Client
Document title
Document date
13.11.2019
Revision: 0
In association with
C:\Users\zoran.cvetkovic\Documents\Bimasa\Toplane\Prijepolje\Prijepolje_Detaljni_Investicioni_Plan_2019.docx
Implementation of Promotion of Renewable Energies – Developing the Biomass Market in Serbia CES/decon
Biomass Project Toplana of Prijepolje: Detailed Investment Plan and Results of the Financial Model 13.11.2019
DATE: 13.11.2019
Checked Approve
Date Revision No. Editor Signature Description
by d by
Revision: 0 Page 2
Implementation of Promotion of Renewable Energies – Developing the Biomass Market in Serbia CES/decon
Biomass Project Toplana of Prijepolje: Detailed Investment Plan and Results of the Financial Model 13.11.2019
CONTENT
1. Introduction ..................................................................................................................... 5
2. Technical Description of the Project .................................................................................. 6
2.1. Project Site ................................................................................................................................. 6
2.2. Heating Station ........................................................................................................................... 6
2.3. Network ...................................................................................................................................... 6
2.4. Heating Sub-Stations .................................................................................................................. 9
3. Fuels used ...................................................................................................................... 11
3.1. Outlook for the Project............................................................................................................. 11
3.2. Brijeg......................................................................................................................................... 11
3.3. Fuel Demand of the Toplana .................................................................................................... 12
4. Reduction of CO2 and SO2 Emissions ................................................................................ 13
5. RevisED Investment Plan................................................................................................. 14
6. Financial Modelling and results ....................................................................................... 15
6.1. Brief Analyis of The Toplana Financial Situation ...................................................................... 15
6.2. Basic Elements and Assumptions for the Biomass Plant Modelling ........................................ 15
6.3. Tariff Increased ......................................................................................................................... 16
Annex 1: Cash Flow Statement .................................................................................................... 17
Annex 2: Layout Plan of the Heating Plant ................................................................................... 18
TABLES
FIGURES
Revision: 0 Page 3
Implementation of Promotion of Renewable Energies – Developing the Biomass Market in Serbia CES/decon
Biomass Project Toplana of Prijepolje: Detailed Investment Plan and Results of the Financial Model 13.11.2019
Abbreviations
BH Boiler house
BoQ Bill of Quantities
BS Balance Sheet
CAPEX Capital Expenditures
CES Clean energy solutions GesmbH (consultant)
CHP Combined Heat and Power (cogeneration)
CO2 Carbon dioxide
CPIU Central Project Implementation Unit (Team in the MoME)
CS Cash Flow Statement
DCS Distributed control system
decon decon international (consultant)
DH District heating
DHC District heating company (or toplana)
DLP Defects Liability Period (or DNP Defects Notification Period)
DNP Defects Notification Period (or DLP Defects Liability Period)
DSR Debt Service Coverage Ratio
FIDIC International Federation of Consulting Engineers
HDD Heating degree days
HFO Heavy gas oil (Gas)
HOB Heat-only boiler
ICB International Competitive Bidding
IHS Individual heating sub-station (mostly on building level)
IRR Internal Rate of Return
IS Income Statement
kJ Kilo Joule (unit used for LCVs)
JP Javno Preduzeće (public company)
JKP Javno Komunalno Preduzeće (public communal company)
KfW Kreditanstalt für Wiederaufbau (the bank)
kWh Kilowatt hour (unit for electric energy)
LCV Lower calorific value (or lower heating value)
LFO Light Gas Oil
MW Megawatt (capacity)
MWh Megawatt-hours (energy)
MoME Ministry of Mining and Energy (of Serbia)
OPEX Operational expenditures
PB (FIDIC) Pink Book
PEA Project Executing Agency (Municipality or Toplana)
PIMO Public Investment Management Office
PIU Project Implementation Unit (Team in the PEA)
RB (FIDIC) Red Book
RSD Serbian Dinar (currency unit of the republic of Serbia)
SCADA Supervisory Control and Data Acquisition (control system)
SCO Suisse Co-operation Office
SO2 Sulphur dioxide
TA Technical Assistance
Revision: 0 Page 4
Implementation of Promotion of Renewable Energies – Developing the Biomass Market in Serbia CES/decon
Biomass Project Toplana of Prijepolje: Detailed Investment Plan and Results of the Financial Model 13.11.2019
1. INTRODUCTION
This report summarizes the Consultants findings and recommendation for the further
implementation of the Biomass Plant for the Toplana of Prijepolje. The findings are based on the
revision of the preliminary investment plan and on the interactions with the financial analysis and
checking further relevant issues such as current state of project preparations by the Toplana. A
detailed pre-feasibility report has been elaborated and presented by CES and been approved by KfW
and the MoME in 2016.
There are only minor changes in the project compared to the PFS from 2015/16. The differences are
described briefly in the following sections. For project details please refer to the above mentioned
PFS report. The new boiler station will be equipped with a 1.8 MW boiler on LFO to act together with
the boiler house “Gymnazija” as back-up system. The boiler house “Valter” will be decommissioned.
Revision: 0 Page 5
Implementation of Promotion of Renewable Energies – Developing the Biomass Market in Serbia CES/decon
Biomass Project Toplana of Prijepolje: Detailed Investment Plan and Results of the Financial Model 13.11.2019
The plot is the same like that described in the PFS report of 2015/16. On the western part of the plot
there is the gymnasium of Prijepolje. The plot will be split and the eastern part (with the small
football field) will be the site for the biomass heating station.
The heating station comprises of following main components which are necessary for a proper
function such as:
The heating station “Gymnazia” with a 3.5 MW boiler on mazut will be integrated into the new DH
system.
2.3. NETWORK
There are no changes compared to the PFS from 2015/16. The network of “Brijeg” will stay as
separate network with a boiler house on mazut. All other networks will be merged to one network.
Route
DN Type of pipe Comment
length (m)
40 103,1 DRE 40/110 standard New
40 39,2 DRE 40/110 standard New
200 27,2 DRE 200/315 standard Replace
150 140,2 DRE 150/250 standard New
150 59,7 DRE 150/250 standard Replace
80 65,1 DRE 80/160 standard New
65 25 DRE 65/140 standard New
80 34,5 DRE 80/160 standard New
100 35,8 DRE 100/200 standard Replace
100 42,9 DRE 100/200 standard New
80 129 DRE 80/160 standard Replace
80 27,1 DRE 80/160 standard Replace
65 22,8 DRE 65/140 standard New
65 86,5 DRE 65/140 standard New
32 20,4 DRE 32/110 standard New
50 21,7 DRE 50/125 standard New
32 30,7 DRE 32/110 standard New
Revision: 0 Page 6
Implementation of Promotion of Renewable Energies – Developing the Biomass Market in Serbia CES/decon
Biomass Project Toplana of Prijepolje: Detailed Investment Plan and Results of the Financial Model 13.11.2019
Revision: 0 Page 7
Implementation of Promotion of Renewable Energies – Developing the Biomass Market in Serbia CES/decon
Biomass Project Toplana of Prijepolje: Detailed Investment Plan and Results of the Financial Model 13.11.2019
Revision: 0 Page 8
Implementation of Promotion of Renewable Energies – Developing the Biomass Market in Serbia CES/decon
Biomass Project Toplana of Prijepolje: Detailed Investment Plan and Results of the Financial Model 13.11.2019
The list below shows the buildings, which will be connected to the new network and to be equipped
with new heating sub-stations.
Type of
Building IHS capacity
consumer
Dečiji vrtić "Miša Cvijović" public 120 kW
Nacionalna služba za zapošljavanje public 160 kW
Osnovna Škola Valter public 610 kW
residential
Centrala "C1" 100 kW
commercial
residential
Centrala "C2" 150 kW
commercial
Centrala "C3" residential 50 kW
Centrala "C4" residential 150 kW
residential
Podvaroš 8 120 kW
commercial
residential
Podvaroš 7 160 kW
commercial
residential
Podvaroš 6 60 kW
commercial
residential
Podvaroš 5 160 kW
commercial
residential
Podvaroš 4 70 kW
commercial
residential
Podvaroš 3 170 kW
commercial
residential
Podvaroš 2 80 kW
commercial
residential
Podvaroš 1 150 kW
commercial
residential
Pijaca I 120 kW
commercial
Pijaca II residential 120 kW
residential
Pijaca III 130 kW
commercial
Pijaca IV residential 120 kW
Poslovni niz commercial 50 kW
Opštinska uprava public 190 kW
Muzej public 70 kW
residential
Apoteka 220 kW
commercial
Gimnazija public 830 kW
Šehovića Polja - Stara zgrada residential 380 kW
Revision: 0 Page 9
Implementation of Promotion of Renewable Energies – Developing the Biomass Market in Serbia CES/decon
Biomass Project Toplana of Prijepolje: Detailed Investment Plan and Results of the Financial Model 13.11.2019
residential
Šehovića Polja - Nova zgrada 380 kW
commercial
EPS public 90 kW
Vrtic (Gimnazija) public 110 kW
Dom Kulture public 630 kW
Indoor swimming pool public 400 kW
Total 6 150 kW
Table 2: List of Heating Sub-stations
Revision: 0 Page 10
Implementation of Promotion of Renewable Energies – Developing the Biomass Market in Serbia CES/decon
Biomass Project Toplana of Prijepolje: Detailed Investment Plan and Results of the Financial Model 13.11.2019
3. FUELS USED
In Prijepolje it has to be considered, that the project does not affect the entire Toplana’s heating
system. The network of “Brijeg” stays as separate DH system with its boilers on Mazut.
The chart below shows the fuels used in the future by the new heating station (without the network
of “Brijeg”). After the implementation of the project approx. 95% of the total heat will be generated
by the biomass boiler.
3.2. BRIJEG
The network of “Brijeg” will be operated as usual and will not be affected by the project. Therefor
the Mazut demand will develop as expressed in the chart below.
Revision: 0 Page 11
Implementation of Promotion of Renewable Energies – Developing the Biomass Market in Serbia CES/decon
Biomass Project Toplana of Prijepolje: Detailed Investment Plan and Results of the Financial Model 13.11.2019
Revision: 0 Page 12
Implementation of Promotion of Renewable Energies – Developing the Biomass Market in Serbia CES/decon
Biomass Project Toplana of Prijepolje: Detailed Investment Plan and Results of the Financial Model 13.11.2019
The proposed project will significantly contribute to the reduction of annual CO2 and SO2 Emissions
as presented in the table below:
CO2 SO2 1
No project 2880 tons/yr 14,7 tons/yr
With project 590 tons/yr 6,2 tons/yr
Reduction 2290 tons/yr 8,5 tons/yr
Reduction 80% 58%
Program target indicators 70% 70%
The network of “Brijeg” is not affected by the project and it will be operated as a separate
network with boilers on mazut and
The boiler house “Gymnazija” on Mazut will act as back-up boiler with its SO2 emissions
Therefor the program target indicator for SO2 emissions cannot be achieved.
The CO2 and SO2 emission reductions have been achieved due the high share of renewables
combined with heat loss reductions due to the new equipment like boilers, pre-insulated pipes,
automatic controlled substations and the proposed SCADA.
It should be noted, that in the financial modelling no costs for CO2 Emissions are considered, but it
could be expected that in the future environmental costs be to be added.
1
According to Annex 1 “Objectives and Results of the Program and Assumptions/Risks for their Achievement” only applicable to fuel
switches from Mazut
Revision: 0 Page 13
Implementation of Promotion of Renewable Energies – Developing the Biomass Market in Serbia CES/decon
Biomass Project Toplana of Prijepolje: Detailed Investment Plan and Results of the Financial Model 13.11.2019
Main Complem.
Cost component Total
Investment Measures
Mechanical components € 1.010.000 € - € 1.010.000
Civil works € 500.000 € - € 500.000
E&C installations € 160.000 € - € 160.000
Commissioning € 90.000 € - € 90.000
Network replacements € - € 310.000 € 310.000
Sub-stations € - € 190.000 € 190.000
SCADA € - € 30.000 € 30.000
Contingencies 10% € 176.000 € 53.000 € 229.000
General contractor's fee 0% € - € - € -
Engineering € - € - € -
Total € 1.936.000 € 583.000 € 2.519.000
Revision: 0 Page 14
Implementation of Promotion of Renewable Energies – Developing the Biomass Market in Serbia CES/decon
Biomass Project Toplana of Prijepolje: Detailed Investment Plan and Results of the Financial Model 13.11.2019
The financial analysis based on the financial reports of JKP "LIM", Prijepolje (BS, IS, CS) for the years
2015 – 2018.
The brief analysis of the available data of the DH sector only shows that the revenues of this sector
are not covering its operational costs. See below the relevant DH sector figures for the years 2015-
2018 below:
6.2. BASIC ELEMENTS AND ASSUMPTIONS FOR THE BIOMASS PLANT MODELLING
Revision: 0 Page 15
Implementation of Promotion of Renewable Energies – Developing the Biomass Market in Serbia CES/decon
Biomass Project Toplana of Prijepolje: Detailed Investment Plan and Results of the Financial Model 13.11.2019
Annual efficiency 85% State of the art for new biomass plant
new bio mass plant
Table 6: Selected basic elements of the financial modelling of the new biomass plant
Other OPEX items are based on the Toplanas historical data and projected in the future. Details can
be found in the financial model (separate EXCEL file).
A summary of the cash flow and DSCR development of this option is presented in Annex 1.
Revision: 0 Page 16
Implementation of Promotion of Renewable Energies – Developing the Biomass Market in Serbia CES/decon
Biomass Project Toplana of Prijepolje: Detailed Investment Plan and Results of the Financial Model 13.11.2019
Business Year Total 2020 2021 2022 2023 2024 2025 2026 2027 2028 2029 2030 2031 2032 2033 2034 2035 2036
Total Revenues 15.990 497 497 838 773 744 744 744 744 744 744 744 744 744 743 743 743 743
Opex (7.760) (483) (483) (384) (363) (353) (351) (348) (346) (344) (342) (340) (338) (337) (335) (333) (331) (329)
Major Overhaul Expenditures - - - - - - - - - - - - - - - - - -
Cash Change in Working Capital - (4) - (108) 11 5 (1) (0) (0) (0) (0) (0) (0) (0) (0) (0) (0) (0)
Tax (875) (2) (2) (48) (42) (39) (40) (40) (41) (41) (42) (42) (43) (43) (44) (44) (45) (45)
Interest Income on DSRA - - - - - - - - - - - - - - - - - -
Operating Cash Flows after WC and Tax 7.355 9 13 298 379 357 353 355 356 358 359 361 362 363 365 366 367 369
CFADS 7.355 9 13 298 379 357 353 355 356 358 359 361 362 363 365 366 367 369
Interest Senior Debt (227) - - (23) (22) (21) (20) (18) (17) (16) (15) (13) (12) (11) (10) (8) (7) (6)
Principal Senior Debt (2.105) - - (106) (108) (109) (110) (111) (112) (114) (115) (116) (117) (119) (120) (121) (123) (124)
Cash Available to Equity 5.004 9 13 167 249 226 223 224 226 227 229 230 232 233 234 236 237 238
Dividends and Equity Redemption (5.004) - - (189) (249) (226) (223) (224) (226) (227) (229) (230) (232) (233) (234) (236) (237) (238)
9 22 - - - - - - - - - - - - - - -
Cash Balance C/f
DSCR n/a n/a 2,28 x 2,91 x 2,73 x 2,71 x 2,72 x 2,73 x 2,74 x 2,75 x 2,76 x 2,77 x 2,78 x 2,79 x 2,80 x 2,81 x 2,82 x
Revision: 0 Page 17
Implementation of Promotion of Renewable Energies – Developing the Biomass Market in Serbia CES/decon
Biomass Project Toplana of Prijepolje: Detailed Investment Plan and Results of the Financial Model 13.11.2019
Revision: 0 Page 18
Implementation of Promotion of Renewable Energies – Developing the Biomass Market in Serbia CES/decon
Biomass Project Toplana of Prijepolje: Detailed Investment Plan and Results of the Financial Model 13.11.2019
Revision: 0 Page 19