This drawing and design is the exclusive property of Alfanar Electrical Systems and must not be copied or lent

without its permission in writing. 1 2 3 4 5 6 7 8

F CUSTOMER : Technical Development for Contracting F

PROJECT : Establishing a station for Saudi customs


at the Omani border - Al rub al khali
PANEL NAME : ESH-04-LPP

ENCLOSURE TYPE : IP-42 (INDOOR) FORM-1


E E
FLUSH WALL MOUNTED
REFERENCE No. : RT-59431 Rev.0

MANUFACTURER REF. NO. : -

D
DRAWING & REV. No. : C49794-LCP01TN142EI0 D

ITEM No. : 39

QUANTITY : 01 No.

C C

MANUFACTURER :

ALFANAR ELECTRICAL SYSTEMS


P.O.BOX 564, RIYADH-11383
RIYADH, KINGDOM OF SAUDI ARABIA
B B
TEL No. 01-2651114 FAX No. 01-2652184

X FOR APPROVAL

FOR PRODUCTION
Drawn by : Date : 04 - - - Scale :
A
A.HAMDY 03 - - - NTS A
AS BUILT Checked by : Date : 02 - - - Sheet No.
S.HAMED 01 - - - 01
Approved by : Date : 00 30.Nov.22 FIRST ISSUE TICKET # 328911 A.H Next sht.
ALAA REV. No. DATE NATURE OF REVISION DRAWN 02
1 2 3 4 5 6 7 8
This drawing and design is the exclusive property of Alfanar Electrical Systems and must not be copied or lent without its permission in writing. 1 2 3 4 5 6 7 8

PARTS SCHEDULE
F 400 400 160 01 - PANEL ENCLOSURE F
02 - FRONT DOOR
05 03 - DOOR KEY LOCK
04 - DOOR HINGE
11 F1-F12 05 - PANEL MOUNTING HOLES
04 06 - TOP / BOTTOM OPENING WITH REMOVABLE COVER
07 - MAIN CIRCUIT BREAKER
08 08 - BRANCH CIRCUIT BREAKER
03 09 - NEUTRAL BAR
E 10 - EARTH BAR E
11 - PANEL NAME PLATE
02 13 12 - MANUFACTURER LOGO
13 - MOUNTING PAN
600

09 14 - DEAD FRONT COVER


16 Q1 15 - DOOR TO CABINETS GROUNDING CABLE
16 - DIRECTORY POCKET
01 07
10 SPECIFICATION
D X X 400/230V, 60HZ, 3PH/4W D
E N SYSTEM VOLTAGE -
14 PROTECTION - IP-42 (INDOOR) FORM-1
PANEL MOUNTING - SURFACE WALL MOUNTED
12 No. OF WAY - 12 WAYS (DIN RAIL TYPE)
PANEL CONSTRUCTION - 1.6mm THICK E.G.S SHEET
PANEL FINISH - RAL 7035 (LIGHT GREY)
FRONT VIEW SIDE VIEW - POLYESTER POWDER COATED
FRONT VIEW S.C. LEVEL - 10KA
(COVER REMOVED)

C BUSBAR SYSTEM C
400 80
MAIN BUS - 125A Cu. (TIN-PLATED)
NEUTRAL BUS - 125A Cu. (TIN-PLATED)
EARTH BUS - 100A Cu. (TIN-PLATED)

20
ESH-04-LPP
40

06 400/230V, 60HZ, 3PH/4W CABLE ENTRY


160

20
INCOMING - BOTTOM
15 OUTGOING - TOP/BOTTOM
B
5 70 5 B
SECTION X-X PANEL NAME PLATE
ITEM NO - 39
QUANTITY - 01 No.

ALL DIMENSIONS ARE IN MM


04 - - - Drawn by: Project: Title: Code: Reference No: Scale:
Establishing a station for Saudi customs ESH-04-LPP RT-59431 Rev.0
NTS
A 03
02
-
-
-
-
-
-
A.HAMDY
Checked by: at the Omani border - Al rub al khali PANEL LAYOUT DETAIL - Work Order No:
- Sheet:
A

01 - - - S.HAMED Customer: Drawing No: 02


00 30.Nov.22
IND DATE
FIRST ISSUE TICKET # 328911
NATURE OF REVISION
A.H Approved by:
BY ALAA
Technical Development for Contracting C49794-LCP01TN142EI0 Next Sht:
03
1 2 3 4 5 6 7 8
This drawing and design is the exclusive property of Alfanar Electrical Systems and must not be copied or lent without its permission in writing. 1 2 3 4 5 6 7 8
PANEL NAME ESH-04-LPP MOUNTING TYPE : SURFUCE MOUNTED FEEDER ENTRY: BOTTOM
LOCATION : SHDE 04 - Two way vehicales parking VOLTAGE: 380/220V , SC 10KA PF=0.9
F FEEDER ORIGIN :DP-IB-01 NO OF WAYS : 12 IP : 54 - OUTDOOR F
* FOLLD LIGHTS CONTROLLED VIA PHOTO CELL

CONNECTED LOAD PHASE MCB BREAKER BUS LOADING (VA) DEMAN MCB BREAKER CIRCUIT BREAKER
DEMAN
CONN. D CONDUIT CONN.
WIRE SIZE SQMM CKT.NO LOAD DESCRIPTION CONDUIT SIZE D LOAD LOAD DESCRIPTION CKT.NO WIRE SIZE SQ MM
LOAD VA PH ":R' PH ":Y' PH ":B' NO.OF BKR LOAD SIZE BKR NO.OF PH ":R' PH ":Y' PH ":B' LOAD VA
(VA) R Y B
VA VA VA POLES AMPS (VA) AMPS POLES VA VA VA

2*4+4 1 FLOOD LIGHTS 1500 1500 1 20 25 1500 * 0 25 20 1 0 SPARE 2

2*4+4 3 FLOOD LIGHTS 1500 1500 1 20 25 1500 t 0 25 20 1 0 SPARE 4

*
E 2*4+4 5 SOCKET 500 500 1 20 25 500 500 20 1 500 500 SOCKETS 6 2x4+4 E
7 SPARE 0 1 20 0 * 2000 20 1 0 SPARE 8

9 SPARE 0 1 20 0 * 0 20 1 0 SPACE 10

11 SPARE 0 1 32 0 * 0 32 1 0 SPACE 12

TOTAL LOAD 3500 1500 1500 500 3500 500 0 0 500 500 TOTAL LOAD ( KVA)

TOTAL CONNECTED LOAD 4,000 VA TOTAL CONNECTED LOAD /PHASE (VOLT-AMPS) 1,500 1,500 1,000

CHOOSE BREAKER SIZE CABLE SIZE : 4*10+10MM2 CU/XLPE/PVC /SWA, 0.6/1 kv


;- 32AT/50AF MCCB

D D

C C

B B

04 - - - Drawn by: Project: Title: Code: Reference No: Scale:


Establishing a station for Saudi customs ESH-04-LPP RT-59431 Rev.0
NTS
A 03
02
-
-
-
-
-
-
A.HAMDY
Checked by: at the Omani border - Al rub al khali LOAD SCHEDULE - Work Order No:
- Sheet:
A

01 - - - S.HAMED Customer: Drawing No: 03


Technical Development for Contracting
00 30.Nov.22
IND DATE
FIRST ISSUE TICKET # 328911
NATURE OF REVISION
A.H Approved by:
BY ALAA
C49794-LCP01TN142EI0 Next Sht:
4
1 2 3 4 5 6 7 8
This drawing and design is the exclusive property of Alfanar Electrical Systems and must not be copied or lent without its permission in writing. 1 2 3 4 5 6 7 8

TAG. ITEM DISCRIPTION QTY MODEL MAF.


F MAIN BREAKER: F

Q1 1090209 S125-NJ, MCCB, 3P, 32AT/125AF, 36KA@415V, 50KA@240V, ADJ (THERM&MAG), [50 SQ.MM] 1 255014 ALFANAR
FEEDERS:
F*-F* 1192870-H MCB, 1P, 32AT/63AF, 15kA@230V, CURVE-C, [25/35 SQ.MM FLEX./REG. CONDUCTOR] 2 TD3M15C132 ALFANAR
F*-F* 1192868-H MCB, 1P, 20AT/63AF, 15kA@230V, CURVE-C, [25/35 SQ.MM FLEX./REG. CONDUCTOR] 10 TD3M15C120 ALFANAR
E E

D D

C C

B B

04 - - - Drawn by: Project: Title: Code: Reference No: Scale:


Establishing a station for Saudi customs ESH-04-LPP RT-59431 Rev.0
NTS
A 03
02
-
-
-
-
-
-
A.HAMDY
Checked by: at the Omani border - Al rub al khali BILL OF MATERIALS - Work Order No:
- Sheet:
A

01 - - - S.HAMED Customer: Drawing No: 04


Technical Development for Contracting
00 30.Nov.22
IND DATE
FIRST ISSUE TICKET # 328911
NATURE OF REVISION
A.H Approved by:
BY ALAA
C49794-LCP01TN142EI0 Next Sht:
--
1 2 3 4 5 6 7 8

You might also like