Barsan Engineering

Services
Client : ……………. Prepared by:Eng Mohamed Farah

Contructor: Barsan engineering and logistic services Date: Dec 4, 2022

Project name: Relocation of sliding gate


NO Description Unit Quty Rate Amount ($)

1.0 Mobilization Lms 1.00 450.00 $ 450.00

Excavation of footing supporting and receiving columns posts with


2.0 Cum 7.20 35.00 $ 252.00
dimension of 1.1m length and 1.1m wide and 1.5m in deep
Cast Rcc footing of supporting and receiving column posts with 1m
3.0 length and 1m wide and 0.5m height using of Ø12 bars whit ratio Cum 2.80 365.00 $ 1,022.00
(1:2:4) 20Mpa
Rcc column with dimension 0.4m length and 0.4m wide use 3.8m
4.0 Cum 3.43 365.00 $ 1,252.68
height using Ø16 mm bars
5.0 Supply and fix of 4 terminal posts attached to supporting RCC columns Alms 4.00 152.00 $ 608.00

Provide and fix v grooved truack middle of terminal post and supporting
6.0 Lms 1.00 450.00 $ 450.00
colums pairs with

7.0 installation of sliding gate Lms 1.00 380.00 $ 380.00

8.0 Providing and spraying lubricating oil to v-grooved track surface Lms 1.00 145.00 $ 145.00

Relocation and fixing of sliding gate from carrunt location to prepared


9.0 Lms 1.00 310.00 $ 310.00
location

10.0 $ -

Grand Total $ 4,869.68