundation of posts for fencing, dimensions 50 x 50 x 70cm
11.1.1 including disposal of surplus material and foundation for the gate having area m3 9.00 340.00 3,060.00
of 60x60x100cm.
11.1.2 Cyclopean concrete work for foundation of fencing Poles m3 8.60 4,300.00 36,980.00
Supply & installation precasted concrete poles 13X13cm for fencing, length
11.1.3 3m fixed at 2m interval Pcs 40.00 2,400.00 96,000.00
11.1.4 Supply & fix mesh wire up to a height not less than 2.50m, fixed to the concret m 100.00 400.00 40,000.00
Construction of concrete columns to support the gate having area of 60x60cm
11.1.5 having a total height fo 4m with it foundation under the surface having a depth No. 2.00 13,000.00 26,000.00
of 1m.
11.1.6 Supply & fix metal gate with its locks -
11.1.7 a/ 2x2.5m No. 1.00 21,500.00 21,500.00
Sub-Total 223,540.00
Sub-Total for two - 447,080.00
11.2 FENCEING WORK AT CONTROLE STATION
Unit Rate Total Amount
Item No. Item Description Unit Quantity (Birr) (Birr)
Excavation for foundation of posts for fencing, dimensions 50 x 50 x 70cm
11.2.1 including disposal of surplus material and foundation for the gate having area m3 28.22 340.00 9,594.80
of 60x60x100cm.
11.2.2 Cyclopean concrete work for foundation of fencing Poles m3 21.96 2,300.00 50,508.00
Supply & installation precasted concrete poles 13X13cm for fencing, length
11.2.3 3m fixed at 2m interval Pcs 96.00 13,500.00 1,296,000.00
Supply & fix mesh wire up to a height not less than 2.50m, fixed to the
11.2.4 concrete poles by caped including all necessary fixing materials. m 196.00 1,800.00 352,800.00
Construction of concrete columns to support the gate having area of 60x60cm
11.2.5 having a total height fo 4m with it foundation under the surface having a depth No. 2.00 52,300.00 104,600.00
of 1m.
11.2.6 Supply & fix metal gate with its locks -
11.2.6.1 a/ 2x2.5m No. 1.00 19,400.00 19,400.00
11.2.6.2 b/ 1x2m No. 1.00 19,000.00 19,000.00
Sub-Total 1,851,902.80
TOTAL CARRIED TO SUMMARY 1,851,902.80
12.1.2 Excavation to 30cm depth and 8cm width around Clear water tank m3 8.00 310.00 2,480.00
13.1.2 GS Flange 8" to be welded to the 8" steel casing No. 1 165,000.00 165,000.00
GS Wellhead with a 8" flange, DN100 short piece with a DN100
PN25 threaded socket welded on the inside & DN100 short
13.1.3 piece with a DN100 PN25 flange welded on the outside & all No. 1 80,000.00 80,000.00
accessories as shown in the drawing & as per the specification
13.2.2 GS Flange 8" to be welded to the 8" steel casing No. 1 165,000.00 165,000.00
13.2.3 GS Wellhead with a 8" flange, DN80 short piece with a DN80
PN25 threaded socket welded on the inside & DN80 short piece
with a DN80 PN25 flange welded on the outside & all No. 1 80,000.00 80,000.00
accessories as shown in the drawing & as per the specification
13.2.4 GS riser pipe, heavy grade, threaded DN80, PN40 L = 3000mm 35,691.00
No. 10 356,910.00
c/w socket
13.2.5 Double flanged GS bend DN80 PN25 - 90° No. 3 21,250.00 63,750.00
13.2.6 Single flanged GS pipe DN80, PN25 L = 4000mm No. 1 35,963.00 35,963.00
13.2.7 dismantling piece DN80 PN25 No. 2 19,723.00 39,446.00
13.2.8 14,711.00
Double flanged GS pipe with puddle DN80, PN25,L = 500mm No. 1 14,711.00
13.2.9 21,250.00
Double flanged GS pipe with puddle DN80, PN25,L = 1200mm No. 1 21,250.00
13.2.1 17,850.00
Double flanged GS pipe with puddle DN80, PN25,L = 1000mm No. 1 17,850.00
13.2.11 Double flanged GS pipe DN80, PN25 L = 1000mm with two 1/2" 17,850.00
female sockets welded for the attachment of pressure gauge No. 1 17,850.00
and pressure switch
13.2.12 Double flanged GS pipe DN80, PN25 L = 1000mm, with one 17,980.00
No. 1 17,980.00
DN 3/4" welded socket
13.2.13 Single flanged GS pipe DN80, PN25 L = 2000mm No. 1 24,480.00 24,480.00
13.2.14 Double flanged GS tee DN80/50/80 PN25 - 90° No. 2 22,335.00 44,670.00
13.2.15 Double Air relief valve DN80, PN25, with isolating gate valve No. 1 24,990.00 24,990.00
13.2.16 Double flanged Dismantling piece DN80, PN25 No. 1 19,720.00 19,720.00
13.2.17 Pressure gauge, glycerin filled, 100mm dia., 1/2” male 12,240.00
connection, 0-15 bar with isolating cock No. 1 12,240.00
13.2.18 3/4" pipe, elbows, nipples, unions and faucet for sample water 19,635.00
tapping & compound supply Sum 1 19,635.00
13.2.19 26,299.00
Double Flanged woltman water meter, turbine type, DN80, PN25 No. 1 26,299.00
13.2.2 Double flanged Non return valve DN80 PN25- spring-loaded 19,720.00
No. 1 19,720.00
type
13.2.21 Double Flanged Gate valve DN80 PN25 No. 1 14,535.00 14,535.00
13.2.22 Double Flanged Gate valve DN80 PN25 No. 1 15,700.00 15,700.00
13.2.23 single flanged GS elbow DN80 PN25, 90° No. 1 14,000.00 14,000.00
13.2.24 double flanged reducer, GS, DN80/150 PN25 No. 1 23,800.00 23,800.00
13.2.25 flanged Socket piece, PVC DN150 PN25 No. 1 19,728.00 19,728.00
13.2.26 Pipe support with pipe clamp, foot plate, anchor bolts etc. Sum 1 30,600.00 30,600.00
13.2.27 Necessary pipes, fittings bolts, nuts, gaskets etc. required to 840.00
complete installation & to connect to the discharge (collector) Sum 1 840.00
pipe
Sub-Total .13-2 4,841,667.0
13.4.12 Cable tray, cable trunking, cable supports etc. as required Sum 1 100,800.00 100,800.00
DN25 Service water supply system, connected to water pump, 179,200.00
13.4.13 to feed the solution preparation tanks including all valves & Sum 1 179,200.00
fittings
Solution pipe system, made of DN20 uPVC pressure pipes & 112,000.00
13.4.14 fittings, connection from the preparation tank to the injection Sum 1 112,000.00
point at the top of the reservoir
swiveling type gantry crane 1/4 ton to be installed on top of the 134,400.00
13.4.15 Sum 1 134,400.00
reservoir
Sub-Total .13-4 2,217,600.00
Total Amount
13.5 PART 7-BH'S POWER PLANTS @ El-gof
(Birr)
Item Unit Rate
Description of works Unit Qty
(Birr)
13.5.1 PART 7-SUPPLY OF PLANT, POWER PLANT
Power Plant
Diesel generator set, PRIME RATING, as per the technical
specification, engine & alternator pre-installed on a common
rigid frame, switchgear including manual changeover switch
panel, day tank incorporated into the frame, exhaust piping
system and all accessories required for installation, alternator:
13.5.3 No. 1 6,500,000.00 6,500,000.00
150 KVA, 3 phase, 400 V, 1500 RPM (woking environment =
45 degree centigrade at an average elevation of 888 masl).and
with all fast moving spare parts, to be installed at MBH3.
49,500.00
13.5.7 Hot air discharge louver for wall installation with all accessories No. 2 99,000.00
Ducting & framework between hot air discharge wall outdoor 46,500.00
13.5.8 louver and engine radiator with all accessories required for No. 2 93,000.00
installation
90,750.00
13.5.9 Storage fuel storage tank, 5000 ltr capacity with all accessories No. 2 181,500.00
Fuel pipe work consisting of DN1 1/2" black mallable iron pipes, 19,500.00
13.5.1 No. 2 39,000.00
fittings & valves
Fuel hand pump suitable for standard oil barrels with three 16,950.00
13.5.11 No. 2 33,900.00
meters long flexible hose 1"
Sub-Total .13-5 11,446,400.00
TOTAL CARRIED TO SUMMARY 26,870,846.00