CERTIFICATE OF COMPLETION

This is to certify that ABC CONSTRUCTION has completed the Supply and
Installation of STRUCTURAL WORKS with PEDRO BUILDER., at the Four
Storey Building Project owned by Ramirez Holdings. ,located at Munoz Edsa, Quezon
City, all in accordance with the approved plans, specifications and other related
subcontract documents.

The Subcontractor shall complete and correct the work in accordance with the punch
lists and the completion dates as approved by Pedro Builder.

Nothing contained herein shall be construed as to waive completely all rights of Pedro
Builder to reject the whole or any portion of the aforementioned work should the same
be found later to have been constructed or implemented in violation of the terms and
conditions of the Contract.

This CERTIFICATE OF COMPLETION is being issued this 02 day of June, 2014


for PO # 123456.

Recommending Approval : Approved by:

ENGR. PABLO PICASO ENGR. ROBIN HOOD


Project In-Charge Project Manager
Received by:

ABC CONSTRUCTION
(Subcontractor)