Item Comment

1 Section 5.3 – This need to be clarify IBSF should not approved a permit. FSA as a main contractor to approve any pe
2 5.5.1 –Clarify if this is IBSF or FSA HSE
3 This MS refer to logistic plan which has no clear information for part 2.
4 Installation of the propping tower not specific for part 2

5 Installation of the propping tower,access and remove the slings during lifting, Installation of platform beam and rem

Assembly – what are the items to be installed during assembly before transportation to the erection location? Orth
6

7 8. Potential dropped objects need to be clear in this MS,The proposal of having and hanging structure to protect
8 Drawings provided in this MS not clear.
Update risk assessment to be specific for part 2.
9

12

13

14

15
16
17
18

19

20

21
22
23

24

25
26
27
28
HSE C
Comment
ed to be clarify IBSF should not approved a permit. FSA as a main contractor to approve any permits that IBSF will carry out on site
s IBSF or FSA HSE
stic plan which has no clear information for part 2.
ropping tower not specific for part 2

opping tower,access and remove the slings during lifting, Installation of platform beam and removal of propping tower.

e the items to be installed during assembly before transportation to the erection location? Orthotropic deck? Mechanical conduits? Claddi

d objects need to be clear in this MS,The proposal of having and hanging structure to protect public from dropped object and fall arrest

n this MS not clear.


ent to be specific for part 2.
Resposne
Revised
Revised
Revised by adding the summary logistc plan for part#2
Specific lifting plan submitted inculding all the work activity related to installation of the propping tower.

Specific lifting plan with copvering all respects submitted.

only orthotropic deck will be assebled and erected along with box girders .

The erection will be carried during full colsure of the KKR work area and control measures for the drop obejcts will be in place
activites , refer to page 40
Revised , specific lifting plan for each lift will be submited inculding the accurate crane configuration and working para

Revised
Resposne
Revised
Revised
Revised by adding the summary logistc plan for part#2
g plan submitted inculding all the work activity related to installation of the propping tower.

Specific lifting plan with copvering all respects submitted.

only orthotropic deck will be assebled and erected along with box girders .

ring full colsure of the KKR work area and control measures for the drop obejcts will be in place beofre starting
activites , refer to page 40
plan for each lift will be submited inculding the accurate crane configuration and working paraemeters.

Revised