MWTHOD STATEMENT FOR BUFFER TANKS INSTALLATION

(ACMV SYSTEM)

Document Control

Contract Number : Chiller Plant

Contract : CP Chiller Plant Room

Document Title : Method Statement for Buffer Tank BFT-R-03 and BFT- 4
Installation

Document : Revision ‘1’


Content

S/N Item Page

1.0 Brief Description 4

2.0 Preparation Works 4

3.0 Work Procedures 5

4.0 Work Areas 6

5.0 Work Schedule and Contact Person 6

6.0 Risk, Mitigation and Contingencies 7

Page 2 of 7
Method Statement for Buffer Tank BFT-R-03 and BFT-R-04 Installation

1. Brief Description

This method statement consists of methodology of installing below mentioned works

• Installation of Buffer Tank BFT-R-03 and BFT-R-04

2. Preparation Works

a) Conduct site survey.

b) Submit equipment layout and do marking on site.

c) Mobilization of materials, tools, equipment to site.

d) Apply for Permit-to-Work prior to commencement of work.

e) Get approval for isolation of fire alarm devices (Smoke detectors & beam
detectors) before start work.

f) Get approved shop drawing to start work.

g) Provide proper floor protection at the affected work area.

h) Erection of mobile scaffold or ladder to facilitate the installation works.

2.1 Material, Equipment and Tools

• Welding Machine
• Gas cutter
• Metal cutting machine
• Grinding machine
• Drill machine
• Chain Blocks
• Scissor Lift
• Lifting gears

Page 3 of 7
Revision ‘1’
March 2021
Method Statement for Buffer Tank BFT-R-03 and BFT-R-04 Installation

• Steel Hammer
• Torque wrench
• Hand tools

3. Work Procedures

3.1 Installation of Buffer Tank BFT-R-03 and BFT-R-04

a) The equipment location is marked on site and all the necessary material are
arranged to bring to lower roof.

b) The primary support which are the I beams are installed by securing onto the
existing Up-Stand RC Parapet using chemical bolts and nuts.

c) The buffer tank is hoisted through the opening of trellis to sit onto the
primary support.

d) The secondary support which serves as foundation for buffer tank is then
secured onto the primary support using bolts and nuts.

e) The four main support legs of the buffer tank are secured on top of the base
frame of the secondary support.

f) Those CHWS piping, butterfly valves connecting to buffer tank are supported
with beams which secured onto the existing up-stand RC parapet as well.

3.2 Post Completion of Work

a) Remove any floor protection and debris after completion of the work.
b) Clean the work area upon completion.
c) Ensure the smoke detectors and beams detectors are being normalized if
any.

Page 4 of 7
Revision ‘1’
March 2021
Method Statement for Buffer Tank BFT-R-03 and BFT-R-04 Installation

4. Work Areas

LOWER ROOF BUFFER TANK LOCATION

Page 5 of 7
Revision ‘1’
March 2021
Method Statement for Buffer Tank BFT-R-03 and BFT-R-04 Installation

5. Work Schedule & Contact Person

Duty Technician
Date/Time Work Description Engineer-in-charge
Contact Number

16 June 2021 Mani


To 8152 2812
Duty Technician
14 July 2021 Installation of Buffer Tank
8XXX XXX5
Sam
BFT-R-03 and BFT-R-04 9720 9628
8am to 10pm Daily

6. Risks / Mitigation / Contingencies

Risk:

• Trip and Fall


• Hand Cut

Mitigation:

• Proper Warning signage and Barricade opening of raise floor


• Wear hand gloves while cutting or drilling process • Safety boots to be worn
at all times during work process.
• Work to be supervised by a competent person.
• House Keeping

Contingencies Work:

If accident occurs, inform the respective Duty Engineer or Technician immediately


and wait for further instruction from Project Director or Project Manager. The

Page 6 of 7
Revision ‘1’
March 2021
Method Statement for Buffer Tank BFT-R-03 and BFT-R-04 Installation

respective duty team must know who is the first aider and where the first aid kit are
located

Page 7 of 7