SESSION PLAN

Sector : HEATING, VENTILATION, AIR-CONDITIONING AND REFRIGERATION TECHNOLOGY SECTOR

Qualification Title : RAC SERVICING PACKAGE-TYPE AIR-CONDITIONING UNIT AND COMMERCIAL


REFRIGERATION EQUIPMENT (PACU/CRE) NC III

Unit of Competency: PERFORM START-UP, TEST AND COMMISSIONING FOR PACKAGE-TYPE AIR-
CONDITIONING UNIT

Module Title : PERFORM STARTING-UP, TESTING AND COMMISSIONING FOR PACKAGE-TYPE AIR-
CONDITIONING UNIT

Learning Outcomes:

LO1 Prepare for start-up, test and commissioning of PACU

LO2 Conduct start-up, test and commissioning of PACU

Date Developed: July 2022 Document No.


RAC SERVICING (PACU/CRE) NC IIII Issued by:
Date Revised:

Developed by: Page 1


Session Plan
PERFORM START-UP, TEST AND Revision # 00
COMMISSIONING FOR PACKAGE-TYPE Caeyh Rhumcess O. Guiang
AIR-CONDITIONING UNIT
A. INTRODUCTION

This unit competency covers the knowledge, skills and attitudes in performing start-up, test and commissioning in the
package type air-conditioning unit (PACU).

B. LEARNING ACTIVITIES

LO 1: Prepare for start-up, test and commissioning of PACU

Learning Content Methods Presentation Practice Feedback Resources Time

● Self-paced learning ● Read Answer Evaluate ● CBLM 8


Commissioning ● Lecture information the ● SmartTV
Self Check hours
instruments ● Video Presentation sheet 7.1-1 answers to ● White
7.1-1
Commissioning answer key Board
instrument 7.1-1

Date Developed: July 2022 Document No.


RAC SERVICING (PACU/CRE) NC IIII Issued by:
Date Revised:

Developed by: Page 2


Session Plan
PERFORM START-UP, TEST AND Revision # 00
COMMISSIONING FOR PACKAGE-TYPE Caeyh Rhumcess O. Guiang
AIR-CONDITIONING UNIT
● Discuss ● Marker
Commissioning
instruments
● Multimedia
presentation of
Commissioning
instruments

● Demonstration The trainer will Perform job Refer on


demonstrate on sheet 7.1-1 performanc
how to evacuate/ e criteria
evacuate/
vacuuming the checklist
vacuuming
system. the system 7.1-1

evacuate/
vacuuming

Date Developed: July 2022 Document No.


RAC SERVICING (PACU/CRE) NC IIII Issued by:
Date Revised:

Developed by: Page 3


Session Plan
PERFORM START-UP, TEST AND Revision # 00
COMMISSIONING FOR PACKAGE-TYPE Caeyh Rhumcess O. Guiang
AIR-CONDITIONING UNIT
the system.
LO 2: Conduct start-up, test and commissioning of PACU

Learning Content Methods Presentation Practice Feedback Resources Time

● Self-paced learning ● Read Answer Evaluate ● Laptop 16


Electrical checks ● Video Presentation information the ● Smart TV hours
Self Check
sheet 7.2-1 on answers to ● Manufact
7.2-1
Electrical answer key urer's
electrical
checks 7.2-1 manual
checks
● Multimedia electrical
presentation of checks
Electrical
checks

Date Developed: July 2022 Document No.


RAC SERVICING (PACU/CRE) NC IIII Issued by:
Date Revised:

Developed by: Page 4


Session Plan
PERFORM START-UP, TEST AND Revision # 00
COMMISSIONING FOR PACKAGE-TYPE Caeyh Rhumcess O. Guiang
AIR-CONDITIONING UNIT
The trainer will Perform task Refer on
● Demonstration demonstrate the sheet 7.2-1 performanc
standard procedure e criteria
electrical
on how to check checklist
checks
voltage and current. 7.2-1

electrical
checks
● Self-paced learning ● Read Answer Evaluate ● CBLM 16
Refrigerant piping checks ● Lecture information ● Projector hours
Self Check the answer
sheet 7.2-2 ● Laptop
to answer
7.2-2
Refrigerant Power
key 7.2-2
Refrigerant
piping checks Point
piping checks Refrigerant
● Letting the Presentat
piping
trainees to ion
checks
familiarize ● Manufact

Date Developed: July 2022 Document No.


RAC SERVICING (PACU/CRE) NC IIII Issued by:
Date Revised:

Developed by: Page 5


Session Plan
PERFORM START-UP, TEST AND Revision # 00
COMMISSIONING FOR PACKAGE-TYPE Caeyh Rhumcess O. Guiang
AIR-CONDITIONING UNIT
Refrigerant urer's
piping checks manual

● Demonstrate The trainer will Perform task Refer on


demonstrate the sheet 7.2-2 performanc
standard on how to e criteria
Refrigerant
check the checklist
piping checks
refrigerant 7.2-2
pressure. Refrigerant
piping
checks
Condensing unit checks ● Self-paced learning ● Read Answer Evaluate ● CBLM 16
● Lecture information ● Projector hours
Self Check the answer
sheet 7.2-3 ● Laptop
to answer
7.2-3

Date Developed: July 2022 Document No.


RAC SERVICING (PACU/CRE) NC IIII Issued by:
Date Revised:

Developed by: Page 6


Session Plan
PERFORM START-UP, TEST AND Revision # 00
COMMISSIONING FOR PACKAGE-TYPE Caeyh Rhumcess O. Guiang
AIR-CONDITIONING UNIT
Condensing Condensing key 7.2-3 Power
unit checks unit checks Point
Condensing
● Letting the Presentat
unit checks
trainees to ion
familiarize ● Manufact
Condensing urer's
unit checks manual
● Demonstrate The trainer will Perform task Refer on
demonstrate the sheet 7.2-3 performanc
standard on how to e criteria
Condensing
check the checklist
unit checks
condenser 7.2-3
temperature and
condenser fins.
Compressor unit checks ● Self-paced learning ● Read Answer Evaluate ● CBLM 16

Date Developed: July 2022 Document No.


RAC SERVICING (PACU/CRE) NC IIII Issued by:
Date Revised:

Developed by: Page 7


Session Plan
PERFORM START-UP, TEST AND Revision # 00
COMMISSIONING FOR PACKAGE-TYPE Caeyh Rhumcess O. Guiang
AIR-CONDITIONING UNIT
● Lecture information Self Check the answer ● Projector hours
● Video Presentation sheet 7.2-4 to answer ● Laptop
7.2-4
Compressor key 7.2-4 Power
Compressor
unit checks Point
unit checks Compresso
● Letting the Presentat
r unit
trainees to ion
checks
familiarize ● Manufact
Compressor urer's
unit checks manual
● Viewing the
video
● Demonstrate The trainer will Perform task Refer on
demonstrate the sheet 7.2-3 performanc
resistance checking e criteria
Compressor
on the compressor checklist
unit checks

Date Developed: July 2022 Document No.


RAC SERVICING (PACU/CRE) NC IIII Issued by:
Date Revised:

Developed by: Page 8


Session Plan
PERFORM START-UP, TEST AND Revision # 00
COMMISSIONING FOR PACKAGE-TYPE Caeyh Rhumcess O. Guiang
AIR-CONDITIONING UNIT
unit. 7.2-3

compressor
unit checks
Indoor unit checks ● Self-paced learning ● Read Answer Evaluate ● CBLM 8
● Lecture information ● Projector hours
Self Check the answer
● Video Presentation sheet 7.2-5 ● Laptop
to answer
7.2-5
Indoor unit Power
key 7.2-5
Indoor Unit
checks Point
checks Indoor unit
● Letting the Presentat
checks
trainees to ion
familiarize ● Manufact
Indoor unit urer's
checks manual
● Viewing the

Date Developed: July 2022 Document No.


RAC SERVICING (PACU/CRE) NC IIII Issued by:
Date Revised:

Developed by: Page 9


Session Plan
PERFORM START-UP, TEST AND Revision # 00
COMMISSIONING FOR PACKAGE-TYPE Caeyh Rhumcess O. Guiang
AIR-CONDITIONING UNIT
video
● Demonstrate The trainer will Perform task Refer on
demonstrate the sheet 7.2-5 performanc
temperature e criteria
Indoor unit
checking in the checklist
checks
indoor room. 7.2-5

Indoor unit
checks

C. ASSESSMENT PLAN

● Written Test
● Performance Test
● Demonstration
D. TEACHER’S SELF-REFLECTION OF THE SESSION

Date Developed: July 2022 Document No.


RAC SERVICING (PACU/CRE) NC IIII Issued by:
Date Revised:

Developed by: Page 10


Session Plan
PERFORM START-UP, TEST AND Revision # 00
COMMISSIONING FOR PACKAGE-TYPE Caeyh Rhumcess O. Guiang
AIR-CONDITIONING UNIT
Date Developed: July 2022 Document No.
RAC SERVICING (PACU/CRE) NC IIII Issued by:
Date Revised:

Developed by: Page 11


Session Plan
PERFORM START-UP, TEST AND Revision # 00
COMMISSIONING FOR PACKAGE-TYPE Caeyh Rhumcess O. Guiang
AIR-CONDITIONING UNIT

You might also like