Professional Documents
Culture Documents
Where an exclusion zone is required, the SWMS must clearly state the detail of the required exclusion zone,
including the person responsible for implementation and supervision.
Work Location (Attach Site Plan): Refer Attachments Duration: From 18/01/2017 (Date) to 18/02/2017 (Date)
Remarks:
- Appendix A - SI Points layout.
- Appendix B - Loading unloading area and Mobile Crane movement route layout
2 Yes No
3 Yes No
4 Yes No
5 Yes No
6 Yes No
7 Yes No
8 Yes No
2 Lifting Supervisor
3 Supervisor
6. Traffic Controller
7. Rigger
8. Signal Man
Name: Jeganathan Nair Signed: Name: Kevin Che Kam Seng Signed:
Designation: Safety and Health Officer Date: ……17…. /…1……. /……17…. Designation: Project Manager Date: …17……. /……1…. /…17…….
Applicable Environment, Safety & Health (ES&H)
Risk Assessment Team Approved Code of Practice (COP) and/or CSR
Legislation
Name Designation Signature
NO Job Steps Hazard Risk Risk Control / Control Measures L I Risk Accountable Person
Rating
- Delivery of SI Equipment, Lorry Crane & Mobile Uncontrolled traffic / Major injury due to contact with Designated & Trained Traffic controllers to be assigned. 2 4 Moderate Supervisor
Crane to worksite vehicle movement moving vehicles or machineries Traffic controller to be equipped with whistle, high visibility clothing & batons/ flags
Proper signage to be placed to warn the public
- Use Of Lorry / truck Mounted Crane to Unsafe lorry crane Major injury due to contact with To use competent operator & rigger 1 4 Minor Lifting Supervisor
unload the SI Equipment &lifting operation load or machinery during lifting Lifting Gears & Crane to be inspected & with valid fitness certificates
operation Truck to be levelled and outriggers fully extended.
Steel plates to be provided for padding.
To lift using designated lifting points only
To only use tested and certified lifting gears & equipment only
Barricade the work area
- Mobilization of boring rigs/SI machines to boring Unsafe lifting operation Major injury due to contact with To use competent operator 1 4 Minor Lifting Supervisor
points / work areas by using mobile crane load or machinery during lifting Crane to be inspected & with valid fitness certificates
operation Crane to use 1m x 1m steel plate for out riggers
Out riggers to be fully extended
Wheels to be slightly above the ground
Crane to be balanced -refer level meter / water leveller on the body
Barricade the work area
Unsafe slinging Major injury due to material fall To use competent rigger 1 4 Minor Lifting Supervisor
To use tested and certified slings & lifting gears
To lift using designated lifting points only
No overhead lifting or standing under suspended load
- Assembly of SI Boring Rig To Attach the Tripod Unstable ground Major injury due to toppling of Ensure ground is stable and levelled 1 3 Minor Supervisor
Frame Tripod frames
Unsafe Tripod structure Major injury due to collapse of Ensure all structure is in good condition 1 3 Minor Supervisor
Tripod structure Secure the Tripod to the main frame once in vertical position
- Setting Up Compressors and water Pumps Unsecured hose & Major injury due to hit or Proper hose & connectors to be used 1 4 Minor Supervisor
connectors contact with high pressure Test the hose and connection with 110% of the normal usage pressure
release
1 4 Minor Supervisor
Unprotected rotating Major injury due to contact with All rotating parts and heating elements of the compressor and water pump to be
parts and heating rotating equipment and heating fitted with machine guarding
elements element of the compressor and
water pump
1 4 Minor Supervisor
- Soil Drilling / Boring & Rock Probing for Unprotected rotating Major injury due to contact with All rotating parts and heating elements of the boring rig to be fitted with machine
sampling. parts and heating rotating equipment and heating guarding
elements element of the boring rig
Inadequate access for Minor to major injury due to fall Proper access ladders to be provided on the Tripod Frame for access during 1 4 Minor Supervisor
mast/ tripod climbing while climbing the Tripod changing of drilling rods.
Frame Safety Harness to be worn to access the pulley or top of the Tripod frame
- Housekeeping Poor housekeeping Minor to major injury due to Regular housekeeping during work progress 1 3 Minor Supervisor
poor housekeeping Proper waste segregation, collection and removal (i.e. construction and Schedule
Wastes)
- Weather Condition Unsafe weather Major injury due to working in To stop work during unfavourable / extreme weather conditions (rain, storm, 1 4 Minor Supervisor
condition extreme weather conditions strong wind, etc)
- Welfare facilities Inadequate welfare Unavailability of welfare To provide First Aider & First Aid Box 1 4 Minor Supervisor & SHO
facilities facilities may limit assistance To ensure availability of drinking waters & shelters for resting.
during emergencies
- Use Of Lorry / truck Mounted Crane to Lifting supervisor with the truck mounted crane operator to check the crane and all slings and
unload the SI Equipment liftin equipment / lifting gears. Inspection to be recorded and kept at work area and filed upon
completion of work.
Work area to be barricaded to prevent unauthorised entry using hard barriers.
Outriggers to be fully extended and steel plates used as padding.
Truck to be levelled and stable condition.
Load being lifted should not be more than 80% of the crane’s maximum capacity along the
lifting radius and unloading point (locations to be predetermined and verified by the Lifting Lifting
supervisor to confirm this) Supervisor
Lifting of material then shall be done by competent operator (competencies to be verified
prior to lifting by the Lifting Supervisor) of lorry crane and shall be assisted by lifting
supervisor and 2 riggers.
Loads to be hooked to a designated and engineered lifting points only.
Total load distribution to the slings should not be more than 80% of its capacity. Total loading
to the sling need to be also based on the number of slings and method of slinging.
All Lifting hooks must be fitted with safety latch.
- Mobilization of boring rigs/SI machines to To use 20t or more crane to shift the SI machines to the work areas Crane & Lifting Lifting
boring points / work areas by using mobile Supervisor and operator to inspect the ground condition along the crane movement routes. Equipment Inspection Supervisor &
crane Where unsuitable grounds suspected further assessment to be conducted by a competent Checklist Operator
Geotech Engineer.
Lifting Supervisor and operator to inspect the crane and all the lifting equipment / gears to
ensure they are all in good condition, properly rated, tested with tags displayed and meets
the capacity needed for the lifting activity.
AJ 001 _Rev 0 Page 7 of 10
Steel plates to be laid along the crane movement routes where necessary.
Crane to be parked with outriggers fully extended and lifted to level the crane in a balanced
position. 1m x1m steel plates to be placed for load distribution of the mobile crane outriggers.
All the wheels/ tyres of the crane must be slightly above the ground.
To lift the boring rigs and other equipment to the work area. To only use the designated lifting
points.
No overhead lifting is allowed and workers not to stand under any suspended loads.
Assembly of SI Boring Rig To Attach the Setup the boring rig at the drilling point. Ensure ground is levelled. Ensure all the rotating
Tripod Frame parts and heating elements are adequately and neatly protected using metal plates or steel
mesh.
Ensure drip trays are positioned under the boring rig to capture and oil leak or spillage.
Place the Tripod frame on a horizontal position in front of the boring rig for lifting and
assembly.
Ensure Tripod frame structures and joints are in good condition.
To ensure pulleys at the top of the frame is in good condition and fitted with guide bar to
prevent dislodging of wire rope during operation. To ensure proper access is inbuilt to the Supervisor
Tripod Frame for climbing purposes during the operation.
Ensure the ground is levelled prior to placing the boring rig and Tripod frame.
Hook the boring rig’s lifting sling to the Tripod Frame and lift slowly to the vertical position.
Balancing of the tripod to be ensured during the process.
Once vertically positioned the tripod to be secured to the main frame of the boring rig to
become one complete unit.
Attach the drilling rods to the boring rig by lifting it using the lifting sling.
- Setting Up Compressors and water Pumps Ensure all the rotating parts and heating elements of the compressors and water pumps are
adequately and neatly protected using metal plates or steel mesh.
To ensure all the hoses are in good condition and connected using proper connectors.
Test the compressor with and additional 10% of the pressure used during normal operation.
Supervisor
Check back the hoses and connections to ensure they are still intact
Stop operation if any loose connections or leaks observed and rectify immediately.
To dig a small pond of not more than 400mm deep to manage the runout water during boring
activity. Hard barriers to be provided around the pond for identification and warning.
Continue to bore once all the setup is checked and verified by the supervisor. N95 type of mask to be Supervisor
- Soil Drilling / Boring & Rock Probing for Drill to the depth required and do sampling at intervals as stated or agreed in the method used dust cannot be
sampling. statement. controlled.
Water to be used to minimise any dust pollution.
Ensure proper access is provided for access to the tripod frame for slinging and unslinging
during changing of the drilling rods.
Safety Harness to be worn and hooked at highest point if need to access to the top of the
Tripod frame or pulley.
Not to store or keep materials around the areas where access is required to operate the rig
Section 3: Verification
I have provided, accurate and sufficient information and instructions pertaining to this Safe Work Method Statement - the aspects / hazards associated with each work process and activity, the type of potential impact,
incident or accident, and the risk controls / practicable measures to be taken in the course of work and during an emergency - to ensure its / their safe undertaking.
Instructed by (print name): …………………………………………………………………….. Signed: ………………………………………….. Date: …..../…...../……… Time: .............. am / pm