MEASURMENT SHEET

Repair Works of hostel Quaid e Azam Hall

S# DETAIL Nos L B H Qty Unit

Civil Works
1 Dismantling Tiles
Stairs 1 12.5 4.25 53.125 Sft
2 10.5 4.25 89.25 Sft
1 20 4.25 85
Entrance 1 11.25 5.25 59.0625
1 6.08 5.25 31.92
Entrance Pillars 1 4.67 5.25 24.5175
Toilet Block 2 15 26.25 787.5
4 15 5.5 330
4 26.25 5 525
Ablution 2 3 2.5 15
2 10 2 40
Sup Wash Room 1 6 8 48
1 14 5 70

Total 2158.375 Sft


2 Removing Door with Chowkat
Washroom Block 2 1 7 14 Each
Sup Wash Room 1 1 1 1 Each
Total 15 Each
3 Removing Skylights with Chowkats
Toilet Block 1 20.00
Total 20.00 Sft

4 Dismantling Brickwork in lime or Cement mortar


Toilet Block 8 4.5 0.375 8 108 Cft
6 5.75 0.375 8 103.5 Cft
Face Partitions 2 18.16 0.375 8 108.96 Cft
Ablution 2 10 3 2.25 135 Cft
Sup Wash Room 1 8.5 0.375 11 35.0625 Cft
1 4.6 0.375 11 18.975 Cft
Door Sup Washroom 1 2.5 0.75 7 13.125 Cft
Gutka LAwn Side 1 22 0.5 25 275 Cft
Gutka Washroom road side 1 15 0.5 25 187.5
d/d door -1 2.5 0.375 7 -6.5625
Total 978.56 Cft
7 Excavation in foundation
Washroom 2 10 2 2 80 Cft
2 6 2 2 48 Cft

Total 80 Cft

Dry rammed brick or stone ballast, 1½" to 2"( 40 mm to 50 mm guage)


8
2 10 2 0.33 13.2 Cft
2 6 2 0.33 7.92 Cft
Total 21.12 Cft
9 Pacca Brick Work in F&P 1:6
New Washrooms 2 9.25 1.5 0.25 6.94 Cft
2 6 1.5 0.25 4.50 Cft
1 8.875 1.125 0.75 7.49 Cft
1 6.375 1.125 0.75 5.38 Cft
MEASURMENT SHEET

Repair Works of hostel Quaid e Azam Hall

S# DETAIL Nos L B H Qty Unit

2 8.5 0.75 0.25 3.19 Cft


2 6.75 0.75 0.25 2.53 Cft
Cft
0 Cft
Total 30.02 Cft

10 P/L DPC Cement concrete 1:2:4 1.5" Thick


2 8.5 0.75 12.75 Sft
2 6.75 0.75 10.125 Sft
Total 22.875 Sft

11 Removing Cement or Lime Plaster


Toilet Block Internal FF 1 15 10 150 Sft
1 15 6.000 90 Sft
2 26.25 5.500 288.75
Toilet Block GF 1 14 8.000 112
1 14 6.000 84
2 26.25 6.000 315
Toilet Entrance 1 8 10.000 80
Extrenal Side Toilet Block 1 28.5 25.000 712.5
Extrenal Side Toilet Block 1 28.5 25.000 712.5
Big Rooms FF 6 14 5.000 420.000
14-C 1 5.33 3.500 18.655
11-C 1 3 6.500 19.5
1 1.5 2.000 3
10-C 1 3 7.000 21
1 5 2.750 13.75
1 2.75 1.125 3.09375
9-C 1 3 7.000 21
1 5 2.750 13.75
1 2.75 1.250 3.4375
1 14 3.750 52.5
8-C 1 3 7.000 21
1 5 2.750 13.75
1 2.75 1.250 3.4375
1 12 4.500 54
7-C 1 3 7.000 21
1 14 4.500 63
Gallery Lawn side 1 37 7.000 259
1 13 4.000 52
1 66 3.000 198
Sup Room 1 18.5 4.000 74
1 16 5.000 80
1 18.5 2.750 50.875
1 12 2.500 30
Big Rooms GF (1,2,3,4 D) S Wall 8 14 5.500 616
L wall 4 18 3.000 216
0
0
D/d Windows -2 22.5 2.000 -90
d/d washroom block -1 3 7.000 -21
Total 4775.50 sft

12 Dismantling Concrete 1:2:4


Toilet 2 15 26.25 0.25 196.9 Cft
For Pipe Horizontal 4 15 1 0.5 30.0
MEASURMENT SHEET

Repair Works of hostel Quaid e Azam Hall

S# DETAIL Nos L B H Qty Unit

For WC 8 2 1 0.5 8.0


For Pipe Baths 4 15 1 0.5 30.0
Stairs 21 10 1.75 0.125 45.9
Landing 2 10.5 3.5 0.125 9.2
New Washrooms 1 10 8 0.125 10.0
Sup Wash Room 1 8 6 0.125 6.0
0.0
0.0
0.0
Total 336.0 Cft

Cement concrete plain including placing, compacting, finishing and curing complete (including screening and
13
washing of stone aggregate): Ratio 1:2:4
Toilet Block 1 15 26.25 0.125 49.22 Cft
For Pipe 1 45 1 0.5 22.50 Cft
For WC 4 2 1 0.5 4.00 Cft
New Washrooms 0 6 8 0.125 0.00

0.00 Cft
Total 75.72 Cft

14 Pacca Brick Work in G.F Cement Sand Mortar 1:5


Washroom 1 8.5 0.75 11.5 73.31 Cft
1 6 0.375 11.5 25.88 Cft
Sup 1 9.5 0.75 11 78.38 Cft
2 6 0.75 11 99.00 Cft
Toilet Block 4 4.5 0.375 7.5 50.63
3 5.75 0.375 7.5 48.52
4 0.42 0.375 7.5 4.73
3 1.75 0.375 7.5 14.77
Mess/Office Partition 1 9.84 0.75 6.58 48.56
Counter 3 2 0.375 2.5 5.63
1 5.5 0.375 2.5 5.16
Wall closing washroom 1 1.5 0.75 6 6.75

Total 461.29 Cft


D/d
15 Pacca Brick Work in F.F Cement Sand Mortar 1:5
Toilet Block 4 4.5 0.375 7.5 50.63 Cft
3 5.5 0.375 7.5 46.41
4 0.42 0.375 7.5 4.73
3 1.75 0.375 7.5 14.77

Total 116.52 Cft


MEASURMENT SHEET

Repair Works of hostel Quaid e Azam Hall

S# DETAIL Nos L B H Qty Unit

Providing and laying reinforced cement concrete (including prestressed concrete), using coarse sand and screened
graded and washed aggregate, in required shape and design,including forms, moulds, shuttering, lifting, compacting,
16 after removing centring, curing, rendering and finishing exposed surface, complete (but excluding the cost of steel
reinforcement, its fabrication and placing in position, etc.):- Type C (nominal mix 1: 2: 4)

Lintel Beam 4 13.5 0.375 0.5 10.13 Cft


Slab Washroom 1 9.50 7.5 0.42 29.93 Cft
Lintel New Washroom 1 3.5 0.375 0.5 0.66 Cft
Counter 1 5.87 2.75 0.25 4.04 Cft

Total 44.74 Cft

Fabrication of mild steel reinforcement for cement concrete including cutting, bending, laying in position, making joints
17 and fastenings, including cost of binding wire and labour
charges for binding of steel reinforcement (also includes removal of rust from bars):- Deformed bars (Grade-60)

Qty as per item no 5 11.00 7 0.30 23.33 kg


8 9 0.303 21.82
Lintel Beam 4.00 3 0.30 3.64
Lintel Beam 8.00 13.5 0.30 32.72
Counter 7.00 2.5 0.30 5.30
3.00 5.5 0.30 5.00

Total 91.81 Kg
18 1/2" Thick Plaster 1:4 upto 20ft Height
Qty as per item no 11 4775.50
Small Rooms GF 8 14.5 4 464.00
16 5 2.75 220.00
16 4 4 256.00
8 12 4 384.00
8 2.5 4 80.00
New Washroom 2 8.5 11.5 195.50
2 6.5 11.5 149.50
Toilet Block Partition walls toilet 8 5.5 8 352.00
P.walls bath 4 4.25 8 136.00
Ablution/bath 2 4.75 8 76.00 FF
Faces bath 1 12.24 8 97.92
Face toilet 1 5.92 8 47.36
Mess/Office Partition 2 9.84 6.58 129.49
Counter 6 2 2.5 30.00
2 5.5 2.5 27.50
Sup Washrooom 2 6 10 120.00
2 8 10 160.00
Toilet Block GF 8 4.75 8 304.00
P.walls bath 6 4.5 8 216.00
GF
Face Partitions 2 3 8 48.00
Faces bath 2 5 8 80.00
MEASURMENT SHEET

Repair Works of hostel Quaid e Azam Hall

S# DETAIL Nos L B H Qty Unit

d/d door -2 2.50 7 -35.00


Total 8313.77 Sft
19 3/4" Thick Plaster 1:4 upto20' height
New Washrooms ceiling 1 6 8 48.00 Sft
Walls 2 7.25 11.5 166.75 Sft
1 4 11.5 46.00 Sft
Parapet 1 22 1.75 38.50 Sft
Wall closing washroom 2 1.5 6 18.00 Sft
Gutka LAwn Side 1 22 25 550.00
Total 867.25 Sft
P/F Mild Steel chowkat of doors, windows, C. windows i/c holdfast making and threading holes for hinges etc complete
26
MS Angle iron 1.5"x1.5"x1/4" welded with M.S Flat 2"x1/4"
New Washrooms 2 2.5 7 35.00 Sft
Total 35.00 Sft
33 Dismantling First Class tile roofing
1 36 54 1944.00 Sft
Total 1944.00 Sft
Single Relayer of tiles 9"x4.5"x1.5" laid over 4" earth and 1" mud plaster without bhoosa grouted with cement sand
34 1:3 on top of RCC roof slab provided 34lbs per % sft bitumen coating and sand blinded (rate without earth and
bitumen)
40% of Qty of item no 33 40 0.01 1944.00 777.60 Sft
Total 777.60 Sft
Single Relayer of tiles 9"x4.5"x1.5" laid over 4" earth and 1" mud plaster without bhoosa grouted with cement sand
35 1:3 on top of RCC roof slab provided 34lbs per % sft bitumen coating and sand blinded (rate without earth, brick tile
and bitumen)
60% of Qty of item no 33 60 0.01 1944.00 1166.40 Sft
Total 1166.40 Sft
Providing, laying, cutting, jointing, testing and disinfecting.P.V.C. pipe line with `B' Class working pressure pipe, in
56 trenches, complete in all respects:-
b) 4" i/d (100 mm)
For Toilet Block FF 2 15.75 31.50 Rft
1 6.5 6.50 Rft
1 10 10.00 Rft
2 1.5 3.00
4 2.5 10.00
Down 6 11 66.00
For TOilet Block GF 2 15.5 31.00
1 6.5 6.50
1 10 10.00
2 1.5 3.00
4 2.5 10.00
0.00 Rft
Total 187.50 Rft
Providing, laying, cutting, jointing, testing and disinfecting.P.V.C. pipe line with `B' Class working pressure pipe, in
57 trenches, complete in all respects:-
b) 3" i/d
15 2.5 37.50
For Toilet Block Rft
0.00 Rft
Total 37.50 Rft
Providing, laying, testing and commissioning of PPRC water supply pipe(Dadex,Popular,Beta or equivalent) with
60 specified pressure rating PN and conforming to DIN 8077-8078 code i/c cost of solvent specials, making jharries
complete in all respects as approved by engineer in charge. PN-20(25mm)
MEASURMENT SHEET

Repair Works of hostel Quaid e Azam Hall

S# DETAIL Nos L B H Qty Unit

Washroom Block 1 125 125.00 Rft


Total 125.00 Rft
Providing, laying, testing and commissioning of PPRC water supply pipe(Dadex,Popular,Beta or equivalent) with
61 specified pressure rating PN and conforming to DIN 8077-8078 code i/c cost of solvent specials, making jharries
complete in all respects as approved by engineer in charge. PN-20(32mm)
1 105 105.00 Rft
Total 105.00 Rft
71 P/F P-Trap:- Glazed 4" Dia
5 5.00 Nos

Total 5.00 Nos


72 P/F P-Trap:- Glazed 3" Dia
7 7.00 Nos

Total 7.00 Nos


73 Providing and installing P.V.C Bends of B.S.S Class B working Pressure:- 4" dia
2 2.00 Nos

Total 2.00 Nos


74 Providing and installing P.V.C Tee of B.S.S Class B working Pressure:- 4" dia
0 0.00 Nos

Total 0.00 Nos


75 Providing and installing P.V.C Tee of B.S.S Class B working Pressure:- 4" dia (Y-Tee 45 Degree)
5 5.00 Nos

Total 5.00 Nos


76 Providing and installing P.V.C Elbows of B.S.S Class B working Pressure:- 4" dia (Plain Plug and 45 Degree)
FF Washroom 10 10.00 Nos

Total 10.00 Nos


Carriage of 100 Cft. (2.83 cu.m) of all materials like stone aggregate, spawl, kankar lime (unslaked), surkhi, etc. or
91 150 Cft. (4.25 cu.m) of timber, by truck or by any other means owned by the contractor.
Lead Upto 5 Miles
Dismantling Brickwork in lime or Cement morta 1 1 978.56 978.56
Dismantling Tiles 1 0.125 2158.375 269.80
Dismantling Concrete 1:2:4 1 1 336.0 336.00
Removing Cement or Lime Plaster 1 0.04 4775.50 191.02

Total 1775.38 Cft