Professional Documents
Culture Documents
1. Business Case
5. Teambuilding
Project success
3
Integrated solution to fulfil business case
Performing facilities
information / data
4
Plant performance after MC - “Typical”
Typical Plant
Performance
Curve over time
t
CSU - first year(s) of operation
5
Examples (1)
6
Examples (2)
Refinery
Many leaks of flanges at start up causing “rework”. Start Up
‘struggle’ several months. Significant cost due to loss of (potential)
production.
>> 10 million US$.
Root cause: tightness programme failed.
Refinery
Reactor scale up caused serious problems during start up (both
operational problems and mechanical failure). It took about 3
months before problems were solved. Estimated cost about 25
million US$.
Root cause: design (detailed engineering) errors / prototypes.
7
Examples (3)
Refinery
Instrumentation problems causing severe delay in start up (and
during start up).
Estimated production loss in the order of 60 millions US$.
Root cause: insufficient testing, instrument integrity
Refinery
Inadequate cleaning / adjustment of construction - cleaning -
commissioning/start up, resulting in commissioning and start up
delay(s), corrosion problems (inadequate preservation of
stainless steel in combination with cleaning with chlorides
containing water) ….
Costs: > 100 million US$ (production loss and rework).
8
Plant performance after MC - Typical vs Flawless
Typical Plant
Performance
Curve over time
t
CSU - first year(s) of operation
9
Origins of Facility Diseases
Pre
Scout/BOD/BDP Detail Eng/Proc/Constr Comm/S-U
Scout/BOD/BDP PS
Study Det Eng/Proc/Constr Comm/SU
10
Overall Strategy for successful
11
COTENTS
1. Business Case
5. Teambuilding
Targeting for success
Starting in time
Make sure that the products are sold when production starts
13
The Operations Implementation Process
Development of the project
Scouting, Detailed
Design Project
Project Engineering,
Specification(s) Specification
Initiation Procurement
Construction
Development of operations implementation
Commissioning
and
Start Up
Operations and
Maintenance
Focus on design
Philosophy
related Key
Operations
Performance Areas
Implementation
Plan
Project Objectives Further specification and
will include implementation of plans
Systemisation (including Q-cases)
commissioning
and start up. Overall outline of
Prototypes
Operations
Targets for Implementation
Complexity
eventual operation
(production, Schedule
Detailed and integrated
reliability, plans for precommissioning,
availability) Resource
commissioning and start up,
requirements
incl. testing to ensure
Set out the main Develop Q-cases for integrity
strategy for Budget Key Success Areas
Operations and Implementation of best
Maintenance Key Success
practices for cleanliness
Areas - outline of
and tightness
Management management
Systems system(s)
15
Blueprint - highlights
Systemisation
16
Process Systemisation
Hydro
Sub system
Cleaning
system
Hydro
Tightness Process
system system
Plant
Hydro
Cleaning
DCS system
system
Site
Process
system
Electrical
Plant
system
Process
system
Control
Cleaning system
system Process
system
Tightness Tracing
system system
Cleaning
system
17
Blueprint - highlights
Systemisation
18
Potential impact of prototypes and complexity
10
Start-up time ratio
0.1
0.01
0 20 40 60 80 100
Preparation fulfilled, Proactive Organisation
19
Blueprint - highlights
Systemisation
20
Management for key performance areas.
Elements of the management system
Values and Know ledge and
Change Methods and
Matrix: Bus ine s s controls for critical Shared purpose Audit, review Roles and Organisational Ethics, Inf ormation Inf ormation and
management, Procedures incl. Competences
pe rform ance are as and objectives and appraisal Responsibilities structure Leadership and Management, Data
responsiveness risk management
Teamw ork communication
Operations Role s and Re s pons ibilitie s Sk ills , Attitude s and Be haviour Inform ation and data, including
Operations Integrity Assurance Proce s s e s and s ys te m s (s tructure )
Implementation (s tructure ) (com pe te nce ) s upporting s ys te m s
Manage m e nt
Re putation
Profitability
Te s ting and
Punching
Production
Coinciding
Eve nts
Key
Mainte nance
Cle anline s s
Prototype s ,
Com ple xity
De s ign
Performance
Expe rie nce Hum an Re s ource s
Areas
Le arning and De ve lopm e nt
21
Key performance areas
22
Management System, Business Controls
23
Blueprint - highlights
Systemisation
24
Management for key performance areas.
Values and Know ledge and
Change Methods and
Matrix: Business controls for critical Shared purpose Audit, review Roles and Organisational Ethics, Inf ormation Inf ormation and
management, Procedures incl. Competences
perform ance areas and objectives and appraisal Responsibilities structure Leadership and Management, Data
responsiveness risk management
Teamw ork communication
Operations Roles and Responsibilities Skills, Attitudes and Behaviour Inform ation and data, including
Operations Integrity Assurance Processes and system s (structure)
Implementation (structure) (com petence) supporting system s
Managem ent
Reputation
Profitability
Testing and
Punching
Production
Coinciding
Events
Execution of w ork
Functional
Mechanical
Tightness
Rotating
equipment
Prototypes,
Com plexity
Design
Key
Experience Hum an Resources
Performance
Learning and Developm ent
Areas
25
Operations Work Breakdown
Normal De-
Commissioning Start Up Shut Down
Operations Commissioning
Process
Mechanical Disassembly,
Completion Reconditioning
Commissioning Activities
Activities
Commissioning Tasks
Tasks
Commissioning Hand-actions
Hand Actions
28
Scorecard - “Flawless Start Up”
Tightness V
5Q’s Cleanliness V
Facility
Integrity V V
Operability
Safety V V V
Prototypes
5Q’s Complexity V
Schedule
Testing V V
Experience V
Coinciding Events ?
29
Q-case for key success areas
Barriers to prevent
threats
Recovery
preparedness
measures
31
Blueprint - highlights
Systemisation
32
Typical Manpower curve
Start Up
100
90
80
num ber of staff
70 operators shift
60 operators day
50 maintenance staff
Core team to
40 managing contractor
30be in place staff and support
at BOD phase
20
10
0
tim e
About 2 years
prior to
Start Up
38
Overall Strategy for successful
Business case
Early involvement of the client organisation (who
will eventually operate and maintain the facilities)
Structured preparation of commissioning, start up
and normal operation/maintenance of the facilities.
Solution
The Operations Implementation Planning process will
provide a structure for activities of the client organisation
in all phases (planning timeline, milestones).
It will provide a clear and well defined work-process
leading to successful start up and sustainable operation.
39
Overall Strategy for successful
Business case
Focus on key success areas which are known to be of
critical importance for a good start up
Application of best practices based on lessons learned.
Solution
The Flawless Start Up programme will focus on a
selected set of key performance areas. For these so
called key success areas a structured approach is
available based on best practices.
40
In Summary
42
Flawless Start-Up Procedure for EPC
Commissioning Commercial
Design Procurement Construction Start-Up Operation
Assign
Flawless Start-Up Procedure
Design Flaw
Procure Flaw
Commissioning Flaw
Vendor’s Flaw
COTENTS
1. Business Case
5. Teambuilding
Status at RFSU; Specifications
Components
complete, whole device checked,
dry, simulation, and live tested (no process medium applicable)
System
filled, pressurised and tightness tested
energized, vibration and noise tested
capacity, cleanliness and flow stability tested
tuned, controllable and safeguarded, tested
all process and operation modes: fail and recovery simulation tested
Compiled systems
all interaction between the systems tested
Total facility
all work operation and maintenance routines available and workable
inspection /monitoring programs activated,
ready for intake of HC and start reliable processing
46
COTENTS
1. Business Case
5. Teambuilding
Key Success Factors and KPIs
Tightness Operability
leak severity /work- capacity window
specification flexibilty to modes
training control on auto
protocols alarms /trips
supervision conformance to License
Cleanliness recovery on loss
critical dirt levels window monitoring
best cleaning methods Safety
spec’s and protocols sampling, filter cleaning
supervision safety district facilities
Integrity Fire, Gas and Remote
installation skills operation systems
Fat / SIT, QA/QC Emergency procedures
consistency in settings HSE review, no H risks
testing, Methods, protocols Asset management
early 100% safeguarding
simulation test
risk based inspection
48
Key Success Factors and KPIs
Structure Information
KPI’s, Milestones New Look Design Book
Risk driven, PATH assign custodians
Roles and responsibilities Data
clear split main parties complete,
clear split individuals consistent,
integrate construction, accurate, precise,
engineering csu staff for timely
best fit assign custodians
review contracts if
necessary
Competencies
PATH training
TRA, FMEA training
5Q’s implementation
49
COTENTS
1. Business Case
5. Teambuilding
Four stages of team building
Stage 4
Experimentation
Appropriate leadership
Risky issues debated
Methodical working Max. use of energy/ability
Wider options considered
Plus Agreed procedures Plus Essential principles & social aspects considered
Personal feelings raised
Established groundrules Needs of all met
More listening
Development & priority
Concern for others
Stage 3
Experimentation
Risky issues debated
Methodical working
Wider options considered
Plus Agreed procedures
Personal feelings raised
Established groundrules
More listening
Concern for others
Stage 2
Experimentation
Risky issues debated Performing
4 Fully effective
Wider options considered
Personal feelings raised team operations
More listening
Concern for others 3 Norming
Roles accepted
Stage 1 Unclear objectives Developing team
Low involvement in planning
Weaknesses covered up
Workplace is for work 2
Poor listening Storming
Feeling not dealt with Stressful negotiating of
Bureaucracy working terms
Established line prevails
No "rocking the boat"
Forming
Boss takes most decisions 1 Learning to deal with other
Minimal work achievement
51
Successful teams
Team
Monitor/evaluator Objective judge
synergy
52
Integrated Commissioning Team
Expert
PMC
Engineer’s
Integrate
Commissioning
Team
Sub-
Vendor’s
contractor
EPC
Contractor