Cangkat Sungai ARA 2 Bill Of Quantities/

Painting costing Schedule of Rate

Item Description Unit Quantity Amount (RM)

Fairview

To supply labour and tools install

A Dad's bedroom

To supply and install whole unit interior wall using jotun (2 layers coating,
i 1 color) not included dining feature wall L/S 1,345.00
- cover plus +

B Alvin's bedroom

To supply and install whole unit interior wall using jotun (2 layers coating,
i 1 color) not included dining feature wall L/S 1,345.00
- cover plus +

TOTAL CARRIED TO SUMMARY 2,690.00

Cangkat Sungai ARA 2


M&E costing

Item Description Unit Quantity Amount (RM)

Fairview

To supply labour and tools install

A Dad's bedroom

i Supply and install conceal 13amp switch socket Nos 5 1,000.00


ii Supply and install panasonic aircond Nos 1 2,572.00
iii Supply and install Surface light Nos 2 80.00

B Alvin's bedroom

i Supply and install conceal 13amp switch socket L/S 1,177.00


ii Supply and install panasonic aircond Nos 1 2,572.00
iii Supply and install Surface light Nos 2 80.00

TOTAL CARRIED TO SUMMARY 7,481.00


Cangkat Sungai ARA 2 Bill Of Quantities/
Painting costing Schedule of Rate

Item Description Unit Quantity Amount (RM)