TASK SHEET

Title:
Testing the GFCI with a Multimeter Tester

Performance Objective:

Test the GFCI following the specifications given below and in compliance with the PEC
standards.

Supplies/Materials:

● Installed GFCI

Equipment:

● Multimeter tester
Steps/Procedure:
1. Set the multimeter tester to the AC Voltage setting, and to the highest voltage
range.
2. Connect the probes to the proper inputs on the tester: COM for the black lead and
Volts for the red lead.
3. Connect the red probe lead into the right slot of the outlet.
4. Connect the black probe lead into the left slot of the outlet.
5. Examine the result displayed on the meter. there should be a reading of 220 Volts.
If the multimeter reads 0.0, it can mean a bad lead connection. Try to move it
around for better contact. If the result still does not change to a value, there is a
chance of an electrical problem with the outlet.
6. Remove the black probe lead from the slot and put it inside the oval slot of the
outlet, which is the ground. A voltage reading should be displayed on the
multimeter. If no reading is displayed, then the GFCI must be defective.
Assessment Method:

Performance Criteria Checklist


PERFORMANCE CRITERIA CHECKLIST

Name of Trainee:________________________________________________________ 

During the performance of the activity did the trainees perform according to the required
criteria?

CRITERIA YES NO
Were you able to:
1. Prepare hand tools and materials according to job requirements
2. Set the multimeter to the correct setting
3. Connect the probe leads to the multimeter and the GFCI
appropriately

4. Get a proper reading on the testing procedure

5. Wear proper PPE

6. Practice OHS
7. Perform 5S of good housekeeping

8. Submit the Share Link in the Submission Bin at the TOP course?

For satisfactory achievement, all items should receive a YES response.