Professional Documents
Culture Documents
Civil Measurement - CESMM Introduction - Pre Recording
Civil Measurement - CESMM Introduction - Pre Recording
measurement
CESMM 4 Revised
Ravindu Kahandawa
Use the definitions when
reading this document if not
specified different in the
context
Work means work, liabilities,
obligations and risks
undertaken by the contract
1
Contract admin can be the
employer or his rep or agent
Commencement level –
• Level before any work is
1 carried out
• If it’s a group of work
items, (example
excavation, bored, drilled
2 or driven hole in different
materials,) surface of the
ground before work
started by that set of
items
Excavated surface
3
• To the level that item
excavates to
• IF its group of items – to
the level all items
4 excavate to
means
Maximum excavation
depth for topsoil is
between 5m and
10m
End of section
1
Use the standard only for CIVIL work and
simple building work related to Civil work
To gain these
objectives,
1. different BOQ
CESMM shows items should be
2 there for, Different
• How work
should be work classes,
divided into Different nature of
sections work, Or changes
3 in cost
• What details
should be 2. But make the BOQ
given in the as brief and simple
description as possible
• Unit 4
• How the Defined work should
measure the be covered by the BOQ
items
End of section
2
Has 26 classes,
• Each class three divisions
which describes the work
• Each division has 8 descriptive
features of work
• Each item should only cover
one feature from each division
1
E.g. - Precast concrete (class H)
• Type of concrete unit (division
1). Dimension (division 2),
Mass (division 3)
2 E.g., Pipes
• division classifies pipes =
material (division 1), nominal
bore of the pipe (division 2),
3 and the depth Commencing
Surface (division 3).
5
Section 3 - Application of the work Classification
5
Format
Format
A double line means
applies to below items
2 Code is note
• Its not part of the
3 description
• Do not use it to
interpret the contract
4
• Use the full description
the describe the item,
not the code
Section 4 - Coding and numbering items
3
End of section
4
These provisions apply for
completed work
measurement too
Sub headings
Numbering
Example for
BOQ page
Line ending the
section to which
the headings and
sub headings
apply
Section ending
line
Section 5
1 -
Preparation of the Bill
of Quantities
tenderers cannot be told
2 what is required, they
must not be asked to say
what it will cost.
Added contingencies to
provisional sums and
show in the grand
summary -
3
Measure –
• Net
• according to drawings,
unless mentioned
otherwise in CESMM 4
or Contract
• NO bulkage, shrinkage
or waste
Section 5
1 -
Preparation of the Bill
of Quantities
1. Excavations
2 1. Original surface
not commencing
surface - Mention
the commencing
level
3 2. Final surface not
excavated surface
– mention
excavated surface
Give details about 3. Depth –
1. Total of each page – totalled Commencement
bodies of water and carried to summary of each
affecting the site surface to
section excavated surface
2. Total of each section – carried to
grand summary
1 Section 5
-
Preparation of the Bill
2 of Quantities
Tabulated summary of
3 sections
5
Adjustment item
• Rules do not explain what the Adjustment Item is for. It only explains what
they are used for
• Its object is to provide a convenient place at the end of a bill where the
tenderer can make an adjustment without altering rates and amounts
within the work items themselves
• Example
• You receive a supplier quote ( which lower than estimated) at the last minute for
earthmoving and no time to change the BOQ. So the adjustment is used to make the
change
• Final review by the senior staff, requires the OH/P to change in the whole BOQ
• Mainly helpful for the tenderer
• To clients only benefit is to eliminate irrational pricing of ordinary general
items.
Adjustment item
• For interim payments (6.4)
• Mainly for lump sum amounts
• adjustment item should also be adjusted for inflation.
• Changes made pro rate to the value of work done until calculation gives the full value
• Preamble should mention how its calculated
• If the full amount is not paid after completion of work, next interim certificate after
the completion should certify the full amount.
• If you want to limit the use of “the Adjustment items” mention them in his
instructions
• This amount of ADJUSTMENT ITEM would not change dues variations in
work.
• This will not be deleted even if the relevant item is removed. SO be careful
in use.
Adjustment
A Preamble should
mention show method
related charges are paid
4
Only changes due to
variations instructed by
contract admin
e.g. Variation of method-related charges
• Time-Related Charge for operating a batching plant
• A variation to work may increase the volume of concrete – not applicable
• variation produces a significant lengthening of the time of operation of the
batching plant – increase in Time related cost
Method related charges
• If there is a change in the Method related charges
• Reach an agreement on how to pay it
• if ready-mixed concrete is being used instead of a site batching plant – a batching plant
will be paid pro rata
• No agreement – it becomes an adjustment item
• Paid pro rata until the tender sum is reached
Method related charges
• Method-related charges are adjusted according to price fluctuations
• The Main contractor can ask the subcontractor can give their method-
related charges
• Sub contractor can include a normal rate to the main contractor
• Which the Main contractor can divide into method-related charges
• Sub contractor can include a method-related charges to the main contractor
• Contractor can use them as is
• Contractor can use them + add their mark up
• Include them in other rates
• Method-related charges most included –
• At the beginning of each bill with sub-sections or
• More convenient to - Keep them in Class A while describing which permanent work
it relates to
End of section
7