SHUTTERING (Steel):-

The Quantity of Shuttering = 10


Rate of Shuttering & Supports per day = 45 Rs/
= 485 Rs/

Sr# Resources Quantity Unit Time (Day) Rate Amount (Rs)


Man Power
1 Carpenter 1 - 0.3 600 180
Labour 1 - 0.45 250 112.5
Miscellaneous
Shuttering Plates 10 9 484.5 43605
2 43897.5
Sundries @7.5% of Sum Of Resources 3292.3
Cost Without the Profit Of Contractor 47189.8
3 Profit @10% 4719
Total Amount For 10 of Steel Shuttering 51909
4 Total Amount For 1 of Steel Shuttering 5191
Total Amount For 1 of Steel Shuttering 482

SHUTTERING (Wood):-

The Quantity of Shuttering = 10


Rate of Shuttering & Supports per day = 25 Rs/
= 269.124 Rs/

Sr# Resources Quantity Unit Time (Day) Rate Amount (Rs)


Man Power
1 Carpenter 1 - 0.3 600 180
Labour 1 - 0.45 250 112.5
Miscellanous
Shuttering Plates 10 9 269.124 24221.2
2 24513.7
Sundries @7.5% of Sum Of Resources 1838.5
Cost Without the Profit Of Contractor 26352.2
3 Profit @10% 2635.2
Total Amount For 10 of Wooden Shuttering 28987
4 Total Amount For 1 of Wooden Shuttering 2899
Total Amount For 1 of Wooden Shuttering 269