INDEPENDENT ENGINEER
Submitted by:
CONCESSIONAIRE
DA TOLL ROAD PRIVATE LIMITED
Executive Summary
[1]
M/s L.N. Malviya Infra Projects Pvt Ltd
INDEPENDENT ENGINEER SERVICES DURING OPERATION & MAINTENANCE PERIOD OF 5 YEARS FOR “SIX
LANING OF DELHI-AGRA SECTION FROM KM. 20.500 TO KM. 200 IN THE STATE OF HARYANA AND U.P ON
DBFOT BASIS.
TABLE OF CONTENTS
[2]
M/s L.N. Malviya Infra Projects Pvt Ltd
INDEPENDENT ENGINEER SERVICES DURING OPERATION & MAINTENANCE PERIOD OF 5 YEARS FOR “SIX
LANING OF DELHI-AGRA SECTION FROM KM. 20.500 TO KM. 200 IN THE STATE OF HARYANA AND U.P ON
DBFOT BASIS.
5. Pending Issue 13
8. Project Overview 19
10 Location Map 26
[3]
M/s L.N. Malviya Infra Projects Pvt Ltd
INDEPENDENT ENGINEER SERVICES DURING OPERATION & MAINTENANCE PERIOD OF 5 YEARS FOR “SIX
LANING OF DELHI-AGRA SECTION FROM KM. 20.500 TO KM. 200 IN THE STATE OF HARYANA AND U.P ON
DBFOT BASIS.
31. Reports 48
[4]
M/s L.N. Malviya Infra Projects Pvt Ltd
INDEPENDENT ENGINEER SERVICES DURING OPERATION & MAINTENANCE PERIOD OF 5 YEARS FOR “SIX
LANING OF DELHI-AGRA SECTION FROM KM. 20.500 TO KM. 200 IN THE STATE OF HARYANA AND U.P ON
DBFOT BASIS.
The Ministry of Road, Transport and Highway (MoRT&H), Government of India had entrusted National
Highways Authority of India with the task of implementing of Golden Quadrilateral project. The
National Highway Authority of India is engaged in the development of highways and as part of this
endeavor, the authority has decided to undertake development of six laning of Delhi-Agra section of NH-
2 from km. 20.500 to km. 200.00 through private participation on built operate and transfer basis.
Delhi-Agra section of National Highway no. 2 is a part of Golden Quadrilateral connecting cities of Delhi
and Kolkata. This portion of NH-2 also provides connectivity to East-West corridor and North-South
corridor of NHDP. This stretch from Delhi to Agra of NH-2 comes under NHDP Phase- V.
The Authority has awarded this project to M/s Reliance Infrastructure Limited on DBFOT basis. M/s
Reliance Infrastructure Limited has since promoted and incorporated the concessionaire as a limited
liability company (M/s. DA Toll Road Pvt. Ltd.) as the entity which shall undertake & perform the
obligations and exercise the right of the selected bidder.
This monthly progress report covers project highlights, progress of work and includes the “Independent
Engineers monthly inspection report” on the highway project as per clause 13.2 of Concession
Agreement on the works executed in the Month of January 2023
The project road starts from Km 20+500 of NH-2 and ends at Km 200+000 of NH-2, thus making a total
The project road lies in State of Haryana and Uttar Pradesh, starts from Badarpur Delhi Border (Km
20.500) and passes through Faridabad industrial area, Ballabgarh, Palwal, Hodal, Kosi, Mathura and ends
at Agra (Km.200.00). The project road lies between latitudes of 28o28’18” and 27o12’22.7” north and
longitudes of 77’18’20.65’’ and 78’01’53” east.
[5]
M/s L.N. Malviya Infra Projects Pvt Ltd
INDEPENDENT ENGINEER SERVICES DURING OPERATION & MAINTENANCE PERIOD OF 5 YEARS FOR
“SIX LANING OF DELHI-AGRA SECTION FROM KM. 20.500 TO KM. 200 IN THE STATE OF HARYANA AND
U.P ON DBFOT BASIS.
Sl. Nos of
Particulars Unit Completed Balance Remarks
No. Structure
1 PUPs Nos. 11 11 0
2 VUPs Nos. 23 23 0
Minor/Major Bridges (New on
3 Nos. 12 12 0
SR)
Minor/Major Bridges
4 Nos. 14 14 0
(Widening on MCW)
5 Flyover Nos. 15 15 0
6 Elevated Highway Palwal Rmt 2195 100% 0
A. Haryana Section
Foot over Bridges (Faridabad District)
Minor/Major Bridge/VUPs
Sl.
Location of Structure Ch. Structure
No.
1 Gurgaon Canal 34+479 Minor Bridge
2 Sikri- Piyala mor 43+200 VUP
3 Sikri- Piyala mor 43+367 PUP
4 Dudhola 47+735 PUP
5 Dudhola 48+205 VUP
SERVICE Road
S. From
To Chainage Side
No. Chainage
1 63+600 64+600 RHS
2 64+400 67+120 RHS
3 67+500 67+750 RHS
4 69+220 69+580 RHS
5 69+080 71+300 LHS
6 69+660 70+000 RHS
7 70+840 70+920 RHS
8 70+990 71+300 RHS
B. UP Section
VUP/ Minor Bridge/Flyover/Box culvert
Sl.
Location of Structure Chainage Structure
No.
1 Mandi Crossing 143+640 VUP
2 IOCL Township 153+067 VUP
3 Refinery Gate no. 9 158+991 VUP
4 Panwari 185+800 VUP
5 Hindustan college 171+273 Minor Bridge
6 ISBT Agra 195+100 Flyover
7 Near Sabji Mandi 189+250 Box Culvert
1.1.5Utility Shifting
ELECTRICAL UTILITIES
Name of Estimate/
State Chainage Status
Elec. Sub-Division
HR Old Faridabad 20.500 to 31.000 Completed & Handed over
HR Ballabhgarh 31.000 to 44.200 Completed & Handed over
HR Palwal-City 56.000 to 64.000 Completed & Handed over
HR Palwal Sub-Urban 45.000 to 55.700 Completed & Handed over
HR Deeghot 67.000 to 77.000 Completed & Handed over
HR Hodal 77.000 to 93.800 Completed & Handed over
UP Kosi-I 094+500 to 106+000 Completed & Handed over
UP Kosi-II 106+000 to 123+000 Completed & Handed over
UP Mathura Rural-I 123+000 to 141+000 Completed & Handed over
UP Mathura Rural-II 144+000 to 175+000 Completed & Handed over
UP Mathura City 142+000 to 152+000 Completed & Handed over
UP Sikandra Agra 176+000 to 190+000 Completed & Handed over
7. Strip Chart
NH no (New/old) NH-2
Mode of the Project DBFOT
No. of Lanes 6-Lane
Length of the Project 179.50 Km
Total Project cost 1928.22 Cr.
Concessionaire/ Contractor M/s DA Toll Road Pvt. Ltd. Toll Road Pvt.
Ltd.
9. Project Overview
2 PUPs Nos. 10
3 VUPs Nos. 23
6 Flyover Nos. 14
9 ROB Nos. 8
ST A R T OF
P R O J E CT
R O AD
UTTAR PRADESH
EN D OF
P R O J E CT
R O AD
IN D E X M A P E X H IB IT N O . 2 .A
1 No of flyovers 15
2 Service Road 204.16 Km
3 ROBs 08
5 RUBs 01
6 RUB location (chainage) Mathura Bangar Ch.
141+390
7 No of Bypass Nil
8 Length of Bypass Nil
9 No of Major Bridges 01
10 No of Minor Bridges 02
11 No of Culvert 219
12 No of VUP 23
13 No of PUP/Cattle Underpass 10
Concession Agreement, Scope of Project, stipulates that the Project shall be executed on the Site as
described in Schedule “A.” The Scope of the Project shall include performance and execution by the
Concessionaire of all design, engineering, financing, procurement, construction, completion, operation
and maintenance of the Project during Concession Period as described in Schedule “B” of this
Agreement. The Concessionaire shall undertake its obligations at its own cost and risk.
The Concessionaire shall operated and maintain the project Highway by itself, or through O&M
Contractors and if required, modify, repair or otherwise make improvements to the project Highway to
comply with Specifications and standards, and other requirements set forth in this Agreement. Good
Industries Practice, Applicable laws and Applicable Permits and manufacturer’s guidelines and
instructions with respect to toll systems, and more specifically:
(i) Permitting safe, smooth and uninterrupted flow of traffic during normal operating
conditions;
(ii) Charging, collecting and retaining the Fees in accordance with these Agreements;
(iii) Minimizing disruption to traffic in the event of accidents or other incidents affecting the
safety and use of the Project Highways by providing a rapid and effective response and
maintaining liaison procedures with emergency services;
(iv) Undertaking routine maintenance including prompt repairs of potholes, cracks, concrete
joints, drains, line marking, lighting and signage;
(v) Undertaking major maintenance such as resurfacing of pavements, repairs to structures,
repairs and refurbishment of tolling system and hardware and other equipment;
(vi) Carrying out periodic preventive maintenance to Project Highways including tolling
system;
(vii) Preventing with the assistance of concerned law enforcement agencies unauthorized
entry to and exit from the Project Highway;
(viii) Preventing with the assistance of the concerned law enforcement agencies encroachments
on the Project Highway including Site and preserve the right of way of the Project
Highway;
(ix) Maintaining a public relations unit to interface with and attend to suggestions from users
of the Project Highways, the media, Government Agencies, and other external agencies;
and
(x) Adherence to the safety standards set out in Schedule ‘S”.
Site was inspected by us on various dates along with the staff of Concessionaire’s
representatives during the month. During inspection, site visit & meeting at Toll plazaswith
the representatives of NHAI and Concessionaire, various issues were discussed regarding
maintenance of road, Safety Regulation, Environmental Status, Mobilization, Maintenance
Work Plan Schedule, Progress, Quality of the work, Procurement of Material, Plants and
equipment installation, Technical & Administration etc.
During the month, the undersigned has raised the various issues during frequent visit to site
regarding Maintenance work plan schedule, Progress effective utilization resources, Highway
Management and other Safety aspects of the Project.
Further during the meeting on various occasions following manuals\reports etc. has been
discussed:
i) Monthly Maintenance Report and implementation of methodology as stated in
Maintenance Manual,
ii) Various important correspondence issued by NHAI, the Contractor and the Consultant.
iii) Quality Assurance Plan.
iv) Safety Issues and implementation of Safety Plan.
v) Maintenance Programme.
vi) Traffic Management Plan.
vii) Maintenance Manual.
viii) Toll Management Systems.
ix) ETC & Fastag.
x) Implementation of Various Guidelines, directives issued by MoRT&H and NHAI from time
to time.
During the meetings it was suggested that well planned sequence of operation and proper
methodology should be used to have best results. Concessionaire has been advised to submit
the Monthly Maintenance Programme well in time to ensure the proper implementation.
e) Junction signs
f) Median Grills
g) Studs
h) Delineators
i) Road Marking
j) Kerb Painting
k) Guard Posts
b) Telecom
b) Toll plazas
c) Bridges
The Consultants shall perform the services and carry out their obligations hereunder with all
due diligence, efficiency and economy, in accordance with generally accepted professional
techniques and practices, and shall observe sound management practices and employ
appropriate advanced technology and safe and effective equipment , machinery materials and
methods” The Consultants shall always ” act, in respect of any matter relating to this Contract
or to the Services, as faithful advisers to the Client, and shall at all times support and safeguard
the Client’s legitimate interests in any dealing with Sub-consultants or Third parties and as per
Independent consultancy Agreement .
OPERATION AND MAINTENANCE STAGE:
The Independent Engineer shall Inspect the Project Highway once every month,
preferably after receipt of the monthly status report from the Concessionaire, but before
the 20th (twenty) day of each monthly in any ease, and make out an O & M Inspection
Report setting forth an overview of the status, quality and safety of O & M, including
conformity with the maintenance and safety requirements. In a separate section of O&M
Inspection Report, the Independent Engineer shall describe in reasonable detail the
lapses, defects or deficiencies observed by it the operation and maintenance of the
Project Highway. The Independent Engineer shall send a copy of its O&M Inspection
Report to the Authority and the Concessionaire within 7 (seven) days of Inspection.
The Independent Engineer shall in its O&M Inspection Report specify test if any, that the
Concessionaire shall carry out or cause to be carried out for the purpose of determining
that the Highway Project is in conformity with the maintenance requirements. It shall
monitor and review the results of such test and remedial measures, if any, taken by the
Concessionaire on his behalf. The Independent Engineer shall examine the request of the
Concessionaire for closure of any lane(s) of the carriageway for undertaking maintenance
/ repair thereof, keeping in view the need to minimize disruption to traffic and the time
required for completing such maintenance / repair in accordance with Good Industry
practice, It shall grant permission with such modification, as it may deem necessary,
within 3 (Three) days of receiving a request from the Concessionaire. Upon expiry of the
permitted period of such lane(s) and in case of delay, determine the Damages payable by
the Concessionaire to the Authority under clause 17.7.
Project: Independent Engineer Services during Operation &Maintenance period of 5 years for “Six
Laning of Delhi-Agra section from Km. 20.500 to Km. 200 in the State of Haryana and U.P. on
Design, Build, Finance, Operate and Transfer (DBFOT) basis”
1. INTRODUCTION :
Site was inspected by us on various dates along with the staff of Concessionaire’s
representatives during the month. During inspection, site visit & meeting at Toll plazaswith
the representatives of NHAI and Concessionaire, various issues were discussed regarding
maintenance of road, Safety Regulation, Environmental Status, Mobilization, Maintenance
Work Plan Schedule, Progress, Quality of the work, Procurement of Material, Plants and
equipment installation, Technical & Administration etc.
During the month, the undersigned has raised the various issues during frequent visit to site
regarding Maintenance work plan schedule, Progress effective utilization resources, Highway
Management and other Safety aspects of the Project.
Further during the meeting on various occasions following manuals\reports etc. has been
discussed:
xi) Monthly Maintenance Report and implementation of methodology as stated in
Maintenance Manual,
xii) Various important correspondence issued by NHAI, the Contractor and the Consultant.
xiii) Quality Assurance Plan.
xiv) Safety Issues and implementation of Safety Plan.
xv) Maintenance Programme.
xvi) Traffic Management Plan.
xvii) Maintenance Manual.
xviii) Toll Management Systems.
xix) ETC & Fastag.
xx) Implementation of Various Guidelines, directives issued by MoRT&H and NHAI from time
to time.
During the meetings it was suggested that well planned sequence of operation and proper
methodology should be used to have best results. Concessionaire has been advised to submit
the Monthly Maintenance Programme well in time to ensure the proper implementation.
(2) ROW
The fixing of Boundary pillars is incomplete.Ch.35+000 to 36+000 RHS MCW Cleaning
required, 33+500 RHS S/R Cleaning required, 43+900 RHS S/R lane Cleaning required.
(3) Drainage System
Pipe drains are chocked at many locations especially Side drain in Ch. 43+380 RHS Damage
Drain cover and Chamber Damage. Manhole covers is being laid at some places but that is
not fixed properly.
Construction of drains in some built-up areas is still pending. Cleaning of Covered drains
shall be carried out regularly. At many locations the drains are not functioning, require
urgent attention.
The establishments like Dhabas, Factories and retail out let have encroached upon ROW.
However some of the encroachments have been removed under the structure, which are
again encroached. Ch. 49+500 LHS, 160+350 LHS, 162+500 LHS, 100+420 RHS, 100+180
RHS.
4) Separators, PGRs and Footpath
Separator damaged at Km. 187+820, Ch. 185+600 RHS.
PGRS have been found not painting, unauthorized opening, damaged at many locations like
Ch. 38+480 RHS, Ch. 30+620(MGR), Ch. 25+180,(MGR) Ch. 33+460(MGR), Ch. 32+860
(MGR) Ch. 82+940, Ch. 50+040 LHS, Ch. 153+870 LHS, 167+350 RHS needs repair for
safety point of view.
PGR not paint at Km. 34+020 RHS, Km. 34+060 RHS, km.44+930 RHS, 46+960 to 47+000
RHS, Km. 54+040 LHS
PGR & MGR faded at few locations. Ch. 109+200 to 111+700 RHS, Km.135+000 to 136+900
median, 149+600 to 151+750, 196+350 to 197+100 median.
At Km 130+520 RHS, 153+700 RHS footpath are damaged.
Sign Board Ch. 82+670 LHS, 60+700 RHS, 68+190 Median, 58+300 Median, 57+310 Sign
Board damage.
Delineator damage Ch. 54+790, 43+700 Median,
5) Structures
Minor Bridge at Km. 92+980
Repair of abutment A2 and pier work is under progress.
Palwal Elevated Highway.
Cleaning of pier caps is yet not completed.
Concessionaire has been advised to maintain the Toll plaza premises and clean the
Toll booths and Lanes regularly.
8) SAFETY
Hazard Markers
Hazard Markers are present at the required locations like Median Openings, near
structures. Cleaning at a few locations is required and Concessionaire has been
informed to take the action at the earliest.
Thermoplastic Pavement marking and Kerb Painting
Kerb painting and Thermoplastic Painting work has been faded at some sections.
Contractor has been asked to redo the faded road marking stretches.
Crash Barriers
Crash Barriers have been installed as per the provisions. Concessionaire has been
asked to put the retro reflective tapes on it for night vision.
9) Street lighting works
Installation of street lighting poles/high mast is completed. Electricity Connection at Toll
plazas has already been done.
10) CONCLUSION:-
16. Concessionaire has to maintain the project corridor safe for the users and has to conduct
Condition survey of Road to assess the pavement condition.
17. The safety aspects as directed by the NHAI, IE& Safety cell be complied.
18. Monthly work programme to be submitted by the Concessionaire including details and
planned activities of weekly and daily regular & Special Maintenance work.
19. Concessionaire shall keep a record of Daily inspection report at Toll Plaza for the
verification.
20. Route Patrol shall be made more effective and staff shall monitor the project Highway for
ensuring uninterrupted flow of traffic by minimizing the Wrong direction traffic.
21. Deficiencies in Avenue and median planation shall be rectified at the earliest.
22. Unauthorized median opening shall be closed and Unauthorized Access must be closed.
23. Prevention of over speeding is required to reduce the fatal accidents by providing speed
limit boards.
24. It has been observed that removal of advertisement boards has been done at many locations
but still removal of the same within ROW are still left at some locations. Concessionaire is
instructed to remove left over advertisement boards/hoardings etc on priority.
25. All the balance missing sign & caution boards like T-Junction, Pedestrian Crossing, Median
gaps etc shall be restored in place from safety point of view.
26. It has been observed that blinkers at some locations are not functional, needs
repair/replacement on priority.
27. Sufficient / regular watering for plants in avenue & median is required.
28. Open RWH pit & manholes be covered on priority especially near Ajronda structure in RHS.
29. Excavated portion while removing electrical poles at Ballabgarh Flyover be rectified.
30. Garbage dumped at many locations, be removed.
Concessionaire is hereby advised to rectify the above defects & deficiencies within seven days in
accordance with the provisions of Concession Agreement and submit compliance report.
Sample photographs taken at site are enclosed herewith.
20. Summary of NCR : Details of Schedule -K Issued and Maintenance carried out by
Concessionaire till date
S. No Total NCR issued NCR issued in Total NCR NCR closed Balance
till previous reporting month (B) NCR
month (A) (A+B-C)
1 26 11 37 33 4
Fee
Collected
No of Vehicles (For Previous Fee Collected (For Fee Per Vehicle (For No of Vehicles (For
(For
Month) Previous Month) Current Month) Current Month)
Current
Month)
516794 35854165 0 487170 33758840
39856 4966445 0 38412 4828405
117610 32032385 0 114831 31364950
0 0 0 0 0
188845 84129875 0 179546 79953970
170 81970 0 141 68355
0 0 0 0 0
0 0 0 0 0
0 0 0 0 0
0 0 0 0 0
0 0 0 0 0
0 0 0 0 0
Equipment as
Hardware
Equipment Owner per
/Software 8 Units Damaged/Missing Remarks
/Provider specifications
Description
(Y / N)
Hardware-T1 24+2 0 Comvision Y Gadpuri
Software-T1 24+2 0 Comvision Y Gadpuri
Hardware-T1 16+2 0 Comvision Y Karman
Software-T1 16+2 0 Comvision Y Karman
Intercom
unit is
damaged at
Mahuvan
Hardware-T1 14 0 Comvision Y Plaza
Software-T1 14 0 Comvision Y Mahuvan
Av
er
ag
e
Avera Tr
Average
Average ge an
Queue Average Average Average
Lan Queue length Trans sa
length Transaction Transaction Transactio
e during no action cti
during (Cash) (RFID) n (Wallet)
peak time (Card on
peak time
s) ti
me
(ot
he
rs)
1- 60
T1 50 m 10 m 45 sec 8 sec sec 30 sec 0
2- 60
T1 50 m 10 m 45 sec 8 sec sec 30 sec 0
3- 60
T1 50 m 10 m 45 sec 8 sec sec 30 sec 0
4- 60
T1 50 m 10 m 45 sec 8 sec sec 30 sec 0
5- 60
T1 50 m 10 m 45 sec 8 sec sec 30 sec 0
6- 60
T1 50 m 10 m 45 sec 8 sec sec 30 sec 0
7- 60
T1 50 m 10 m 45 sec 8 sec sec 30 sec 0
8- 60
T1 50 m 10 m 45 sec 8 sec sec 30 sec 0
1- 60
T2 70 m 15 m 45 sec 8 sec sec 30 sec 0
2- 60
T2 70 m 15 m 45 sec 8 sec sec 30 sec 0
3- 60
T2 70 m 15 m 45 sec 8 sec sec 30 sec 0
4- 60
T2 70 m 15 m 45 sec 8 sec sec 30 sec 0
5- 60
T2 70 m 15 m 45 sec 8 sec sec 30 sec 0
6- 60
T2 70 m 15 m 45 sec 8 sec sec 30 sec 0
7- 60
T2 70 m 15 m 45 sec 8 sec sec 30 sec 0
1- 60
T1 50 m 10 m 45 sec 8 sec sec 30 sec 0
2- 60
T1 50 m 10 m 45 sec 8 sec sec 30 sec 0
3- 60
T1 50 m 10 m 45 sec 8 sec sec 30 sec 0
45 8
4- se se
T1 50 m 10 m c c 60 sec 30 sec 0
5-
T1 50 m 10 m 45 sec 8 sec 60 sec 30 sec 0
6-
T1 50 m 10 m 45 sec 8 sec 60 sec 30 sec 0
7-
T1 50 m 10 m 45 sec 8 sec 60 sec 30 sec 0
8-
T1 50 m 10 m 45 sec 8 sec 60 sec 30 sec 0
1-
T2 70 m 15 m 45 sec 8 sec 60 sec 30 sec 0
2-
T2 70 m 15 m 45 sec 8 sec 60 sec 30 sec 0
3-
T2 70 m 15 m 45 sec 8 sec 60 sec 30 sec 0
4-
T2 70 m 15 m 45 sec 8 sec 60 sec 30 sec 0
5-
T2 70 m 15 m 45 sec 8 sec 60 sec 30 sec 0
6-
T2 70 m 15 m 45 sec 8 sec 60 sec 30 sec 0
7-
T2 70 m 15 m 45 sec 8 sec 60 sec 30 sec 0
1-
T1 50 m 10 m 45 sec 8 sec 60 sec 30 sec 0
2-
T1 50 m 10 m 45 sec 8 sec 60 sec 30 sec 0
3-
T1 50 m 10 m 45 sec 8 sec 60 sec 30 sec 0
4-
T1 50 m 10 m 45 sec 8 sec 60 sec 30 sec 0
5-
T1 50 m 10 m 45 sec 8 sec 60 sec 30 sec 0
6-
T1 50 m 10 m 45 sec 8 sec 60 sec 30 sec 0
7-
T1 50 m 10 m 45 sec 8 sec 60 sec 30 sec 0
8-
T1 50 m 10 m 45 sec 8 sec 60 sec 30 sec 0
1-
T2 70 m 15 m 45 sec 8 sec 60 sec 30 sec 0
2-
T2 70 m 15 m 45 sec 8 sec 60 sec 30 sec 0
3-
T2 70 m 15 m 45 sec 8 sec 60 sec 30 sec 0
4-
T2 70 m 15 m 45 sec 8 sec 60 sec 30 sec 0
5-
T2 70 m 15 m 45 sec 8 sec 60 sec 30 sec 0
6-
T2 70 m 15 m 45 sec 8 sec 60 sec 30 sec 0
7-
T2 70 m 15 m 45 sec 8 sec 60 sec 30 sec 0
Nil
I.E has recommended for the damages of 47.44 cr vide letter no6434 dated 25.01.23 to
grant the EOT to the Concessionaire upto 20.05.2022(Date of issuance of provisional
completion certificate) by imposing damages @0.1%the performance security of Rs
107.89 Cr for each day of delay as per Article 15 of the CA.
Change of Scope
NHAI has accorded “in-principle” Approval for COS& Issued change of scope notice
In principal
Approval Work done /
COS Order
COS Scope of work (As approved by Certified
Value
the authority amount
letters)
Extension of Flyover - Ballabgarh
35+050
1
Additional VUP - 23+660 64.71 63.74 57.99
Additional VUP - 32+150
4 Palwal Elevated
59.70 56.52
Total Amount
268.62 252.66
Notice
Order
COS COS Works Amount Received
Received Date
on
Additional VUP at HUDA bye pass @ Ch. 40+950
Additional VUP at Bamnikhera(Km. 68+125)
Additional PUP at Hodal Km. 89.030
Additional drain in Hodal (Km 88 to Km 90, BHS)
3 113.87 22.03.2016 09.06.2017
Construction of VUP instead of PUP at Km. 123.075
Additional VUP at Km 145+045, Jai Gurudev
Additional PUP at Km 145+500, Jai Gurudev
Additional VUP at Km 189+800, Sabzi Mandi
To curb the long pending persistent issue of water logging existing at the project stretch at 48
locations (20 in Haryana Section and 28 in UP Section), the concessionaire undertook the
resolution of drainage issues and has successfully resolved most of them, The same have been
acknowledged with due back up of RFI’s. However, drainage issue at 7 locations in Haryana still
exists due to the issue beyond the reasonable control of the concessionaire and all such locations
are subjected to water logging due the adjoining communities surface water run-off and
accordingly the concessionaire has notified multiple times to the concerned Municipal
Corporations for the needful intervention and NHAI has also made several correspondences to
the concerned public bodies for their needful intervention. As acknowledged during site
inspections the issue is largely resolved in the entire section except Faridabad Section and the
matter is jointly pursued with the MCF.
The list of affected locations supplied by the Concessionaire where sewer over flow is taking
place, has been inspected jointly by the IE along with Concessionaire and found that the
Concessionaire has made reasonable efforts to resolve the drainage issue at all the locations
but still sewerage water is coming on the Service road at 7 locations which relates to MC
Faridabad and unless suitable action is not taken up by MCF, the permanent solution of water
logging at these locations cannot be resolved. The sewer line laid by MCF is very old which
have now blockage at many places resulting in overflow of sewer.
It has also been observed that at three locations, private residential colonies are at higher level
and have open side drains which overflow and water comes on Service road. Moreover, at
some locations the remedial measures such as pump house has been set up by the
Concessionaire but the MCF has not taken the hand over for further maintenance.
Furthermore the Concessionaire requested for shifting of the all-balance 7 number locations in
a punch list-B. In this regard the Authority has also communicated to the MCF and
DC,Faridabad to intervene and to resolve the issue by their end vide NHAI letter no 69096 and
69097 dated 06.02.2023 and accordingly, we can take undertaking from the concessionaire to
resolve all concerned locations in due coordination with the MCF and the concessionaire
should also undertake to take the whole responsibility of surface water run-off pertaining to
the road and must also keep dewatering resources at large , to ensure MCW and Service road
remains water logging free even in a case of unexpected unprecedented rains.
31. Report
SCHEDULE- M
MONTHLY FEE STATEMENT
Project Highways :-Delhi Agra Toll Road Pvt. Ltd. NH-2 Month - Jan - 23
Fee Plaza Name ( Chainage) :- Gadpuri Toll Plaza CH- 46 KM
For the Corresponding Month of Previous year
For Proceeding Month (Dec.2022) For the Month reported up on (Jan -2023)
(June.2021)
Types of
Travel Type No. of Vehicles
Vehicles Fee collected Fee collected Fee Per Vehicles Fee collected
No. of Vehicles No. of Vehicles (including ETC
( In Rs.) ( In Rs.) (in Rs.) ( In Rs.)
Traffic)
1 2 3 4 5 6 7 8 9
One Way 0 0 378176 43768340 110 367132 42317770
(A) Car
Return 0 0 188251 10353805 55 188913 10390215
One Way 0 0 32184 5829250 175 31510 5654075
(B) LCV
Return 0 0 17139 1456815 85 17083 1452055
One Way 0 0 12991 4652985 355 13276 4743865
(C) Bus Return 0 0 10869 1956420 180 11304 2034720
One Way 0 0 46585 16666540 355 45611 16284560
(D) Truck
Return 0 0 14817 2667060 180 14648 2636640
(E) Multi-
One Way 0 0 79076 43278995 545 77014 42090350
axle
Return 0 0 20673 5685075 275 19272 5299800
Truck
(F) Oversized One Way 0 0 200 141085 695 86 59770
vehicle Return 0 0 155 53475 345 58 20010
Total 0 0 801116 136509845 3355 785907 132983830
1 2 3 4 5 6 7 8 9 10
SCHEDULE- M
MONTHLY FEE STATEMENT
Project Highways :-Delhi Agra Toll Road Pvt. Ltd. NH-2
Month :-January 2023
Fee Plaza Name ( Chainage) :- Mahuvan Toll Plaza Mathura at CH- 164.500 KM
1 2 3 4 5 6 7 8 9 10
One Way 29884 5470380 32448 4941150 150 30754 237 4648650
(B) LCV
Return 6816 613440 7256 580480 80 6611 528880
(E) Multi-axle One Way 175240 103489540 191415 95757500 500 181934 90 91012000
Truck
Return 9235 2724325 12365 3091250 250 10619 2654750
SCHEDULE- M
MONTHLY FEE STATEMENT
Project Highways :-Delhi Agra Toll Road Pvt. Ltd. NH-2
Month :-Jan - 2023
For the Corresponding Month
For Proceeding Month For the Month reported up on
of Previous year (December
(Decemberr 2022) (Jan-2023)
Types of 2021)
Travel Type
Vehicles No. of Vehicles
No. of Fee collected No. of Fee collected Fee collected
(including ETC
Vehicles ( In Rs.) Vehicles ( In Rs.) ( In Rs.)
Traffic)
1 2 3 4 5 6 8 10
SCHEDULE-V
[Referance clause 23 (D) of Appendix- IV]
Monthly User Fee Collection Statement -Part- A
Project Highways :-Delhi Agra Toll Road Pvt. Ltd. NH-2
Fee Plaza Name ( Chainage) :-Gadpuri Toll Plaza CH- 46 KM Month- Jan-23
SCHEDULE-V
[Referance clause 23 (D) of Appendix- IV]
Monthly User Fee Collection Statement -Part- B
Fee Plaza Name ( Chainage) :-Gadpuri Toll Plaza CH- 46 KM
Monthly Vehicle Passing Report
For the Month of :- Jan-23
Oversized
LCV, LGV, Mini Bus Truck (2 Multi-axle
No. Of Monthly Passes Car, Jeep, Van Bus vehicle (More Total
School Bus Axle) Truck ( More than 3 axle)
than 7 Axles)
No. of Passes 16897 49 38 0 0 0 16984
Revenue ( In Rs.) 3531665 332790 450870 4315325
Oversized
Truck (2 Multi-axle
Types of Vehicles as per Car, Jeep, Van LCV, LGV, Mini Bus Bus vehicle (More Total
Axle) Truck ( More than 3 axle)
notification than 7 Axles)
Nos Nos Nos Nos Nos Nos Nos
All types of singles entry
(Excluding commercial
Multiple Entry
Reusage of multiple
entry ticket
Reusage of monthly
passes
Single entry of
commercial vehicles
Exempted etc.
Grant Total
SCHEDULE-V
[Referance clause 23 (D) of Appendix- IV]
Monthly User Fee Collection Statement -Part- A
Project Highways :-Delhi Agra Toll Road Pvt. Ltd. NH-2
Fee Plaza Name ( Chainage) :-Karman Fee Plaza, Palwal at CH- 94.00 KM
Month- January 2023
Amount of user fee collected User Fee collected through
Types of Vehicles as Total Amount Collected Total Amount Deposited
through tickets Passess
Sr.No. per notification Remarks
provisions For the For the
For the Month Cummulative For the Month Cummulative Cummulative Cummulative
Month Month
Multi-axle
7 79813445 151859745 258825 828690 80072270 152688435 80072270 152688435
Truck
Oversized
8 68355 151928100 0 828690 68355 152756790 68355 152756790
vehicle
SCHEDULE-V
[Referance clause 23 (D) of Appendix- IV]
Monthly User Fee Collection Statement -Part- B
Fee Plaza Name ( Chainage) :-Karman Fee Plaza, Palwal at CH- 94.00 KM
Monthly Vehicle Passing Report
For the Month of :- January - 2023
Multi-axle Oversized
LCV, LGV, Mini
No. Of Monthly Passes Car, Jeep, Van Bus Truck (2 Axle) Truck ( More vehicle (More Total
Bus
than 3 axle) than 7 Axles)
Multi-axle Oversized
LCV, LGV, Mini
Car, Jeep, Van Bus Truck (2 Axle) Truck ( More vehicle (More Total
Types of Vehicles as per notification Bus
than 3 axle) than 7 Axles)
Multiple Entry
Grant Total
SCHEDULE-V
[Referance clause 23 (D) of Appendix- IV]
Monthly User Fee Collection Statement -Part- A
Project Highways :-Delhi Agra Toll Road Pvt. Ltd. NH-2
Fee Plaza Name ( Chainage) :-Mahuvan Toll Plaza Mathura at CH- 164.500 KM
Month :-January 2023
Amount of user fee collected User Fee collected through
Types of Vehicles as Total Amount Collected Total Amount Deposited
through tickets Passess
Sr.No. per notification Remarks
provisions For the For the
For the Month Cummulative For the Month Cummulative Cummulative Cummulative
Month Month
Multi-axle
7 93666750 163917815 0 641035 93666750 164558850 93666750 164558850
Truck
Oversized
8 33275 163951090 0 641035 33275 164592125 33275 164592125
vehicle
SCHEDULE-V
[Referance clause 23 (D) of Appendix- IV]
Monthly User Fee Collection Statement -Part- B
Fee Plaza Name ( Chainage) :-Mahuvan Toll Plaza Mathura at CH- 164.500 KM
Monthly Vehicle Passing Report
For the Month of :- January 2023
Multi-axle Oversized
LCV, LGV, Mini
No. Of Monthly Passes Car, Jeep, Van Bus Truck (2 Axle) Truck ( More vehicle (More Total
Bus
than 3 axle) than 7 Axles)
Multi-axle Oversized
LCV, LGV, Mini
Car, Jeep, Van Bus Truck (2 Axle) Truck ( More vehicle (More Total
Types of Vehicles as per notification Bus
than 3 axle) than 7 Axles)
Multiple Entry
Grant Total
SCHEDULE-N
WEEKLY TRAFFIC CENSUS - Jan-2023
Project Highways :-Delhi Agra Toll Road Pvt. Ltd. NH-2
Fee Plaza Name ( Chainage) :-Gadpuri Toll Plaza,Palwal at CH- 46 KM Week Ending :-08-14 Jan"23
No of Vehicles using the Project Highway during
Shift Type of Vehicle Corresponding Week/Last Preceding Week
Week of Report Jan " 2023
Year. June'2021 Dec"- 2022
A Fee Paying Traffic
A1 CAR 0 134671 115688
A2 LCV 0 12235 14135
A3 BUS 0 5721 5547
A4 TRUCK 0 14504 14583
A5 MAV 0 22761 22678
A6 OSV 0 94 25
TOTAL (A) 0 189986 172656
B Local Users (Monthly Pass)
B1 CAR 0 78347 77076
B2 LCV 0 511 500
B3 BUS 0 511 413
B4 TRUCK 0 35 52
B5 MAV 0 48 85
B6 OSV 0 0 0
TOTAL (B) 0 79452 78126
C Exempted Vehicles
C1 Auto 0 19 24
C2 Tractor 0 3893 4277
C3 CAR 0 23736 23417
C4 LCV 0 111 120
C5 BUS 0 38 19
C6 TRUCK 0 200 164
C7 MAV 0 164 65
C8 OSV 0 1 0
TOTAL (C) 0 28162 0
D Violations
D1 CAR 0 0 0
D2 LCV 0 0 0
D3 BUS 0 0 0
D4 TRUCK 0 0 0
D5 MAV 0 0 0
D6 OSV 0 0 0
TOTAL (D) 0 0 0
E Total Traffic (A+B+C+D)
E1 Auto 0 19 24
E2 Tractor 0 3893 4277
E3 CAR 0 236754 216181
E4 LCV 0 12857 14755
E5 BUS 0 6270 5979
E6 TRUCK 0 14739 14799
E7 MAV 0 22973 22828
E8 OSV 0 95 25
GRAND TOTAL 0 297600 278868
SCHEDULE-N
WEEKLY TRAFFIC CENSUS - Jan-2023
Project Highways :-Delhi Agra Toll Road Pvt. Ltd. NH-2
Fee Plaza Name ( Chainage) :-Gadpuri Toll Plaza,Palwal at CH- 46 KM Week Ending :-15-21 Jan"23
SCHEDULE-N
WEEKLY TRAFFIC CENSUS - Jan-2023
Project Highways :-Delhi Agra Toll Road Pvt. Ltd. NH-2
Fee Plaza Name ( Chainage) :-Gadpuri Toll Plaza,Palwal at CH- 46 KM Week Ending :-22-28 Jan" 23
SCHEDULE-N
WEEKLY TRAFFIC CENSUS - Jan-2023
Project Highways :-Delhi Agra Toll Road Pvt. Ltd. NH-2
Fee Plaza Name ( Chainage) :-Gadpuri Toll Plaza,Palwal at CH- 46 KM Week Ending :-29-31 Jan" 23
SCHEDULE-N
WEEKLY TRAFFIC CENSUS - January 2023
Project Highways :-Delhi Agra Toll Road Pvt. Ltd. NH-2
Fee Plaza Name ( Chainage) :-Karman Fee Plaza, Palwal at CH- 94.000 KM Week Ending :- 08-14
SCHEDULE-N
WEEKLY TRAFFIC CENSUS - January 2023
Project Highways :-Delhi Agra Toll Road Pvt. Ltd. NH-2
Fee Plaza Name ( Chainage) :-Karman Fee Plaza, Palwal at CH- 94.000 KM Week Ending :- 15-21
SCHEDULE-N
WEEKLY TRAFFIC CENSUS - January 2023
Project Highways :-Delhi Agra Toll Road Pvt. Ltd. NH-2
Fee Plaza Name ( Chainage) :-Karman Fee Plaza, Palwal at CH- 94.000 KM Week Ending :- 22-28
SCHEDULE-N
WEEKLY TRAFFIC CENSUS - January 2023
Project Highways :-Delhi Agra Toll Road Pvt. Ltd. NH-2
Fee Plaza Name ( Chainage) :-Karman Fee Plaza, Palwal at CH- 94.000 KM Week Ending :- 29-31
SCHEDULE-N
WEEKLY TRAFFIC CENSUS - January 2023
Project Highways :-Delhi Agra Toll Road Pvt. Ltd. NH-2
Week Ending :- 08-14
Fee Plaza Name ( Chainage) :-Mahuvan toll plaza, Mathura at CH- 164.500 KM
January-2023
No of Vehicles using the Project Highway during
Corresponding
Shift Type of Vehicle Preceding Week Week of Report
Week/Last Year
December- 2022 January- 2023
January 2022
A Fee Paying Traffic
A1 CAR 52784 83783 67113
A2 LCV 8188 8716 8474
A3 BUS 4789 6020 5645
A4 TRUCK 20837 23303 22789
A5 MAV 41063 46689 45150
A6 OSV 15 15 8
TOTAL (A) 127676 168526 149179
B Local Users (Monthly Pass)
B1 CAR 7076 8772 7080
B2 LCV 0 20 6
B3 BUS 0 0 0
B4 TRUCK 10 39 19
B5 MAV 12 155 2
B6 OSV 0 0 0
TOTAL (B) 7098 8986 7107
C Return Journey Reuse
C1 CAR 0 0 0
C2 LCV 0 0 0
C3 BUS 0 0 0
C4 TRUCK 0 0 0
C5 MAV 0 0 0
C6 OSV 0 0 0
TOTAL (C) 0 0 0
D Exempt Vehicles
D1 CAR 5419 6497 5249
D2 LCV 464 495 609
D3 BUS 8 20 15
D4 TRUCK 208 251 290
D5 MAV 90 218 162
D6 OSV 0 0 1
D7 Auto 183 128 184
D8 Tractor 1419 1441 910
TOTAL (D) 7791 9050 7420
E Total Traffic (A+B+C+D)
E1 CAR 65279 99052 79442
E2 LCV 8652 9231 9089
E3 BUS 4797 6040 5660
E4 TRUCK 21055 23593 23098
E5 MAV 41165 47062 45314
E6 OSV 15 15 9
E7 Auto 183 128 184
E8 Tractor 1419 1441 910
GRAND TOTAL 142565 186562 163706
MONTHLY PROGRESS REPORT JANUARY -2023. 69
M/s L.N. Malviya Infra Projects Pvt Ltd
INDEPENDENT ENGINEER SERVICES DURING
OPERATION & MAINTENANCE PERIOD OF 5 YEARS FOR “SIX LANINGOF DELHI-AGRA SECTION FROM KM.
20.500 TO KM. 200 IN THE STATE OF HARYANA AND U.P ON DBFOT BASIS.
SCHEDULE-N
WEEKLY TRAFFIC CENSUS - January 2023
Project Highways :-Delhi Agra Toll Road Pvt. Ltd. NH-2
Week Ending :- 15-21
Fee Plaza Name ( Chainage) :-Mahuvan toll plaza, Mathura at CH- 164.500 KM
January-2023
No of Vehicles using the Project Highway during
Corresponding
Shift Type of Vehicle Preceding Week Week of Report
Week/Last Year
December- 2022 January- 2023
January 2022
A Fee Paying Traffic
A1 CAR 53534 73896 71713
A2 LCV 8196 8876 8325
A3 BUS 4774 6212 5984
A4 TRUCK 20666 22958 23179
A5 MAV 41537 46040 43852
A6 OSV 15 17 15
TOTAL (A) 128722 157999 153068
B Local Users (Monthly Pass)
B1 CAR 7576 8111 8744
B2 LCV 0 10 8
B3 BUS 0 0 0
B4 TRUCK 13 45 22
B5 MAV 16 173 9
B6 OSV 0 0 0
TOTAL (B) 7605 8339 8783
C Return Journey Reuse
C1 CAR 0 0 0
C2 LCV 0 0 0
C3 BUS 0 0 0
C4 TRUCK 0 0 0
C5 MAV 0 0 0
C6 OSV 0 0 0
TOTAL (C) 0 0 0
D Exempt Vehicles
D1 CAR 5444 5571 5884
D2 LCV 468 516 508
D3 BUS 24 28 20
D4 TRUCK 151 264 198
D5 MAV 83 166 149
D6 OSV 0 0 0
D7 Auto 175 238 211
D8 Tractor 1484 1448 1122
TOTAL (D) 7829 8231 8092
E Total Traffic (A+B+C+D)
E1 CAR 66554 87578 86341
E2 LCV 8664 9402 8841
E3 BUS 4798 6240 6004
E4 TRUCK 20830 23267 23399
E5 MAV 41636 46379 44010
E6 OSV 15 17 15
E7 Auto 175 238 211
E8 Tractor 1484 1448 1122
GRAND TOTAL 144156 174569 169943
MONTHLY PROGRESS REPORT JANUARY -2023. 70
M/s L.N. Malviya Infra Projects Pvt Ltd
INDEPENDENT ENGINEER SERVICES DURING
OPERATION & MAINTENANCE PERIOD OF 5 YEARS FOR “SIX LANINGOF DELHI-AGRA SECTION FROM KM.
20.500 TO KM. 200 IN THE STATE OF HARYANA AND U.P ON DBFOT BASIS.
SCHEDULE-N
WEEKLY TRAFFIC CENSUS - January 2023
Project Highways :-Delhi Agra Toll Road Pvt. Ltd. NH-2
Week Ending :- 22-28
Fee Plaza Name ( Chainage) :-Mahuvan toll plaza, Mathura at CH- 164.500 KM
January-2023
No of Vehicles using the Project Highway during
Corresponding
Shift Type of Vehicle Preceding Week Week of Report
Week/Last Year
December- 2022 January- 2023
January 2022
A Fee Paying Traffic
A1 CAR 59449 81653 82430
A2 LCV 8111 8880 8527
A3 BUS 4725 6050 6162
A4 TRUCK 20418 22471 22517
A5 MAV 41508 44206 42505
A6 OSV 14 14 13
TOTAL (A) 134225 163274 162154
B Local Users (Monthly Pass)
B1 CAR 7829 8057 8450
B2 LCV 6 21 4
B3 BUS 0 0 0
B4 TRUCK 10 39 16
B5 MAV 51 221 2
B6 OSV 0 0 0
TOTAL (B) 7896 8338 8472
C Return Journey Reuse
C1 CAR 0 0 0
C2 LCV 0 0 0
C3 BUS 0 0 0
C4 TRUCK 0 0 0
C5 MAV 0 0 0
C6 OSV 0 0 0
TOTAL (C) 0 0 0
D Exempt Vehicles
D1 CAR 6012 5978 6100
D2 LCV 491 551 411
D3 BUS 17 26 13
D4 TRUCK 192 249 212
D5 MAV 49 151 109
D6 OSV 0 0 0
D7 Auto 470 226 172
D8 Tractor 1260 1188 997
TOTAL (D) 8491 8369 8014
E Total Traffic (A+B+C+D)
E1 CAR 73290 95688 96980
E2 LCV 8608 9452 8942
E3 BUS 4742 6076 6175
E4 TRUCK 20620 22759 22745
E5 MAV 41608 44578 42616
E6 OSV 14 14 13
E7 Auto 470 226 172
E8 Tractor 1260 1188 997
GRAND TOTAL 150612 179981 178640
SCHEDULE-N
WEEKLY TRAFFIC CENSUS - January 2023
Project Highways :-Delhi Agra Toll Road Pvt. Ltd. NH-2
Week Ending :- 29-31
Fee Plaza Name ( Chainage) :-Mahuvan toll plaza, Mathura at CH- 164.500 KM
January-2023
No of Vehicles using the Project Highway during
Corresponding
Shift Type of Vehicle Preceding Week Week of Report
Week/Last Year
December- 2022 January- 2023
January 2022
A Fee Paying Traffic
A1 CAR 27654 36102 35181
A2 LCV 3662 4081 3761
A3 BUS 1975 2438 2435
A4 TRUCK 9610 10039 9858
A5 MAV 19270 19329 18810
A6 OSV 10 4 2
TOTAL (A) 62181 71993 70047
B Local Users (Monthly Pass)
B1 CAR 3418 3192 3436
B2 LCV 2 5 9
B3 BUS 0 0 0
B4 TRUCK 10 13 13
B5 MAV 30 65 6
B6 OSV 0 0 0
TOTAL (B) 3460 3275 3464
C Return Journey Reuse
C1 CAR 0 0 0
C2 LCV 0 0 0
C3 BUS 0 0 0
C4 TRUCK 0 0 0
C5 MAV 0 0 0
C6 OSV 0 0 0
TOTAL (C) 0 0 0
D Exempt Vehicles
D1 CAR 2800 2568 2624
D2 LCV 213 257 181
D3 BUS 5 11 6
D4 TRUCK 95 92 91
D5 MAV 54 67 50
D6 OSV 0 0 0
D7 Auto 78 84 94
D8 Tractor 700 551 332
TOTAL (D) 3945 3630 3378
E Total Traffic (A+B+C+D)
E1 CAR 33872 41862 41241
E2 LCV 3877 4343 3951
E3 BUS 1980 2449 2441
E4 TRUCK 9715 10144 9962
E5 MAV 19354 19461 18866
E6 OSV 10 4 2
E7 Auto 78 84 94
E8 Tractor 700 551 332
GRAND TOTAL 69586 78898 76889
1 01.01.2023 8:45 PM Near Baghola Prithla 51+170/RHS 8 2 1 3 1 1 1 Bike & Pedistrain 1 1 No Ambulance
2 02.01.2023 8:45 PM Near Softa Village 44+500/RHS 2 2 2 3 1 1 1 Car & Auto 1 No RPV & Hydra
3 04.01.2023 7:28 PM Near Andata Hotel 70+060 RHS 3 3 2 3 1 1 1 Picup & Unknown 1 No RPV
4 05.01.2023 5:50 AM Near Bata Chowk 31+330/LHS 3 1 2 3 1 1 2 Bike & Unknown 1 No Ambulance & RPV
5 05.01.2023 7:50 AM Near Seekri Village 43+470/RHS 1 4 3 3 1 1 2 Picup 1 No RPV & Hydra
7 06.01.2023 8:05 PM Near Ratan Truck Dhabha 81+840/LHS 2 2 4 3 1 1 2 Bike & Unknown 2 No RPV
8 07.01.2023 21:50 pm Near saria Village 78+300/RHS 1 4 3 3 1 1 1 Picup 1 No RPV2 & Hydra karman
10 09.01.2023 6:25 AM Near saria Village 77+030/LHS 3 2 2 3 1 1 2 Auto & LCV 3 1 No Ambulance
11 09.01.2023 8:05 AM Near Banchari Village 83+330/RHS 3 1 2 3 1 1 2 Car & Truck 1 1 No Ambulance
M/s L.N. Malviya Infra Projects Pvt Ltd
12 09.01.2023 4:05 AM Near Prithla Village 48+200/RHS 3 2 2 3 1 1 2 Bike & Lcv 1 No Ambulance
14 12.01.2023 1:10 AM Near Bhagola Village 50+790/RHS 2 2 8 3 2 1 1 Lcv 1 No RPV & Hydra
15 12.01.2023 6:40 AM Near YMCA Collage 32+740/LHS 3 4 2 3 1 1 1 Car & Truck 1 No RPV & Hydra
16 13.01.2023 4:30 AM Near Ballabgarh Bus Stand 36+020/LHS 8 4 3 3 1 1 1 LCV 1 No RPV & Hydra
20.500 TO KM. 200 IN THE STATE OF HARYANA AND U.P ON DBFOT BASIS.
17 13.01.2023 4:00 PM Near Gadpuri Toll Plaza 36+020/LHS 4 3 2 3 1 1 1 Car & Bike 1 No Ambulance
85+860/LHS
73
20 13.01.2023 2:54 PM Near Hodal 3 3 2 3 1 1 1 Bike & Picup 2 No Ambulance
OPERATION & MAINTENANCE PERIOD OF 5 YEARS FOR “SIX LANINGOF DELHI-AGRA SECTION FROM KM.
M/s L.N. Malviya Infra Projects Pvt Ltd
INDEPENDENT ENGINEER SERVICES DURING
OPERATION & MAINTENANCE PERIOD OF 5 YEARS FOR “SIX LANINGOF DELHI-AGRA SECTION FROM KM.
20.500 TO KM. 200 IN THE STATE OF HARYANA AND U.P ON DBFOT BASIS.
RPV-03 Local
Car Reg
2 01.01.2023 14:33 hrs Highway Thana 146.440 LHS 8 3 3 3 1 4 1 1 Public & Police
No.UP85AN2671
Staff
5 02.01.2023 01:15 hrs Kheetam Jheel 181+400 RHS 3 1 2 3 1 4 2 Unknown Vehicle 1 Police Staff
A truck reg-
Our Ambulance,
truck Reg No- Dial 108
9 05.01.2023 14:48 hrs Dwapar Restorent 162+090 LHS 3 3 2 3 1 4 1 1
RJ25GA3125
M/s L.N. Malviya Infra Projects Pvt Ltd
Ambulance &
Our Hydra
RPV-3, our
10 06.01.2023 21:50 hrs Jaint Thana 132+830 LHS 1 4 3 3 2 4 2 Tractor Trolly 1
Hydra & Police
RPV-3,Jaint
truck Reg no- Ambulance,
11 07.01.2023 04:02 hrs Jaint Thana 132+760 LHS 3 3 3 3 2 4 2 1 5
HR39E0749 RPV-5 Police
staff, Pvt Hydra
Karman
Bus Reg No- Ambulance,
12 07.01.2023 20:22 hrs Chhata Underpass 112+880 LHS 4 2 2 3 1 4 1 4
UP85BT1719 RPV-5,Police
staff & Pvt
Car Reg
RPV-3 & Local
14 08.01.2023 17:07 hrs Nawada 149.260 RHS 3 4 3 3 3 4 1 No.DL3CCN5586&un 1
known Vehicle Public
INDEPENDENT ENGINEER SERVICES DURING
75
15 08.01.2023 22:05 hrs Refinery Gate No-09 159.810 LHS 8 3 1 3 3 4 2 1
No.UP85BZ4470 & Police Staff
OPERATION & MAINTENANCE PERIOD OF 5 YEARS FOR “SIX LANINGOF DELHI-AGRA SECTION FROM KM.
Bike Reg. No: Our Ambulance
16 09.01.2023 15:15 hrs Fateha villege 167.270 LHS 2 1 2 3 1 4 1 1 1
UP85AX3269 & Police Staff
RPV-04, Policr
Bus Reg No-
17 10.01.2023 08:33 hrs Shahjad Pur 175.000 RHS 3 4 3 3 1 4 2 4 Staff & Our
UP85AH9654
Hydra
RPV-04, Our
Truck Reg No-
18 12.01.2023 18:28 hrs PNC Flyover 177.100 RHS 3 3 2 3 2 4 1 2 Ambulance &
NL01AD0035
Our Hydra
RPV-4, Police
Eicher canter Reg.
19 13.01.2023 21:30 hrs PNC Flyover 176.460 LHS 3 4 3 3 1 4 2 1 staff & Pvt.
No: UP80ET4515
Hydra
RPV-3, Dial108
Eicher canter Reg Ambulance, pvt
20 14.01.2023 04:25 hrs GLA 129.350 RHS 1 3 3 3 1 4 1 1
No-HR55AF7164 hydra & Police
staff
22 14.01.2023 18:30 hrs HP Petrol Pump Arsena 179+510 LHS 4 4 4 3 1 4 1 Animal 1 1 RPV-4 & JCB
RPV-
Bike Reg
05.Ambulance,L
23 15.01.2023 09:24 hrs Sugar Mil Chhata 114.400 LHS 4 2 3 3 1 4 1 No.UP80GJ2657 & 1 1
26 17.01.2023 03:08 hrs K.D. Chauki 122+730 LHS 8 4 3 3 1 4 1 1 hydra & Police
DL1LV0375
staff
RPV-4, Pvt
Truck Reg. No:
27 17.01.2023 18:43 hrs Near Khndari Flyover 196+280 LHS 1 4 3 3 1 4 1 1 Hydra & Police
RJ52GA1325
staff
RPV-4, Our
Truck Reg no-
29 18.01.2023 17:33 hrs Brij Ki Rasoi (Farah) 169+220 LHS 3 2 2 3 1 4 1 1 Ambulance &
NL01AA4317
20.500 TO KM. 200 IN THE STATE OF HARYANA AND U.P ON DBFOT BASIS.
Police staff
RPV-5, Jaint
Max Pickup Reg No-
30 19.01.2023 04:58 hrs Chhatikara 133+950 LHS 1 3 8 3 1 4 1 1 1 Ambulance &
DL1LAF6334
Police staff
RPV-5, Jaint
INDEPENDENT ENGINEER SERVICES DURING
76
31 21.01.2023 04:00 hrs Agra Gwalior Dhaba Chauma 124+940 RHS 3 3 6 3 1 4 2 2 1
No-PB18AW8662 Hydra & Police
staff
OPERATION & MAINTENANCE PERIOD OF 5 YEARS FOR “SIX LANINGOF DELHI-AGRA SECTION FROM KM.
RPV-4, Our
Bike Reg No-
32 21.01.2023 23:22 hrs Brij Ki Rasoi (Farah) 169+050 RHS 6 2 1 3 1 4 1 1 Ambulance &
UP86AE6591
Police staff
Our Ambulane,
Eicher Canter Reg RPV-3, JCB,
33 22.01.2023 01:45 hrs HP Petrol Pump Refinery 159+990 RHS 3 2 2 3 1 4 1 2 1
no-DL1MA2030 Our Hydra &
Police staff.
Truck Reg
Our karman
Bike Reg No- AMB & RPV
43 28.01.2023 16:05 hrs Chhata Thana 112+280 RHS 2 3 4 3 1 4 1 2
UP85CD5807 staff ,Local
public & police
Our jait
truck ambulance ,
44 29.01.2023 12:20 hrs Chaumuha Villege 125+140 RHS 2 1 2 3 1 4 1 1
Reg.No.RJ52GA6979 Local public &
M/s L.N. Malviya Infra Projects Pvt Ltd
Police staff
Our Jait AMB ,
45 29.01.2023 01:04 hrs GLA University 128+860 LHS 2 1 2 3 1 4 1 Unknown Vehicle 1 RPV -5 & Police
Staff
RPV-03,
Goverdhan
47 29.01.2023 22:49 hrs Radha Vally 140.090 LHS 8 2 1 3 1 4 1 Thar Reg No. A/F 2 2
Ambulance,
Local Persons,
Our Jait
Ambulance ,
48 31.01.2023 19:00 hrs Near By GLA 129+760 LHS 8 1 4 3 1 4 1 Unknown 1
Local public &
20.500 TO KM. 200 IN THE STATE OF HARYANA AND U.P ON DBFOT BASIS.
Police staff
B 1- Overturning, 2- Head on collision, 3- Rear end collision, 4- Collision Brush / Slide wipe, 5- Right turn collision, 6- Skidding, 7- Left turn collision, 8- Others
D 1 - Drunken, 2 - Over speeding, 3 - Vehicle out of control, 4 - Fault of driver of motor vehicle/driver of other vehicle/cyclist/pedestrian/passenger, 5 - Defect in mechanical condition of motor vehicle/road condition, 6 - Dense Fog, 7- Road condition, 8-Dozed off
E 1 - Single lane, 2 - Two lanes, 3 - Three lanes or more with central divider (median), 4 - F lanes or more with central divider
F 1 - Straight road, 2 - Slight curve, 3 - Sharp curve, 4 - Flat road, 5 - Gentle incline, 6 - Steep incline, 7 - Hump, 8 - Dip
INDEPENDENT ENGINEER SERVICES DURING
G 1 - T-Junction, 2 - Y-Junction, 3 - F arm junction, 4 - Staggered junction, 5 - Junction with more than 4 arms, 6 - Roundabout junction, 7 - Manned rail crossing, 9 - Unmanned rail crossing.
77
H 1 - Fine, 2 - Mist/Fog, 3 - Cloudy, 4 - Light rain, 5 - Heavy rain, 6 - Hall/Sleet, 7 - Snow, 8 - Strong wind, 9 - Dust storm, 10 - Very hot, 11 - Very cold, 12 - Other extraordinary weather condition.
OPERATION & MAINTENANCE PERIOD OF 5 YEARS FOR “SIX LANINGOF DELHI-AGRA SECTION FROM KM.
M/s L.N. Malviya Infra Projects Pvt Ltd
INDEPENDENT ENGINEER SERVICES DURING
OPERATION & MAINTENANCE PERIOD OF 5 YEARS FOR “SIX LANINGOF DELHI-AGRA SECTION FROM KM.
20.500 TO KM. 200 IN THE STATE OF HARYANA AND U.P ON DBFOT BASIS.
Issue Descriptio
Long
Queue/Wait
at Toll Plaza - Delhi
29- Non (New rodelhi@nhai.org
Jan-23 Deepak 7459515 Jan-23 Emergency gadpuri Delhi) rodelhi01@gmail.com Mathura mat@nhai.org
Delhi
Rahul 29- Misbehaviour (New rodelhi@nhai.org
Jan-23 Chwal 7460621 Jan-23 by plaza staff Karman Delhi) rodelhi01@gmail.com Mathura mat@nhai.org
Road Delhi
29- Conditions of (New rodelhi@nhai.org
Jan-23 Sohail 7460516 Jan-23 the NH Badarpur Delhi) rodelhi01@gmail.com Mathura mat@nhai.org
Road Delhi
30- Conditions of (New rodelhi@nhai.org
Jan-23 Naveen 7462985 Jan-23 the NH Gadpuri Delhi) rodelhi01@gmail.com Mathura mat@nhai.org
Complaining Delhi
30- About NH (New rodelhi@nhai.org
Jan-23 Naveen 7463014 Jan-23 Services Gadpuri Delhi) rodelhi01@gmail.com Mathura mat@nhai.org
Caller is comp
Received Delhi)
Nil
37.Annexure
Second Milestone has been lapsed on 09.03.2014 and achievement by that time was 2% only. Now
the Concessionaire has submitted EOT of Milestone–II vide letter No DATR/SITE/IE/2014/2031
dated 26th December 2014,
Third MileStone: -has been lapsed on 10.07.2016 a notice under clause 12.4.2 has been issued vide
Independent Engineer IE's letter no. URSSWI/PMG/N1852/18/454 dated 08.10.2016
Schedule Six Laning Date: - Punch list for balance items for completion of project highway has
been prepared and has been submitted to the Authority and Concessionaire vide Independent
Engineer letter no. URSSWI/PMG/N1852/IE Delhi-Agra/2022/706 dated 28 th April 2022.
The I.E has issued the PCOD with punch list A and B vide URSSWI/PMG/IE Delhi-
AGRA/2022/818 dated 20.05.22
EOT Recommended
Achievement date as Total EOT on account of
Sl. On account of
Description envisaged in Concession proportionate delay of 637 days due
No. delay in Revised Mile
Agreement to non- availability of front on
environment Stones date
account of acquisition of land and
Clearance
tree cutting
Project Mile 255 days from the appointed (637-363)/912 x 255 = 77 days
1 363 days Sep 10, 2014
Stone-I date i.e. 27.06.2013 363+77= 440 days
Project Mile 510 days from the appointed (637-363)/912 x 510 = 153 days
2 363 days August 07, 2015
Stone-II date i.e. 09.03.2014 363+153= 516 days
Project Mile 770 days from the appointed (637-363)/912 x 770 = 231 days
3 363 days July 10, 2016
Stone-III date i.e. 24.11.2014 363+231= 594 days