You are on page 1of 80

M/s L.N.

Malviya Infra Projects Pvt Ltd


INDEPENDENT ENGINEER SERVICES DURING OPERATION & MAINTENANCE PERIOD OF 5 YEARS FOR “SIX
LANING OF DELHI-AGRA SECTION FROM KM. 20.500 TO KM. 200 IN THE STATE OF HARYANA AND U.P ON
DBFOT BASIS.

INDEPENDENT ENGINEER SERVICES DURING OPERATION & MAINTENANCE PERIOD OF 5 YEARS


FOR “SIX LANING OF DELHI-AGRA SECTION FROM KM. 20.500 TO KM. 200 IN THE STATE OF
HARYANA AND U.P ON DESIGN, BUILD, FINANCE, OPERATE AND TRANSFER (DBFOT) BASIS”.

INDEPENDENT ENGINEER
Submitted by:

M/s L.N. Malviya Infra Projects Pvt Ltd

CONCESSIONAIRE
DA TOLL ROAD PRIVATE LIMITED
Executive Summary

[MONTHLY PROGRESS REPORT-06]


FOR THE MONTH OF JANUARY-2023
MONTHLY PROGRESS REPORT JANUARY-2023

[1]
M/s L.N. Malviya Infra Projects Pvt Ltd
INDEPENDENT ENGINEER SERVICES DURING OPERATION & MAINTENANCE PERIOD OF 5 YEARS FOR “SIX
LANING OF DELHI-AGRA SECTION FROM KM. 20.500 TO KM. 200 IN THE STATE OF HARYANA AND U.P ON
DBFOT BASIS.

TABLE OF CONTENTS

MONTHLY PROGRESS REPORT JANUARY-2023

[2]
M/s L.N. Malviya Infra Projects Pvt Ltd
INDEPENDENT ENGINEER SERVICES DURING OPERATION & MAINTENANCE PERIOD OF 5 YEARS FOR “SIX
LANING OF DELHI-AGRA SECTION FROM KM. 20.500 TO KM. 200 IN THE STATE OF HARYANA AND U.P ON
DBFOT BASIS.

Sr. no Description Page no.


1. Executive Summary 5-12

2. Overall Road Condition 12

3. Key Reporting metrics 12

4. Key maintenance activities undertaken 13

5. Pending Issue 13

6. Recommended action by Independent Engineer 14

7. Strip Plan for MaintenancJanue 15-18

8. Project Overview 19

9. Key Project Detail 20-25

10 Location Map 26

11. Key Plan 26

12. Row Availavility 27

13. Summary of Project Feature 27-28

14. Critical issue and action taken 28-29

15. Issue and action log 29

16. Summary of Item 30-31

17. Obligation as per Contrac t 32

18. Major Maintenace and inspection schedule 33

19. Inspection report 33-39

20. Summary of NCR issued 39

21. Equipment based Inspection report 39

22. Monitoring of ETC Lane 40

23. Monthly ETC Report 40

MONTHLY PROGRESS REPORT JANUARY-2023

[3]
M/s L.N. Malviya Infra Projects Pvt Ltd
INDEPENDENT ENGINEER SERVICES DURING OPERATION & MAINTENANCE PERIOD OF 5 YEARS FOR “SIX
LANING OF DELHI-AGRA SECTION FROM KM. 20.500 TO KM. 200 IN THE STATE OF HARYANA AND U.P ON
DBFOT BASIS.

24. On ground Infrastructure Report 41

25. On ground ETC operation and SLA 41

26. Status of damage for breach of manitenace 41-43


activities

27. Damage for non completion of project facilities 43

28. Damage for non completion of Major 44


maintenance / periodic overlay

29. Change of Scope proposal 45-46

30. Status of pending dispute 47

31. Reports 48

32 Monthly Toll Collection Report 48-72

33. Accident Report 73-77

34. Details of complaints 78-79

35. Encroachment List 79

36. Lane Closure Report 79

37. Annexure 79-80

MONTHLY PROGRESS REPORT JANUARY-2023

[4]
M/s L.N. Malviya Infra Projects Pvt Ltd
INDEPENDENT ENGINEER SERVICES DURING OPERATION & MAINTENANCE PERIOD OF 5 YEARS FOR “SIX
LANING OF DELHI-AGRA SECTION FROM KM. 20.500 TO KM. 200 IN THE STATE OF HARYANA AND U.P ON
DBFOT BASIS.

1.1 Executive Summary & Summary of Current Month’s Progress

The Ministry of Road, Transport and Highway (MoRT&H), Government of India had entrusted National
Highways Authority of India with the task of implementing of Golden Quadrilateral project. The
National Highway Authority of India is engaged in the development of highways and as part of this
endeavor, the authority has decided to undertake development of six laning of Delhi-Agra section of NH-
2 from km. 20.500 to km. 200.00 through private participation on built operate and transfer basis.

Delhi-Agra section of National Highway no. 2 is a part of Golden Quadrilateral connecting cities of Delhi
and Kolkata. This portion of NH-2 also provides connectivity to East-West corridor and North-South
corridor of NHDP. This stretch from Delhi to Agra of NH-2 comes under NHDP Phase- V.

The Authority has awarded this project to M/s Reliance Infrastructure Limited on DBFOT basis. M/s
Reliance Infrastructure Limited has since promoted and incorporated the concessionaire as a limited
liability company (M/s. DA Toll Road Pvt. Ltd.) as the entity which shall undertake & perform the
obligations and exercise the right of the selected bidder.

This monthly progress report covers project highlights, progress of work and includes the “Independent
Engineers monthly inspection report” on the highway project as per clause 13.2 of Concession
Agreement on the works executed in the Month of January 2023

Description of the Project Road

The project road starts from Km 20+500 of NH-2 and ends at Km 200+000 of NH-2, thus making a total
The project road lies in State of Haryana and Uttar Pradesh, starts from Badarpur Delhi Border (Km
20.500) and passes through Faridabad industrial area, Ballabgarh, Palwal, Hodal, Kosi, Mathura and ends
at Agra (Km.200.00). The project road lies between latitudes of 28o28’18” and 27o12’22.7” north and
longitudes of 77’18’20.65’’ and 78’01’53” east.

MONTHLY PROGRESS REPORT JANUARY-2023

[5]
M/s L.N. Malviya Infra Projects Pvt Ltd
INDEPENDENT ENGINEER SERVICES DURING OPERATION & MAINTENANCE PERIOD OF 5 YEARS FOR
“SIX LANING OF DELHI-AGRA SECTION FROM KM. 20.500 TO KM. 200 IN THE STATE OF HARYANA AND
U.P ON DBFOT BASIS.

1.1.1 Physical Progress for the Month of January-2023: -0.00%


Overall Physical Progress : 99.79 %

% of progress % of progress achieved


Sl. No. Period
achieved up to date
1 16.10.2012 - Dec, 2013 0.85 0.85
2 Year 2014 14.15 15
3 Year 2015 27 42
4 Year 2016 19 61
5 Year 2017 14.5 75.5
6 Year 2018 12.25 87.75
7 Year 2019 (up to October-2019) 6.55 93.80
8 Year 2020(up to December-2020) 0.84% 94.64
9 Year 2021 3.76% 98.40
10 Year 2022 0.86% 99.79
Highway & Structure Progress of the Project
Work
As Per CA/COS Balance
Sr. No Description Completed
in Km
(Km) (Km)
1 Road completed up to BC (MCW) : 359 359 Nil
2 Road completed up to DBM level(MCW) : 359 359 Nil
3 Service road up to DBM : 204.16 204.16 Nil
4 Service road up to BC : 204.16 204.16 Nil
5 VUP's (CA 15+ COS 8 =23) : 23 Nos. 23 Nos. Nil
6 Palwal Elevated Progress
Piles : 720 720 Nil
Piles Cap : 86 86 Nil
Piers : 82 82 Nil
Piers Cap 82 82 Nil
Girder casting : 474 474 Nil
Up to Dec Up to January
Description
2021 2023
Physical
98.40% 99.79%
% of Progress
Financial% of Progress as per
100% 100%
Concessionaire MPR

MONTHLY PROGRESS REPORT JANUARY -2023. 6


M/s L.N. Malviya Infra Projects Pvt Ltd
INDEPENDENT ENGINEER SERVICES DURING OPERATION & MAINTENANCE PERIOD OF 5 YEARS FOR
“SIX LANING OF DELHI-AGRA SECTION FROM KM. 20.500 TO KM. 200 IN THE STATE OF HARYANA AND
U.P ON DBFOT BASIS.

1.1.2 Summary of Highway Progress


Work in progress-(Main Carriageway) : 359 Km
(Km 179.5X2= 359)
Work in Progress (Service Road) (Km : 204.16 Km out of 204.16 Km
BC-204.16
204.16)
DBM-204.16
Road completed up to BC layer & PQC : 359 km (BC 313 + PQC 46.00)
1.1.3 Summary of Structure Progress

: (14 no Flyover opened to traffic)


Elevated structure will be 2 km spanning between two
flyovers at KM 58+080 & Km 60+165 provided in the
Flyover (Total 16 Nos.)
Concession Agreement, these two flyovers also be four lane
instead of six lane provided in Concession Agreement (Work
Completed).
VUP 14 Nos. as per CA + 1 No VUP instead : (All completed and opened to traffic)
of PUP= Total 15 Nos.
VUP 9 Nos. Under COS (Total 24 Nos.) (All completed and opened to traffic)
Pedestrian Underpass (Total 9 Nos.) : (All completed and opened to traffic)
Minor Bridge on new service road : (7 no Minor Bridge opened to traffic)
(Total 8 Nos.) 1. Nos. Minor Bridge (Descoped)
Widening of existing Minor Bridge : 13 no Minor Bridge opened to traffic)
(Total 14 Nos.) 1. Nos. Minor Bridge (Descoped)
Culverts (Total 219 Nos.) : : 219 Nos. completed
Two Lane Overpass- (Total 2 Nos) : (Descoped)
: As per Concession Agreement widening of existing 8 nos.
ROB were proposed. But as per the latest Railway
ROB guidelines, Additional 3 lane ROB at all 8 locations are
finalized. A new contract will be awarded for the 8 nos.
ROB which is under process.
: As per Concession Agreement, 1440m long 4-lane elevated
highway was to be constructed at Sikandra (Agra) but the
proposal was not approved by the ASI. Subsequently, NHAI
decided on 22.03.2016 to shift the said elevated structure
to Palwal. The Hon’ble Minister RT&H on 05.04.2016
Palwal Elevated Structure
made an announcement in this regard in a public meeting
in Palwal Town. Palwal Elevated highway work
completed, and Traffic opened over Elevated Structure
on 10th April 2022

MONTHLY PROGRESS REPORT JANUARY -2023. 7


M/s L.N. Malviya Infra Projects Pvt Ltd
INDEPENDENT ENGINEER SERVICES DURING OPERATION & MAINTENANCE PERIOD OF 5 YEARS FOR
“SIX LANING OF DELHI-AGRA SECTION FROM KM. 20.500 TO KM. 200 IN THE STATE OF HARYANA AND
U.P ON DBFOT BASIS.

Highway & Structure Progress of the Project

Sl. Nos of
Particulars Unit Completed Balance Remarks
No. Structure

1 PUPs Nos. 11 11 0
2 VUPs Nos. 23 23 0
Minor/Major Bridges (New on
3 Nos. 12 12 0
SR)
Minor/Major Bridges
4 Nos. 14 14 0
(Widening on MCW)
5 Flyover Nos. 15 15 0
6 Elevated Highway Palwal Rmt 2195 100% 0

Additional work executed on EPC Mode through other Contractor

A. Haryana Section
Foot over Bridges (Faridabad District)

Sl. No. Location Chainage


1 Crown interior Mall 20+880
2 Link road- sector-29 24+680
3 Old Faridabad 27+350
4 Magpie Resort 28+300
5 Hanuman Temple 30+500
6 Ballabhgarh Grain Market 35+700
7 Between Elson and JCB factory 37+600

Minor/Major Bridge/VUPs

Sl.
Location of Structure Ch. Structure
No.
1 Gurgaon Canal 34+479 Minor Bridge
2 Sikri- Piyala mor 43+200 VUP
3 Sikri- Piyala mor 43+367 PUP
4 Dudhola 47+735 PUP
5 Dudhola 48+205 VUP

MONTHLY PROGRESS REPORT JANUARY -2023. 8


M/s L.N. Malviya Infra Projects Pvt Ltd
INDEPENDENT ENGINEER SERVICES DURING OPERATION & MAINTENANCE PERIOD OF 5 YEARS FOR
“SIX LANING OF DELHI-AGRA SECTION FROM KM. 20.500 TO KM. 200 IN THE STATE OF HARYANA AND
U.P ON DBFOT BASIS.

6 Palwal (HUDA Chowk) 56+340 VUP


7 Atohan 65+517 VUP
8 Hodal (Babri Chowk) 86+200 VUP

9 Ujhina Drain 91+900 Major Bridge

SERVICE Road

S. From
To Chainage Side
No. Chainage
1 63+600 64+600 RHS
2 64+400 67+120 RHS
3 67+500 67+750 RHS
4 69+220 69+580 RHS
5 69+080 71+300 LHS
6 69+660 70+000 RHS
7 70+840 70+920 RHS
8 70+990 71+300 RHS

B. UP Section
VUP/ Minor Bridge/Flyover/Box culvert

Sl.
Location of Structure Chainage Structure
No.
1 Mandi Crossing 143+640 VUP
2 IOCL Township 153+067 VUP
3 Refinery Gate no. 9 158+991 VUP
4 Panwari 185+800 VUP
5 Hindustan college 171+273 Minor Bridge
6 ISBT Agra 195+100 Flyover
7 Near Sabji Mandi 189+250 Box Culvert

Foot over Bridges

Sl. No. Location Chainage


1 Kosi Kalan 102+890
2 Ajijpur Village 105+950

MONTHLY PROGRESS REPORT JANUARY -2023. 9


M/s L.N. Malviya Infra Projects Pvt Ltd
INDEPENDENT ENGINEER SERVICES DURING OPERATION & MAINTENANCE PERIOD OF 5 YEARS FOR
“SIX LANING OF DELHI-AGRA SECTION FROM KM. 20.500 TO KM. 200 IN THE STATE OF HARYANA AND
U.P ON DBFOT BASIS.

3 Jait Village 131+770


4 Nayati Hospital 138+920
5 Romex School 140+130
6 RadhapuramChauraha 141+975
7 Sonkh Chauraha 144+400
8 ARTO Chauraha 148+570
9 Nawada Village 149+781
10 Barari Village 160+734
11 Mahuvan Tiraha 164+183
12 Farah 167+200
13 Hindustan College 171+883
14 Sur Kuti 181+860
15 Runakta 184+307
16 Shastri Puram 188+490
17 Kalash Mandir 190+930
18 Guru ka tal Gurudwara 193+645
19 Abu Lala ki Dargah 198+045
20 Langde ko chowki 199+485

1.1.3.1. PENDING PROCEEDINGS


 5.1 NHAI
Nil.
 5.2 Concessionaire
Nil
The Parties hereby confirm that in view of the full and final settlement arrived between the
Parties, in terms of the ‘In-Principle” approval granted by NHAI dated 07.01.2020 to the
Concessionaire and the subsequent introduction of the Harmonious Substitution circular
dated 24.02.2020. Thus, no cause of action remains pending for pursuing/filing any legal
proceedings now or in future, relating to this Concession Agreement.

MONTHLY PROGRESS REPORT JANUARY -2023. 10


M/s L.N. Malviya Infra Projects Pvt Ltd
INDEPENDENT ENGINEER SERVICES DURING OPERATION & MAINTENANCE PERIOD OF 5 YEARS FOR
“SIX LANING OF DELHI-AGRA SECTION FROM KM. 20.500 TO KM. 200 IN THE STATE OF HARYANA AND
U.P ON DBFOT BASIS.

1.1.4 Land Acquisition (Hindered Length)


Summary Haryana Section:
UP SECTION
SI No From To Side Length (m) Present Land status
1 162260 162320 LHS 60 RELIGIOUS STRUCTURE / MAZAR
2 174120 174160 LHS 40 POLICE CHOWKI
3 196400 197000 LHS 600 LA ISSUE / HIGH COURT CASE
4 156100 156260 RHS 160 IOCL ELECTRIC CABLE/PIPELINE
5 192490 192510 RHS 20 RELIGIOUS STRUCTURE / MAZAR
Total 880
Total (Haryana & UP Section) 880m

1.1.5Utility Shifting
ELECTRICAL UTILITIES

Name of Estimate/
State Chainage Status
Elec. Sub-Division
HR Old Faridabad 20.500 to 31.000 Completed & Handed over
HR Ballabhgarh 31.000 to 44.200 Completed & Handed over
HR Palwal-City 56.000 to 64.000 Completed & Handed over
HR Palwal Sub-Urban 45.000 to 55.700 Completed & Handed over
HR Deeghot 67.000 to 77.000 Completed & Handed over
HR Hodal 77.000 to 93.800 Completed & Handed over
UP Kosi-I 094+500 to 106+000 Completed & Handed over
UP Kosi-II 106+000 to 123+000 Completed & Handed over
UP Mathura Rural-I 123+000 to 141+000 Completed & Handed over
UP Mathura Rural-II 144+000 to 175+000 Completed & Handed over
UP Mathura City 142+000 to 152+000 Completed & Handed over
UP Sikandra Agra 176+000 to 190+000 Completed & Handed over

UP Torrent Power Ltd. 190+700 to 200+000 Completed & Handed over

MONTHLY PROGRESS REPORT JANUARY -2023. 11


M/s L.N. Malviya Infra Projects Pvt Ltd
INDEPENDENT ENGINEER SERVICES DURING OPERATION & MAINTENANCE PERIOD OF 5 YEARS FOR
“SIX LANING OF DELHI-AGRA SECTION FROM KM. 20.500 TO KM. 200 IN THE STATE OF HARYANA AND
U.P ON DBFOT BASIS.

UNDER GROUND UTILITIES work Completed


Sr. Type of Work Work Status
Shifting of water supply, sewerage and storm water drain Completed & Handed
1
(HR) over
Completed & Handed
2 Shifting of water supply line Haryana Tourism (HR)
over
Miscellaneous Work i.e. Sewerage and water supply MCF Completed & Handed
3
(HR) over
Completed & Handed
4 Shifting of water supply line PHED FBD (HR)
over
Completed & Handed
5 Shifting of water supply line (HUDA Deptt.) (HR)
over
Shifting of water supply and sewerage line (HUDA Deptt.) Completed & Handed
6
(HR) over
Completed & Handed
7 Road Crossing via trenchless (MCF, HR)
over
Shifting of water supply and sewerage line UP Jal Nigam Completed & Handed
8
Agra over
Completed & Handed
9 Shifting of Storme water drain (C & DS) UP Jal Nigam Agra
over

2. Overall Road Condition

Road Condition LHS RHS


Satisfactory road condition 179.5 179.5
Poor road condition Nil Nil
Total length of project 179.5 179.5

3. Key Reporting Matrics


Key metrics
No of pending NCRs 6
Damages amount recommended on Concessionaire (Rs Cr) Notice served reg
penalty

No of pending Change of Scope proposals NIL


No of pending disputes NIL
Monthly toll collection (Rs Cr) (If applicable) Enclosed
No of accidents Enclosed
No of encroachments Enclosed

MONTHLY PROGRESS REPORT JANUARY -2023. 12


M/s L.N. Malviya Infra Projects Pvt Ltd
INDEPENDENT ENGINEER SERVICES DURING OPERATION & MAINTENANCE PERIOD OF 5 YEARS FOR
“SIX LANING OF DELHI-AGRA SECTION FROM KM. 20.500 TO KM. 200 IN THE STATE OF HARYANA AND
U.P ON DBFOT BASIS.

4. Key maintenance activities undertaken


Assets Maintenance activities undertaken

Pavement Regular Maintenance is under progress

Shoulder Regular Maintenance is under progress

Drainage Regular Maintenance is under progress

Median Regular Maintenance is under progress

Road Furniture Regular Maintenance is under progress

Bridges Periodic Maintenance is under progress

Buildings Periodic Maintenance is under progress

Horticulture Regular Maintenance is under progress

5. Status of pending disputes

S.No Disputes Date of first Suggests Disputes Current Stage


Details submission to resolution by Amount till
IE IE applicable
1 NIL NIL NIL

2 NIL NIL NIL

MONTHLY PROGRESS REPORT JANUARY -2023. 13


M/s L.N. Malviya Infra Projects Pvt Ltd
INDEPENDENT ENGINEER SERVICES DURING OPERATION & MAINTENANCE PERIOD OF 5 YEARS FOR
“SIX LANING OF DELHI-AGRA SECTION FROM KM. 20.500 TO KM. 200 IN THE STATE OF HARYANA AND
U.P ON DBFOT BASIS.

6. Recommended action by Independent Engineer


1. Concessionaire has to maintain the project corridor safe for the users and has to
conduct Condition survey of Road to assess the pavement condition.
2. The safety aspects as directed by the NHAI, IE& Safety cell be complied.
3. Monthly work programme to be submitted by the Concessionaire including details and
planned activities of weekly and daily regular & Special Maintenance work.
4. Concessionaire shall keep a record of Daily inspection report at Toll Plaza for the
verification.
5. Route Patrol shall be made more effective and staff shall monitor the project Highway
for ensuring uninterrupted flow of traffic by minimizing the Wrong direction traffic.
6. Deficiencies in Avenue and median planation shall be rectified at the earliest.
7. Unauthorized median opening shall be closed and Unauthorized Access must be closed.
8. Prevention of over speeding is required to reduce the fatal accidents by providing speed
limit boards.
9. It has been observed that removal of advertisement boards has been done at many
locations but still removal of the same within ROW are still left at some locations.
Concessionaire is instructed to remove left over advertisement boards/hoardings etc on
priority.
10. All the balance missing sign & caution boards like T-Junction, Pedestrian Crossing,
Median gaps etc shall be restored in place from safety point of view.
11. It has been observed that blinkers at some locations are not functional, needs
repair/replacement on priority.
12. Sufficient / regular watering for plants in avenue & median is required.
13. Open RWH pit & manholes be covered on priority especially near Ajronda structure in
RHS.
14. Excavated portion while removing electrical poles at Ballabgarh Flyover be rectified.
15. Garbage dumped at many locations, be removed.
Concessionaire is hereby advised to rectify the above defects & deficiencies within seven days
in accordance with the provisions of Concession Agreement and submit compliance report.

MONTHLY PROGRESS REPORT JANUARY -2023. 14


M/s L.N. Malviya Infra Projects Pvt Ltd
INDEPENDENT ENGINEER SERVICES DURING OPERATION & MAINTENANCE PERIOD OF 5 YEARS FOR
“SIX LANING OF DELHI-AGRA SECTION FROM KM. 20.500 TO KM. 200 IN THE STATE OF HARYANA AND
U.P ON DBFOT BASIS.

7. Strip Chart

MONTHLY PROGRESS REPORT JANUARY -2023. 15


M/s L.N. Malviya Infra Projects Pvt Ltd
INDEPENDENT ENGINEER SERVICES DURING OPERATION & MAINTENANCE PERIOD OF 5 YEARS FOR
“SIX LANING OF DELHI-AGRA SECTION FROM KM. 20.500 TO KM. 200 IN THE STATE OF HARYANA AND
U.P ON DBFOT BASIS.

MONTHLY PROGRESS REPORT JANUARY -2023. 16


M/s L.N. Malviya Infra Projects Pvt Ltd
INDEPENDENT ENGINEER SERVICES DURING OPERATION & MAINTENANCE PERIOD OF 5 YEARS FOR
“SIX LANING OF DELHI-AGRA SECTION FROM KM. 20.500 TO KM. 200 IN THE STATE OF HARYANA AND
U.P ON DBFOT BASIS.

MONTHLY PROGRESS REPORT JANUARY -2023. 17


M/s L.N. Malviya Infra Projects Pvt Ltd
INDEPENDENT ENGINEER SERVICES DURING OPERATION & MAINTENANCE PERIOD OF 5 YEARS FOR
“SIX LANING OF DELHI-AGRA SECTION FROM KM. 20.500 TO KM. 200 IN THE STATE OF HARYANA AND
U.P ON DBFOT BASIS.

MONTHLY PROGRESS REPORT JANUARY -2023. 18


M/s L.N. Malviya Infra Projects Pvt Ltd
INDEPENDENT ENGINEER SERVICES DURING OPERATION & MAINTENANCE PERIOD OF 5 YEARS FOR
“SIX LANING OF DELHI-AGRA SECTION FROM KM. 20.500 TO KM. 200 IN THE STATE OF HARYANA AND
U.P ON DBFOT BASIS.

8. Project Overview Key Project Details

Project Name Six Laning of Delhi-Agra Section of National


Highway No. 2 in the state of Haryana and
Uttar Pradesh from Km. 20.500 to Km. 200.00
under NHDP Phase-V as BOT

NH no (New/old) NH-2
Mode of the Project DBFOT
No. of Lanes 6-Lane
Length of the Project 179.50 Km
Total Project cost 1928.22 Cr.
Concessionaire/ Contractor M/s DA Toll Road Pvt. Ltd. Toll Road Pvt.
Ltd.

Date of Award (LOA date) 19.05.2010


Appointed Date 16.10.2012
Commercial Operation Date (COD) 15.04.2015
Concession Period 912 days from 16-10-2012
O&M Period 5 years
Independent Engineer M/s L.N. Malviya Infra Projects Pvt. Ltd
IE Agreement Date 20.07.2022
IE Mobilization Date 05.08.2022
IE Schedule Completion Date 04.08.2027
IE EOT (Extension of Time) NA

MONTHLY PROGRESS REPORT JANUARY -2023. 19


M/s L.N. Malviya Infra Projects Pvt Ltd
INDEPENDENT ENGINEER SERVICES DURING OPERATION & MAINTENANCE PERIOD OF 5 YEARS FOR
“SIX LANING OF DELHI-AGRA SECTION FROM KM. 20.500 TO KM. 200 IN THE STATE OF HARYANA AND
U.P ON DBFOT BASIS.

9. Project Overview

1.3.1.1 Details of Service Road


Total Length of Service Road on both side Carriageway = 204.16 KM
Carriageway width of Service road is 7.0 Mtr Total Length = 164.95 KM
Service Road 7.00 Mtr Left Side Length = 83.84 KM
Service Road 7.00 Mtr Right Side Length = 81.11 KM
Carriageway width of Service road is 5.50 Mtr Total Length = 39.210 KM
Service Road 5.50 Mtr Left Side Length = 18.76 KM
Service Road 5.50 Mtr Right Side Length = 20.45 KM

1.3.1.2 Rehabilitation/ Repair/widening of existing Major Bridge = nil


1.3.1.3. List of Intersections

S. No. Particulars Number


1 Major Junctions 53
2 Minor Junctions 239
Total 292
1.3.1.4 List of Structures

Sl. No. Particulars Unit Numbers

1 Pipe Culverts / Slab/ Box Culverts Nos. 219

2 PUPs Nos. 10

3 VUPs Nos. 23

4 Minor Bridges (New on SR) Nos. 8

5 Minor Bridges (Widening on MCW) Nos. 14

6 Flyover Nos. 14

7 Major Bridge Nos. 1

8 4 Lane Viaduct Nos. 1

9 ROB Nos. 8

MONTHLY PROGRESS REPORT JANUARY -2023. 20


M/s L.N. Malviya Infra Projects Pvt Ltd
INDEPENDENT ENGINEER SERVICES DURING OPERATION & MAINTENANCE PERIOD OF 5 YEARS FOR
“SIX LANING OF DELHI-AGRA SECTION FROM KM. 20.500 TO KM. 200 IN THE STATE OF HARYANA AND
U.P ON DBFOT BASIS.

1.3.1.5 List of Bus Shelters & Bus Bays

S. No. Particulars Number

1 Number of Bus Shelters & Bus bays in the Project 23

1.3.1.7 Toll Plaza


S.No. Existing Toll Plaza Location
1 Gadpuri Toll Plaza 46+000
2 Karman Toll Plaza (Km 94) 94+000
Mahuvan Toll Plaza
3 164+000

1.3.1.8 Locations of Rigid Pavement

Sl. No. Start End Side Length


1 42+100 47+850 LEFT 5+750
2 49+325 56+640 LEFT 7+315
3 61+250 67+975 LEFT 6+725
4 69+180 74+530 LEFT 5+350
5 75+680 82+500 LEFT 6+820
6 82+500 83+300 RIGHT 0+800
7 85+200 91+450 RIGHT 6+250
8 91+450 94+000 LEFT 2+550
9 93+300 94+000 RIGHT 0+700
10 115+000 118+800 RIGHT 3+800
11 119+200 122+000 LEFT 2+800
12 132+600 134+100 RIGHT 1+500
13 134+700 137+150 LEFT 2+450
14 137+300 138+400 RIGHT 1+100

Total Length of Rigid pavement = 53.910 KM


 Left Side Rigid Pavement Length = 39.76 KM
 Right Side Rigid Pavement Length = 14.15 KM

MONTHLY PROGRESS REPORT JANUARY -2023. 21


M/s L.N. Malviya Infra Projects Pvt Ltd
INDEPENDENT ENGINEER SERVICES DURING OPERATION & MAINTENANCE PERIOD OF 5 YEARS FOR
“SIX LANING OF DELHI-AGRA SECTION FROM KM. 20.500 TO KM. 200 IN THE STATE OF HARYANA AND
U.P ON DBFOT BASIS.
1.3.1.9 Service Roads

MONTHLY PROGRESS REPORT JANUARY -2023. 22


M/s L.N. Malviya Infra Projects Pvt Ltd
INDEPENDENT ENGINEER SERVICES DURING OPERATION & MAINTENANCE PERIOD OF 5 YEARS FOR
“SIX LANING OF DELHI-AGRA SECTION FROM KM. 20.500 TO KM. 200 IN THE STATE OF HARYANA AND
U.P ON DBFOT BASIS.

MONTHLY PROGRESS REPORT JANUARY -2023. 23


M/s L.N. Malviya Infra Projects Pvt Ltd
INDEPENDENT ENGINEER SERVICES DURING OPERATION & MAINTENANCE PERIOD OF 5 YEARS FOR
“SIX LANING OF DELHI-AGRA SECTION FROM KM. 20.500 TO KM. 200 IN THE STATE OF HARYANA AND
U.P ON DBFOT BASIS.

Major Structures Locations


S.No. Type of Structure Location Chainage

1 Flyover NHPC Chowk 21+750


2 Minor Bridge Near NHPC 21+860
3 VUP MewlaMaharajpur-(COS) 23+660
4 Flyover BadhkalChowk 25+650
5 Minor Bridge Near Swastik Steel Industry 26+065
6 Flyover Old Faridabad Chowk 26+950
7 Flyover AjrondaChowk 29+500
8 Flyover Bata Chowk 31+100
9 VUP YMCA (COS) 32+165
10 Minor Bridge Gurgaon Canal 34+530
11 Flyover BallabhgarhChowk 35+050
12 ROB Ballabhgarh 36+800
13 VUP Sector 59 Ph-2 38+200
14 VUP HUDA Bypass (COS) 40+960
15 Over Pass Baghaula (Tarapur Junction) 48+200
16 Minor Bridge Bagola 54+100
17 VUP Alapur-Firozepur Intersection 54+435

18 Flyover Amarpur – Palwal Intersection 58+070


19 Flyover SohnaChowk 60+165
20 VUP Tikribrahaman 63+170
21 PUP Atohan 65+200
22 VUP Bamnikhera (COS) 68+125
23 VUP Dighot-Aurangabad 71+750
24 VUP Hatla 77+300
25 VUP Banchari 83+270
26 Minor Bridge Widening Banchari 84+365
27 PUP School Area, Hodal 87+875
28 Flyover HodalChowk 88+825
29 PUP Haryana Roadways Bus Stand, Hodal 90+625
30 Minor Bridge , Widening Nandghawan 92+960
31 Flyover Kosi City 101+300
32 ROB Kosi 103+250
33 Minor Bridge Agra Canal Bridge 104+085
34 Minor Bridge Sarah Rajwale 104+480

35 PUP School Area, Dautana Village 107+630

36 VUP ChattaBarsana (COS) 112+100

37 VUP Chatta-GoverdhanChowk 112+700


38 PUP Nanlagiri 116+500

MONTHLY PROGRESS REPORT JANUARY -2023. 24


M/s L.N. Malviya Infra Projects Pvt Ltd
INDEPENDENT ENGINEER SERVICES DURING OPERATION & MAINTENANCE PERIOD OF 5 YEARS FOR
“SIX LANING OF DELHI-AGRA SECTION FROM KM. 20.500 TO KM. 200 IN THE STATE OF HARYANA AND
U.P ON DBFOT BASIS.

S.No. Type of Structure Location Chainage

39 VUP NariSamari 118+800


40 VUP instead of PUP Akrror Inter College (COS) 122+750
41 Minor Bridge Widening Chaumuhan 124+490
42 VUP Chaumuhan 125+900
43 VUP GLA University (COS) 128+068
44 VUP Chatkara 134+555
45 PUP KD Dental College & Hospital 137+242
46 VUP Mathura 139+335
47 ROB Govindpur 140+810
48 RUB Mathura Bangar 141+390
49 Minor Bridge GaneshraNala 141+600
50 Flyover GoverdhanChowk 142+575
51 VUP (Jai Gurudev Temple – (COS) 145+100
52 ROB Narholi (Mathura) 147+600
53 Over Pass Mathura CanttBharatpur 147+730
54 ROB Birjapur (Mathura) 147+800
55 ROB Birjapur (Mathura) 148+080
56 Flyover GokulChowk 152+000
57 PUP Baad Village 154+400
58 Minor Bridge Widening Baad 154+965
59 ROB Baad 156+350
60 Flyover Mathura Refinery 157+775
62 ROB Fatiha 166+300
63 VUP Farah 167+600
64 PUP Bheem Nagar 170+460
65 Minor Bridge Widening Farah 171+091
66 PUP Churmura-Siyapura Village Area 172+990
67 VUP Raipura 175+730
68 Minor Bridge Widening Near BMOS College 179+110
69 VUP Runaketa Industrial Area 183+527
70 VUP SabjiMandiSikandra-(COS) 189+900
71 Viaduct – 1.44 Km Sikandara Fort Area 190+660
72 Flyover KandhariChowk 195+680
73 Flyover Sultan GanjPulia 198+415
74 Minor Bridge Sultanganj Ki Pulia 198+552
75 Flyover Water Works Chowk 199+800

MONTHLY PROGRESS REPORT JANUARY -2023. 25


M/s L.N. Malviya Infra Projects Pvt Ltd
INDEPENDENT ENGINEER SERVICES DURING
OPERATION & MAINTENANCE PERIOD OF 5 YEARS FOR “SIX LANINGOF DELHI-AGRA SECTION FROM KM.
20.500 TO KM. 200 IN THE STATE OF HARYANA AND U.P ON DBFOT BASIS.

10. Location Map.

ST A R T OF
P R O J E CT
R O AD

UTTAR PRADESH

EN D OF
P R O J E CT
R O AD

IN D E X M A P E X H IB IT N O . 2 .A

MONTHLY PROGRESS REPORT JANUARY -2023. 26


M/s L.N. Malviya Infra Projects Pvt Ltd
INDEPENDENT ENGINEER SERVICES DURING
OPERATION & MAINTENANCE PERIOD OF 5 YEARS FOR “SIX LANINGOF DELHI-AGRA SECTION FROM KM.
20.500 TO KM. 200 IN THE STATE OF HARYANA AND U.P ON DBFOT BASIS.

Current Issues & Recommended Actions by Independent Engineer


 Punch list for balance items for completion of project highway has been prepared and has
been submitted to the Authority and Concessionaire vide Independent Engineer letter no.
URSSWI/PMG/N1852/IE Delhi-Agra/2022/706 dated 28th April 2022. Action is pending at the
level of Concessionaire.

11. Key Plan

12. Row Availavility

60 to 100 meter as per CA

13. Summary of Features of Project

S.No Particulars Value


Six Laning of Delhi-Agra
Section of National Highway
No. 2 in the state of Haryana
and Uttar Pradesh from Km.
ProjectName 20.500 to Km. 200.00 under
NHDP Phase – V as BOT
(Toll).

1 No of flyovers 15
2 Service Road 204.16 Km
3 ROBs 08
5 RUBs 01
6 RUB location (chainage) Mathura Bangar Ch.
141+390

7 No of Bypass Nil
8 Length of Bypass Nil
9 No of Major Bridges 01
10 No of Minor Bridges 02
11 No of Culvert 219
12 No of VUP 23
13 No of PUP/Cattle Underpass 10

MONTHLY PROGRESS REPORT JANUARY -2023. 27


M/s L.N. Malviya Infra Projects Pvt Ltd
INDEPENDENT ENGINEER SERVICES DURING
OPERATION & MAINTENANCE PERIOD OF 5 YEARS FOR “SIX LANINGOF DELHI-AGRA SECTION FROM KM.
20.500 TO KM. 200 IN THE STATE OF HARYANA AND U.P ON DBFOT BASIS.

14 No of Major Intersection/ Junction 53


15 No of Toll Plaza 03
16 Location of Toll Plaza (chainage) Ch. 46+00 Gadpuri Toll
Ch.94+00 Karman Toll
Ch. 164+00 Mahuvan Toll
17 No of Truck Laybye nil
18 No of Bus Bays 23
19 No of Wayside Amenities Under Process
20 Location of Wayside Amenities (chainage) Km136

14. Critical Obligations of Authority as per contract

As per clause 6.1 of the CA


Concessionaire obligationsas per Contract

Concession Agreement, Scope of Project, stipulates that the Project shall be executed on the Site as
described in Schedule “A.” The Scope of the Project shall include performance and execution by the
Concessionaire of all design, engineering, financing, procurement, construction, completion, operation
and maintenance of the Project during Concession Period as described in Schedule “B” of this
Agreement. The Concessionaire shall undertake its obligations at its own cost and risk.

The Concessionaire shall operated and maintain the project Highway by itself, or through O&M
Contractors and if required, modify, repair or otherwise make improvements to the project Highway to
comply with Specifications and standards, and other requirements set forth in this Agreement. Good
Industries Practice, Applicable laws and Applicable Permits and manufacturer’s guidelines and
instructions with respect to toll systems, and more specifically:

(i) Permitting safe, smooth and uninterrupted flow of traffic during normal operating
conditions;
(ii) Charging, collecting and retaining the Fees in accordance with these Agreements;
(iii) Minimizing disruption to traffic in the event of accidents or other incidents affecting the
safety and use of the Project Highways by providing a rapid and effective response and
maintaining liaison procedures with emergency services;
(iv) Undertaking routine maintenance including prompt repairs of potholes, cracks, concrete
joints, drains, line marking, lighting and signage;
(v) Undertaking major maintenance such as resurfacing of pavements, repairs to structures,
repairs and refurbishment of tolling system and hardware and other equipment;
(vi) Carrying out periodic preventive maintenance to Project Highways including tolling
system;
(vii) Preventing with the assistance of concerned law enforcement agencies unauthorized
entry to and exit from the Project Highway;

MONTHLY PROGRESS REPORT JANUARY -2023. 28


M/s L.N. Malviya Infra Projects Pvt Ltd
INDEPENDENT ENGINEER SERVICES DURING
OPERATION & MAINTENANCE PERIOD OF 5 YEARS FOR “SIX LANINGOF DELHI-AGRA SECTION FROM KM.
20.500 TO KM. 200 IN THE STATE OF HARYANA AND U.P ON DBFOT BASIS.

(viii) Preventing with the assistance of the concerned law enforcement agencies encroachments
on the Project Highway including Site and preserve the right of way of the Project
Highway;
(ix) Maintaining a public relations unit to interface with and attend to suggestions from users
of the Project Highways, the media, Government Agencies, and other external agencies;
and
(x) Adherence to the safety standards set out in Schedule ‘S”.

15. Issue and action log

Site was inspected by us on various dates along with the staff of Concessionaire’s
representatives during the month. During inspection, site visit & meeting at Toll plazaswith
the representatives of NHAI and Concessionaire, various issues were discussed regarding
maintenance of road, Safety Regulation, Environmental Status, Mobilization, Maintenance
Work Plan Schedule, Progress, Quality of the work, Procurement of Material, Plants and
equipment installation, Technical & Administration etc.
During the month, the undersigned has raised the various issues during frequent visit to site
regarding Maintenance work plan schedule, Progress effective utilization resources, Highway
Management and other Safety aspects of the Project.
Further during the meeting on various occasions following manuals\reports etc. has been
discussed:
i) Monthly Maintenance Report and implementation of methodology as stated in
Maintenance Manual,
ii) Various important correspondence issued by NHAI, the Contractor and the Consultant.
iii) Quality Assurance Plan.
iv) Safety Issues and implementation of Safety Plan.
v) Maintenance Programme.
vi) Traffic Management Plan.
vii) Maintenance Manual.
viii) Toll Management Systems.
ix) ETC & Fastag.
x) Implementation of Various Guidelines, directives issued by MoRT&H and NHAI from time
to time.
During the meetings it was suggested that well planned sequence of operation and proper
methodology should be used to have best results. Concessionaire has been advised to submit
the Monthly Maintenance Programme well in time to ensure the proper implementation.

MONTHLY PROGRESS REPORT JANUARY -2023. 29


M/s L.N. Malviya Infra Projects Pvt Ltd
INDEPENDENT ENGINEER SERVICES DURING
OPERATION & MAINTENANCE PERIOD OF 5 YEARS FOR “SIX LANINGOF DELHI-AGRA SECTION FROM KM.
20.500 TO KM. 200 IN THE STATE OF HARYANA AND U.P ON DBFOT BASIS.

16. Summary of items (Cumulative/ Deficiencies)

S.No Description Unit Total Work Work Balance Remarks


Done Done
upto during
Previous Reporting
month month
1 Carriageway of paved shoulders
a) Pot Holes M2 Nil Nil
b) Roughness value
exceeding
2,500mm
c) Cracking in more
than 5% of road
surface
d) Rutting exceeding
10mm in more
than 2% of road
surface
e) Bleeding/Skidding
f) Raveling
g) Damage to
pavement edges
exceeding 10cm
2 Hard/Earth Shoulders
a) Rain cuts/gullies
in slope
b) Edge drop at
shoulders
exceeding 40mm
3 Drains and culverts
a) Cleaning of
Culvert
b) Damage to or
silting of culverts
c) Silting of drains in
urban/semi urban
areas
4 Road Furniture
a) Sign Boards
b) Kilometer Stones

MONTHLY PROGRESS REPORT JANUARY -2023. 30


M/s L.N. Malviya Infra Projects Pvt Ltd
INDEPENDENT ENGINEER SERVICES DURING
OPERATION & MAINTENANCE PERIOD OF 5 YEARS FOR “SIX LANINGOF DELHI-AGRA SECTION FROM KM.
20.500 TO KM. 200 IN THE STATE OF HARYANA AND U.P ON DBFOT BASIS.

c) Metal Beam Crash


Barrier
d) Bus Shelters

e) Junction signs

f) Median Grills

g) Studs

h) Delineators

i) Road Marking

j) Kerb Painting

k) Guard Posts

5 Street Lighting and telecom (ATMS)


a) Street lights

b) Telecom

6 Trees and plantation


a) Removal of
vegetation
affecting sight line
and road
structures
b) Replacement of
trees and buses
7 Buildings and bridges
a) Rest areas

b) Toll plazas

c) Bridges

MONTHLY PROGRESS REPORT JANUARY -2023. 31


M/s L.N. Malviya Infra Projects Pvt Ltd
INDEPENDENT ENGINEER SERVICES DURING
OPERATION & MAINTENANCE PERIOD OF 5 YEARS FOR “SIX LANINGOF DELHI-AGRA SECTION FROM KM.
20.500 TO KM. 200 IN THE STATE OF HARYANA AND U.P ON DBFOT BASIS.

17. Independent Engineer obligations as per Contract

 The Consultants shall perform the services and carry out their obligations hereunder with all
due diligence, efficiency and economy, in accordance with generally accepted professional
techniques and practices, and shall observe sound management practices and employ
appropriate advanced technology and safe and effective equipment , machinery materials and
methods” The Consultants shall always ” act, in respect of any matter relating to this Contract
or to the Services, as faithful advisers to the Client, and shall at all times support and safeguard
the Client’s legitimate interests in any dealing with Sub-consultants or Third parties and as per
Independent consultancy Agreement .
 OPERATION AND MAINTENANCE STAGE:

 The Independent Engineer shall Inspect the Project Highway once every month,
preferably after receipt of the monthly status report from the Concessionaire, but before
the 20th (twenty) day of each monthly in any ease, and make out an O & M Inspection
Report setting forth an overview of the status, quality and safety of O & M, including
conformity with the maintenance and safety requirements. In a separate section of O&M
Inspection Report, the Independent Engineer shall describe in reasonable detail the
lapses, defects or deficiencies observed by it the operation and maintenance of the
Project Highway. The Independent Engineer shall send a copy of its O&M Inspection
Report to the Authority and the Concessionaire within 7 (seven) days of Inspection.

 The Independent Engineer shall in its O&M Inspection Report specify test if any, that the
Concessionaire shall carry out or cause to be carried out for the purpose of determining
that the Highway Project is in conformity with the maintenance requirements. It shall
monitor and review the results of such test and remedial measures, if any, taken by the
Concessionaire on his behalf. The Independent Engineer shall examine the request of the
Concessionaire for closure of any lane(s) of the carriageway for undertaking maintenance
/ repair thereof, keeping in view the need to minimize disruption to traffic and the time
required for completing such maintenance / repair in accordance with Good Industry
practice, It shall grant permission with such modification, as it may deem necessary,
within 3 (Three) days of receiving a request from the Concessionaire. Upon expiry of the
permitted period of such lane(s) and in case of delay, determine the Damages payable by
the Concessionaire to the Authority under clause 17.7.

MONTHLY PROGRESS REPORT JANUARY -2023. 32


M/s L.N. Malviya Infra Projects Pvt Ltd
INDEPENDENT ENGINEER SERVICES DURING
OPERATION & MAINTENANCE PERIOD OF 5 YEARS FOR “SIX LANINGOF DELHI-AGRA SECTION FROM KM.
20.500 TO KM. 200 IN THE STATE OF HARYANA AND U.P ON DBFOT BASIS.

18. Major Maintenance and inspection schedule

19. Inspection Report

INSPECTION REPORT OF IE FOR THE MONTH OF JANUARY-2023


DELHI-AGRA SECTION (KM. 20.500 TO KM 200) OF NH-2.

Project: Independent Engineer Services during Operation &Maintenance period of 5 years for “Six
Laning of Delhi-Agra section from Km. 20.500 to Km. 200 in the State of Haryana and U.P. on
Design, Build, Finance, Operate and Transfer (DBFOT) basis”
1. INTRODUCTION :
Site was inspected by us on various dates along with the staff of Concessionaire’s
representatives during the month. During inspection, site visit & meeting at Toll plazaswith
the representatives of NHAI and Concessionaire, various issues were discussed regarding
maintenance of road, Safety Regulation, Environmental Status, Mobilization, Maintenance
Work Plan Schedule, Progress, Quality of the work, Procurement of Material, Plants and
equipment installation, Technical & Administration etc.
During the month, the undersigned has raised the various issues during frequent visit to site
regarding Maintenance work plan schedule, Progress effective utilization resources, Highway
Management and other Safety aspects of the Project.
Further during the meeting on various occasions following manuals\reports etc. has been
discussed:
xi) Monthly Maintenance Report and implementation of methodology as stated in
Maintenance Manual,
xii) Various important correspondence issued by NHAI, the Contractor and the Consultant.
xiii) Quality Assurance Plan.
xiv) Safety Issues and implementation of Safety Plan.
xv) Maintenance Programme.
xvi) Traffic Management Plan.
xvii) Maintenance Manual.
xviii) Toll Management Systems.
xix) ETC & Fastag.

MONTHLY PROGRESS REPORT JANUARY -2023. 33


M/s L.N. Malviya Infra Projects Pvt Ltd
INDEPENDENT ENGINEER SERVICES DURING
OPERATION & MAINTENANCE PERIOD OF 5 YEARS FOR “SIX LANINGOF DELHI-AGRA SECTION FROM KM.
20.500 TO KM. 200 IN THE STATE OF HARYANA AND U.P ON DBFOT BASIS.

xx) Implementation of Various Guidelines, directives issued by MoRT&H and NHAI from time
to time.
During the meetings it was suggested that well planned sequence of operation and proper
methodology should be used to have best results. Concessionaire has been advised to submit
the Monthly Maintenance Programme well in time to ensure the proper implementation.

2. OPERATION & MAINTENANCE STATUS OF THE PROJECT


(1) Main Carriageway and Service Road.
 Main Carriageway is still incomplete in 207m in UP section as mentioned in Punch List.
 Service road work in Balance length of 1260m (Haryana 780m and 480m in UP) has not
been completed. Same be completed on priority.
 The work of construction of RWH pits is in progress but the speed is very slow, which
should be expedited.
 Some Km. stone 165 (LHS) is required to be fixed properly.
 11 no. median cuts in Haryana section and 16 no. in UP section have not been closed.
 Work of Kerb painting on raised kerb be taken up with the marking of chainages at every
20m interval. Chainage marking, work is very slow.
 At few location sign board are damaged like Km. 157+360 RHS, Ch. 167+920 RHS, which
should be repaired/replaced immediately. Gantry damage at km. 21+020 LHS, 151+440
LHS.
 Potholes observed at many locations Ch. 117+730 RHS, Ch. 153+740 LSR.
 Unsatisfactory cleaning observed over & below structures (Below Palwal Elevated Haryana
Section) (Flyovers- Kosi, Chhata, Chaumua in UP section).
 Kerb damaged at, Both side Median cut damage at Ch. 44+560, Ch. 148+810 LHS, Ch.
175+320 LHS, Ch. 119+400 RHS.
 Km stone 107+000, Km 80 laid down not painted.
 Kerb faded at Ch. 175+200 to 176+400 LHS, Ch. 183+000 to 185+000 LHS, Ch. 175+250 to
176+380 LHS, Ch. 126+700 to 127+500 RHS, Ch. 125+400 to 126+000 both side,
Ch.130+510 to 130+650, Ch. 47+477 Median, Ch. 47+190 Median have blackened /faded
which should be redone to facilitate the traffic.
 Crash barrier not painted at outer edge at chainage156+300 LHS and 189+970 BHS.
 MBCB damaged at Km. 101+820, Ch. 170+560 RHS, Garbage/debris dumped at many
locations on the Project Highway, 37+290 LSR, 39+300 LSR 39+400 LSR, 160+110 RHS,
167+850 RHS, Ch. 56+580 Median, Ch.47+477 Median Both Side, be removed on priority.

MONTHLY PROGRESS REPORT JANUARY -2023. 34


M/s L.N. Malviya Infra Projects Pvt Ltd
INDEPENDENT ENGINEER SERVICES DURING
OPERATION & MAINTENANCE PERIOD OF 5 YEARS FOR “SIX LANINGOF DELHI-AGRA SECTION FROM KM.
20.500 TO KM. 200 IN THE STATE OF HARYANA AND U.P ON DBFOT BASIS.

(2) ROW
 The fixing of Boundary pillars is incomplete.Ch.35+000 to 36+000 RHS MCW Cleaning
required, 33+500 RHS S/R Cleaning required, 43+900 RHS S/R lane Cleaning required.
(3) Drainage System
 Pipe drains are chocked at many locations especially Side drain in Ch. 43+380 RHS Damage
Drain cover and Chamber Damage. Manhole covers is being laid at some places but that is
not fixed properly.
Construction of drains in some built-up areas is still pending. Cleaning of Covered drains
shall be carried out regularly. At many locations the drains are not functioning, require
urgent attention.
 The establishments like Dhabas, Factories and retail out let have encroached upon ROW.
However some of the encroachments have been removed under the structure, which are
again encroached. Ch. 49+500 LHS, 160+350 LHS, 162+500 LHS, 100+420 RHS, 100+180
RHS.
4) Separators, PGRs and Footpath
 Separator damaged at Km. 187+820, Ch. 185+600 RHS.
 PGRS have been found not painting, unauthorized opening, damaged at many locations like
Ch. 38+480 RHS, Ch. 30+620(MGR), Ch. 25+180,(MGR) Ch. 33+460(MGR), Ch. 32+860
(MGR) Ch. 82+940, Ch. 50+040 LHS, Ch. 153+870 LHS, 167+350 RHS needs repair for
safety point of view.
 PGR not paint at Km. 34+020 RHS, Km. 34+060 RHS, km.44+930 RHS, 46+960 to 47+000
RHS, Km. 54+040 LHS
 PGR & MGR faded at few locations. Ch. 109+200 to 111+700 RHS, Km.135+000 to 136+900
median, 149+600 to 151+750, 196+350 to 197+100 median.
 At Km 130+520 RHS, 153+700 RHS footpath are damaged.
 Sign Board Ch. 82+670 LHS, 60+700 RHS, 68+190 Median, 58+300 Median, 57+310 Sign
Board damage.
 Delineator damage Ch. 54+790, 43+700 Median,

5) Structures
Minor Bridge at Km. 92+980
 Repair of abutment A2 and pier work is under progress.
Palwal Elevated Highway.
 Cleaning of pier caps is yet not completed.

MONTHLY PROGRESS REPORT JANUARY -2023. 35


M/s L.N. Malviya Infra Projects Pvt Ltd
INDEPENDENT ENGINEER SERVICES DURING
OPERATION & MAINTENANCE PERIOD OF 5 YEARS FOR “SIX LANINGOF DELHI-AGRA SECTION FROM KM.
20.500 TO KM. 200 IN THE STATE OF HARYANA AND U.P ON DBFOT BASIS.

 Bearings should be cleaned on regular basis.


 Expansion joints should be cleaned on regular basis.
 Gap between seismic stoppers and girder is less than specified and foreign object
inserted within this gap, needs to be removed.
 Repairing done at pier shaft (P-03) is not as per specification.
Ballabgarh Flyover
 Gap between seismic stoppers and girder is less than specified and foreign object
inserted within this gap, needs to be removed.

Old Faridabad flyover


 Cleaning of pier caps should be cleaned on regular basis.
 Police booth and other temporary structures have been placed in the obligatory
span, obstructing the view need to be removed.
 Bearings should be cleaned on regular basis.
 Expansion joints should be cleaned on regular basis.
 Expansion joint of flyovers have not been cleaned mainly in UP section.

Flyover (in UP Section)


Km. 101+070 and
 Bearings should be cleaned on regular basis.
 Expansion joints should be cleaned on regular basis.
 Expansion joint of flyovers have not been cleaned.
Goverdhan Chauraha at Km. 142+280
 Bearings should be cleaned on regular basis.
 Expansion joints should be cleaned on regular basis.
 Expansion joint of flyovers have not been cleaned mainly in UP section.
Gokul Chowk Mathura at Ch. 151+710
 Bearings should be cleaned on regular basis.
 Expansion joints should be cleaned on regular basis.
 Expansion joint of flyovers have not been cleaned mainly in UP section.
Mathura Refinery at Ch. 158+000
 Bearings should be cleaned on regular basis.
 Expansion joints should be cleaned on regular basis.
 Expansion joint of flyovers have not been cleaned mainly in UP section.
 Vegetation at RE Wall should be clean on regular basis.

MONTHLY PROGRESS REPORT JANUARY -2023. 36


M/s L.N. Malviya Infra Projects Pvt Ltd
INDEPENDENT ENGINEER SERVICES DURING
OPERATION & MAINTENANCE PERIOD OF 5 YEARS FOR “SIX LANINGOF DELHI-AGRA SECTION FROM KM.
20.500 TO KM. 200 IN THE STATE OF HARYANA AND U.P ON DBFOT BASIS.

VUPs (In UP Section)


 Weep hole have not been provided as per structural drawing.
 Locked bearing placed at the time of construction have still not been opened. All
bearing should be free from lock. (Chainage 152+000 & 195+680)
 Drainage pipe provided at flyover and VUP are in damaged condition.
 Cautionary board of narrow bridge (7 ROB BHS and one flyover In Agra) have been
provided as the road merges from six lane to four lane which should be installed
100 m advance to avoid any accident.
 Slab edge corner damaged at chainage 198+415 due to which steel is exposed.
 Expansion Joint needs cleaning at regular intervals. Affected locations are km.
142.700, 101.500 and 146.400.

PUP (in UP Section)


 Weep hole have not been provided as per structural drawing.
 Wearing course has not been provided as per drawing on bottom slab.
 At chainage 154+400 reinforcement of bottom slab is visible which should be
repaired as per MORT&H specifications.
 At chainage 172+990 slope protection should be provided as per drawing.
6) INCIDENT MANAGEMENT :
 One number of Ambulances is available at each Toll Plaza. The ambulances are
being regularly checked for maintenance of First Aid Box, Oxygen and other
equipment.
 One no. of Tow away crane is available at each Toll Plaza and is functional.
 One no. of Patrolling Vehicle is available at each Toll Plaza and is functional.
 Proper furnishing is to be done in the medical aid post.
7) TOLL PLAZA
Following facilities has been provided at toll plazas and checked during the inspection for
their functionality. .
 12 Lanes in each direction at Gadpuri Toll Plaza, 8 lane each at Karman Toll Plaza
and 7 lanes each at Mahuvan Toll Plaza are provided.
 All the lanes are fully Hybrid ETC.
 Medical aid post and Vehicle Rescue post have been provided in Toll Plaza Building.
 02 No’s of Static Weigh Bridge are provided at each Toll Plaza and are functional.
 Toll Lanes are provided with WIM and are operational. Road users are being
informed from time to time about the benefits of Fastags.

MONTHLY PROGRESS REPORT JANUARY -2023. 37


M/s L.N. Malviya Infra Projects Pvt Ltd
INDEPENDENT ENGINEER SERVICES DURING
OPERATION & MAINTENANCE PERIOD OF 5 YEARS FOR “SIX LANINGOF DELHI-AGRA SECTION FROM KM.
20.500 TO KM. 200 IN THE STATE OF HARYANA AND U.P ON DBFOT BASIS.

 Concessionaire has been advised to maintain the Toll plaza premises and clean the
Toll booths and Lanes regularly.
8) SAFETY
 Hazard Markers
Hazard Markers are present at the required locations like Median Openings, near
structures. Cleaning at a few locations is required and Concessionaire has been
informed to take the action at the earliest.
 Thermoplastic Pavement marking and Kerb Painting
Kerb painting and Thermoplastic Painting work has been faded at some sections.
Contractor has been asked to redo the faded road marking stretches.
 Crash Barriers
Crash Barriers have been installed as per the provisions. Concessionaire has been
asked to put the retro reflective tapes on it for night vision.
9) Street lighting works
Installation of street lighting poles/high mast is completed. Electricity Connection at Toll
plazas has already been done.

10) CONCLUSION:-

16. Concessionaire has to maintain the project corridor safe for the users and has to conduct
Condition survey of Road to assess the pavement condition.
17. The safety aspects as directed by the NHAI, IE& Safety cell be complied.
18. Monthly work programme to be submitted by the Concessionaire including details and
planned activities of weekly and daily regular & Special Maintenance work.
19. Concessionaire shall keep a record of Daily inspection report at Toll Plaza for the
verification.
20. Route Patrol shall be made more effective and staff shall monitor the project Highway for
ensuring uninterrupted flow of traffic by minimizing the Wrong direction traffic.
21. Deficiencies in Avenue and median planation shall be rectified at the earliest.
22. Unauthorized median opening shall be closed and Unauthorized Access must be closed.
23. Prevention of over speeding is required to reduce the fatal accidents by providing speed
limit boards.
24. It has been observed that removal of advertisement boards has been done at many locations
but still removal of the same within ROW are still left at some locations. Concessionaire is
instructed to remove left over advertisement boards/hoardings etc on priority.
25. All the balance missing sign & caution boards like T-Junction, Pedestrian Crossing, Median
gaps etc shall be restored in place from safety point of view.

MONTHLY PROGRESS REPORT JANUARY -2023. 38


M/s L.N. Malviya Infra Projects Pvt Ltd
INDEPENDENT ENGINEER SERVICES DURING
OPERATION & MAINTENANCE PERIOD OF 5 YEARS FOR “SIX LANINGOF DELHI-AGRA SECTION FROM KM.
20.500 TO KM. 200 IN THE STATE OF HARYANA AND U.P ON DBFOT BASIS.

26. It has been observed that blinkers at some locations are not functional, needs
repair/replacement on priority.
27. Sufficient / regular watering for plants in avenue & median is required.
28. Open RWH pit & manholes be covered on priority especially near Ajronda structure in RHS.
29. Excavated portion while removing electrical poles at Ballabgarh Flyover be rectified.
30. Garbage dumped at many locations, be removed.
Concessionaire is hereby advised to rectify the above defects & deficiencies within seven days in
accordance with the provisions of Concession Agreement and submit compliance report.
Sample photographs taken at site are enclosed herewith.

20. Summary of NCR : Details of Schedule -K Issued and Maintenance carried out by
Concessionaire till date

S. No Total NCR issued NCR issued in Total NCR NCR closed Balance
till previous reporting month (B) NCR
month (A) (A+B-C)
1 26 11 37 33 4

21. Equipment based Inspection report

The Reports are enclosed as ANNEXURE

MONTHLY PROGRESS REPORT JANUARY -2023. 39


M/s L.N. Malviya Infra Projects Pvt Ltd
INDEPENDENT ENGINEER SERVICES DURING
OPERATION & MAINTENANCE PERIOD OF 5 YEARS FOR “SIX LANINGOF DELHI-AGRA SECTION FROM KM.
20.500 TO KM. 200 IN THE STATE OF HARYANA AND U.P ON DBFOT BASIS.

22. Monitoring of ETC lane

Fee
Collected
No of Vehicles (For Previous Fee Collected (For Fee Per Vehicle (For No of Vehicles (For
(For
Month) Previous Month) Current Month) Current Month)
Current
Month)
516794 35854165 0 487170 33758840
39856 4966445 0 38412 4828405
117610 32032385 0 114831 31364950
0 0 0 0 0
188845 84129875 0 179546 79953970
170 81970 0 141 68355
0 0 0 0 0
0 0 0 0 0
0 0 0 0 0
0 0 0 0 0
0 0 0 0 0
0 0 0 0 0

23. Monthly ETC

No of Vehicles Fee Collected No of Fee Fee Per No of


(For (For Vehicles Collected Vehicle Vehicles Fee Collected
Vehicle Type Corresponding Corresponding (For (For (For (For (For Current
month of month of Previous Previous Current Current Month)
previous year) previous year) Month) Month) Month) Month)
CAR/JEEP/VAN-
39017 2218690 43402 2658535 45 37526 2302880
T1
LCV-T1 17644 1795610 19934 2169080 75 18803 2104985
BUS/TRUCK-T1 8789 1573750 9614 1887210 160 8602 1654715
3 AXLE-T1 7063 1412510 7579 1598975 170 7621 1617690
MAV-T1 20091 5982340 24636 6763105 245 23034 6483345
OSV-T1 9 3160 16 4800 300 27 8400
CAR/JEEP/VAN-
52099 2590380 57122 3132760 40 45327 2459620
T2
LCV-T2 27906 2199510 31217 2708285 65 27635 2362860
BUS/TRUCK-T2 17788 2933295 17806 3204390 140 17236 3023930
3 AXLE-T2 12008 2954000 12110 2853155 150 11434 2468860
MAV-T2 30204 9406800 39058 11441870 220 37595 10736330
OSV-T2 53 13680 21 5565 265 40 12455
Monthly Pass
73 20805 91 28665 315 87 27405
Amomunt T1
Monthly Pass
38 10830 31 9765 315 24 7560
Amomunt T2

MONTHLY PROGRESS REPORT JANUARY -2023. 40


M/s L.N. Malviya Infra Projects Pvt Ltd
INDEPENDENT ENGINEER SERVICES DURING
OPERATION & MAINTENANCE PERIOD OF 5 YEARS FOR “SIX LANINGOF DELHI-AGRA SECTION FROM KM.
20.500 TO KM. 200 IN THE STATE OF HARYANA AND U.P ON DBFOT BASIS.

24. Onground Infrastructure Report

Equipment as
Hardware
Equipment Owner per
/Software 8 Units Damaged/Missing Remarks
/Provider specifications
Description
(Y / N)
Hardware-T1 24+2 0 Comvision Y Gadpuri
Software-T1 24+2 0 Comvision Y Gadpuri
Hardware-T1 16+2 0 Comvision Y Karman
Software-T1 16+2 0 Comvision Y Karman
Intercom
unit is
damaged at
Mahuvan
Hardware-T1 14 0 Comvision Y Plaza
Software-T1 14 0 Comvision Y Mahuvan

25. On Ground ETC operation and SLA

Av
er
ag
e
Avera Tr
Average
Average ge an
Queue Average Average Average
Lan Queue length Trans sa
length Transaction Transaction Transactio
e during no action cti
during (Cash) (RFID) n (Wallet)
peak time (Card on
peak time
s) ti
me
(ot
he
rs)
1- 60
T1 50 m 10 m 45 sec 8 sec sec 30 sec 0
2- 60
T1 50 m 10 m 45 sec 8 sec sec 30 sec 0
3- 60
T1 50 m 10 m 45 sec 8 sec sec 30 sec 0
4- 60
T1 50 m 10 m 45 sec 8 sec sec 30 sec 0
5- 60
T1 50 m 10 m 45 sec 8 sec sec 30 sec 0
6- 60
T1 50 m 10 m 45 sec 8 sec sec 30 sec 0
7- 60
T1 50 m 10 m 45 sec 8 sec sec 30 sec 0
8- 60
T1 50 m 10 m 45 sec 8 sec sec 30 sec 0

MONTHLY PROGRESS REPORT JANUARY -2023. 41


M/s L.N. Malviya Infra Projects Pvt Ltd
INDEPENDENT ENGINEER SERVICES DURING
OPERATION & MAINTENANCE PERIOD OF 5 YEARS FOR “SIX LANINGOF DELHI-AGRA SECTION FROM KM.
20.500 TO KM. 200 IN THE STATE OF HARYANA AND U.P ON DBFOT BASIS.

1- 60
T2 70 m 15 m 45 sec 8 sec sec 30 sec 0
2- 60
T2 70 m 15 m 45 sec 8 sec sec 30 sec 0
3- 60
T2 70 m 15 m 45 sec 8 sec sec 30 sec 0
4- 60
T2 70 m 15 m 45 sec 8 sec sec 30 sec 0
5- 60
T2 70 m 15 m 45 sec 8 sec sec 30 sec 0
6- 60
T2 70 m 15 m 45 sec 8 sec sec 30 sec 0
7- 60
T2 70 m 15 m 45 sec 8 sec sec 30 sec 0
1- 60
T1 50 m 10 m 45 sec 8 sec sec 30 sec 0
2- 60
T1 50 m 10 m 45 sec 8 sec sec 30 sec 0
3- 60
T1 50 m 10 m 45 sec 8 sec sec 30 sec 0
45 8
4- se se
T1 50 m 10 m c c 60 sec 30 sec 0
5-
T1 50 m 10 m 45 sec 8 sec 60 sec 30 sec 0
6-
T1 50 m 10 m 45 sec 8 sec 60 sec 30 sec 0
7-
T1 50 m 10 m 45 sec 8 sec 60 sec 30 sec 0
8-
T1 50 m 10 m 45 sec 8 sec 60 sec 30 sec 0
1-
T2 70 m 15 m 45 sec 8 sec 60 sec 30 sec 0
2-
T2 70 m 15 m 45 sec 8 sec 60 sec 30 sec 0
3-
T2 70 m 15 m 45 sec 8 sec 60 sec 30 sec 0
4-
T2 70 m 15 m 45 sec 8 sec 60 sec 30 sec 0
5-
T2 70 m 15 m 45 sec 8 sec 60 sec 30 sec 0
6-
T2 70 m 15 m 45 sec 8 sec 60 sec 30 sec 0
7-
T2 70 m 15 m 45 sec 8 sec 60 sec 30 sec 0
1-
T1 50 m 10 m 45 sec 8 sec 60 sec 30 sec 0

MONTHLY PROGRESS REPORT JANUARY -2023. 42


M/s L.N. Malviya Infra Projects Pvt Ltd
INDEPENDENT ENGINEER SERVICES DURING
OPERATION & MAINTENANCE PERIOD OF 5 YEARS FOR “SIX LANINGOF DELHI-AGRA SECTION FROM KM.
20.500 TO KM. 200 IN THE STATE OF HARYANA AND U.P ON DBFOT BASIS.

2-
T1 50 m 10 m 45 sec 8 sec 60 sec 30 sec 0
3-
T1 50 m 10 m 45 sec 8 sec 60 sec 30 sec 0
4-
T1 50 m 10 m 45 sec 8 sec 60 sec 30 sec 0
5-
T1 50 m 10 m 45 sec 8 sec 60 sec 30 sec 0
6-
T1 50 m 10 m 45 sec 8 sec 60 sec 30 sec 0
7-
T1 50 m 10 m 45 sec 8 sec 60 sec 30 sec 0
8-
T1 50 m 10 m 45 sec 8 sec 60 sec 30 sec 0
1-
T2 70 m 15 m 45 sec 8 sec 60 sec 30 sec 0
2-
T2 70 m 15 m 45 sec 8 sec 60 sec 30 sec 0
3-
T2 70 m 15 m 45 sec 8 sec 60 sec 30 sec 0
4-
T2 70 m 15 m 45 sec 8 sec 60 sec 30 sec 0
5-
T2 70 m 15 m 45 sec 8 sec 60 sec 30 sec 0
6-
T2 70 m 15 m 45 sec 8 sec 60 sec 30 sec 0
7-
T2 70 m 15 m 45 sec 8 sec 60 sec 30 sec 0

26. Status of Damage

Nil

27. Damage for non completion of Project facilities

I.E has recommended for the damages of 47.44 cr vide letter no6434 dated 25.01.23 to
grant the EOT to the Concessionaire upto 20.05.2022(Date of issuance of provisional
completion certificate) by imposing damages @0.1%the performance security of Rs
107.89 Cr for each day of delay as per Article 15 of the CA.

MONTHLY PROGRESS REPORT JANUARY -2023. 43


M/s L.N. Malviya Infra Projects Pvt Ltd
INDEPENDENT ENGINEER SERVICES DURING
OPERATION & MAINTENANCE PERIOD OF 5 YEARS FOR “SIX LANINGOF DELHI-AGRA SECTION FROM KM.
20.500 TO KM. 200 IN THE STATE OF HARYANA AND U.P ON DBFOT BASIS.

28. Damage for non completion of major maintenance / periodic overlay

 Notice has been served by the IE vide letter no LNMIPPL/DATR/Delhi-Agra/2023/355


Date: 08.02.2023 Reg. Maintenance Requirement as per Schedule- K-(No.36) –PGR Damage- Notice
under clause 17.8.1 of Concession Agreement.
 Notice has been served by the IE vide letter no LNMIPPL/DATR/Delhi-Agra/2023/357
Date: 08.02.23 Maintenance Requirement as per Schedule- K-(No.38) –PGR Damage- Notice under
clause 17.8.1 of Concession Agreement.
 Notice has been served by the IE vide letter no LNMIPPL/DATR/Delhi-Agra/2023/359
Date: 08.02.23 Maintenance Requirement as per Schedule- K-(No.32) –PGR Damage- Notice under
clause 17.8.1 of Concession Agreement.
 Notice has been served by the IE vide letter no LNMIPPL/DATR/Delhi-Agra/2023/302 Date:
09.01.2023 Reg. Maintenance Requirement as per Schedule- K-(No.31) – Deficiencies observed at
Gadpuri & Karman Toll Plazas.

MONTHLY PROGRESS REPORT JANUARY -2023. 44


M/s L.N. Malviya Infra Projects Pvt Ltd
INDEPENDENT ENGINEER SERVICES DURING
OPERATION & MAINTENANCE PERIOD OF 5 YEARS FOR “SIX LANINGOF DELHI-AGRA SECTION FROM KM.
20.500 TO KM. 200 IN THE STATE OF HARYANA AND U.P ON DBFOT BASIS.

29. Change of Scope Proposal

Change of Scope
NHAI has accorded “in-principle” Approval for COS& Issued change of scope notice

In principal
Approval Work done /
COS Order
COS Scope of work (As approved by Certified
Value
the authority amount
letters)
Extension of Flyover - Ballabgarh
35+050
1
Additional VUP - 23+660 64.71 63.74 57.99
Additional VUP - 32+150

2 VUP at GLA University in UP at Km 128 10.00


12.48 11.71

VUP @ KM 40+907 @ Huda Bypass


PUP @ KM 89+030 - Hodal
PUP to VUP &123+075 Akbarpur
VUP @ KM 145+050 & PUP @ KM
3 110.81
145+500 - Jai Gurudev Ashram 132.70 126.43
VUP @ KM 68+640 Bamnikheda & SR
VUP @ KM 189+960 - Sabji Mandi
VUP @ KM 112+200 Chatta

4 Palwal Elevated
59.70 56.52

Total Amount
268.62 252.66

MONTHLY PROGRESS REPORT JANUARY -2023. 45


M/s L.N. Malviya Infra Projects Pvt Ltd
INDEPENDENT ENGINEER SERVICES DURING
OPERATION & MAINTENANCE PERIOD OF 5 YEARS FOR “SIX LANINGOF DELHI-AGRA SECTION FROM KM.
20.500 TO KM. 200 IN THE STATE OF HARYANA AND U.P ON DBFOT BASIS.

COS NOTICE ISSUED


COS COS Works Amount Notice Received on
COS-I (a) Ballabhgarh Flyover extension 14.10.2014
(b) 23+660 – VUP 64.37 14.10.2014
(c) 32+147 - VUP 14.10.2014
COS-II 128+068 – VUP – GLA Unvercity 10.00 06.05.2015
COS-III (a) VUP at Km 145+100, Jai Gurudev Ashram 22.03.2016
(b) VUP at Km 189+800, Sabzi Mandi, 22.03.2016
(c) VUP in place of PUP at Km 122 22.03.2016
(d) VUP at HUDA Bypass – 40+907 22.03.2016
110.81
(e) PUP at Railway road junction, Hodal 22.03.2016
(f) VUP at Km 68+125, Bamnikhera 22.03.2016
(g) SR of 4.06 Kms in Bamnikhera village 22.03.2016
(h) Drain in Hodal (Km 88 to Km 90 both sides) 22.03.2016
3(A) VUP at 112+100-Chatta 18.83 14.09.2017
TOTAL AMOUNT ( Cr) 204.01

COS ORDER RECEIVED


Notice Order
COS COS Works Amount
Recd on Received Date
Ballabhgarh Flyover extension
1 23+660 – VUP 63.74 14.10.2014 20.09.2016
32+147 - VUP
2 128+068-VUP-GLA University 12.48 06.05.2015 08.08.2018

Notice
Order
COS COS Works Amount Received
Received Date
on
Additional VUP at HUDA bye pass @ Ch. 40+950
Additional VUP at Bamnikhera(Km. 68+125)
Additional PUP at Hodal Km. 89.030
Additional drain in Hodal (Km 88 to Km 90, BHS)
3 113.87 22.03.2016 09.06.2017
Construction of VUP instead of PUP at Km. 123.075
Additional VUP at Km 145+045, Jai Gurudev
Additional PUP at Km 145+500, Jai Gurudev
Additional VUP at Km 189+800, Sabzi Mandi

MONTHLY PROGRESS REPORT JANUARY -2023. 46


M/s L.N. Malviya Infra Projects Pvt Ltd
INDEPENDENT ENGINEER SERVICES DURING
OPERATION & MAINTENANCE PERIOD OF 5 YEARS FOR “SIX LANINGOF DELHI-AGRA SECTION FROM KM.
20.500 TO KM. 200 IN THE STATE OF HARYANA AND U.P ON DBFOT BASIS.

30. Pending disputes :Draianage Issues of Faridabad MCF

To curb the long pending persistent issue of water logging existing at the project stretch at 48
locations (20 in Haryana Section and 28 in UP Section), the concessionaire undertook the
resolution of drainage issues and has successfully resolved most of them, The same have been
acknowledged with due back up of RFI’s. However, drainage issue at 7 locations in Haryana still
exists due to the issue beyond the reasonable control of the concessionaire and all such locations
are subjected to water logging due the adjoining communities surface water run-off and
accordingly the concessionaire has notified multiple times to the concerned Municipal
Corporations for the needful intervention and NHAI has also made several correspondences to
the concerned public bodies for their needful intervention. As acknowledged during site
inspections the issue is largely resolved in the entire section except Faridabad Section and the
matter is jointly pursued with the MCF.

The list of affected locations supplied by the Concessionaire where sewer over flow is taking
place, has been inspected jointly by the IE along with Concessionaire and found that the
Concessionaire has made reasonable efforts to resolve the drainage issue at all the locations
but still sewerage water is coming on the Service road at 7 locations which relates to MC
Faridabad and unless suitable action is not taken up by MCF, the permanent solution of water
logging at these locations cannot be resolved. The sewer line laid by MCF is very old which
have now blockage at many places resulting in overflow of sewer.
It has also been observed that at three locations, private residential colonies are at higher level
and have open side drains which overflow and water comes on Service road. Moreover, at
some locations the remedial measures such as pump house has been set up by the
Concessionaire but the MCF has not taken the hand over for further maintenance.
Furthermore the Concessionaire requested for shifting of the all-balance 7 number locations in
a punch list-B. In this regard the Authority has also communicated to the MCF and
DC,Faridabad to intervene and to resolve the issue by their end vide NHAI letter no 69096 and
69097 dated 06.02.2023 and accordingly, we can take undertaking from the concessionaire to
resolve all concerned locations in due coordination with the MCF and the concessionaire
should also undertake to take the whole responsibility of surface water run-off pertaining to
the road and must also keep dewatering resources at large , to ensure MCW and Service road
remains water logging free even in a case of unexpected unprecedented rains.

MONTHLY PROGRESS REPORT JANUARY -2023. 47


M/s L.N. Malviya Infra Projects Pvt Ltd
INDEPENDENT ENGINEER SERVICES DURING
OPERATION & MAINTENANCE PERIOD OF 5 YEARS FOR “SIX LANINGOF DELHI-AGRA SECTION FROM KM.
20.500 TO KM. 200 IN THE STATE OF HARYANA AND U.P ON DBFOT BASIS.

31. Report

32. Monthly Toll Collection

Gadpuri Toll Plaza

SCHEDULE- M
MONTHLY FEE STATEMENT
Project Highways :-Delhi Agra Toll Road Pvt. Ltd. NH-2 Month - Jan - 23
Fee Plaza Name ( Chainage) :- Gadpuri Toll Plaza CH- 46 KM
For the Corresponding Month of Previous year
For Proceeding Month (Dec.2022) For the Month reported up on (Jan -2023)
(June.2021)
Types of
Travel Type No. of Vehicles
Vehicles Fee collected Fee collected Fee Per Vehicles Fee collected
No. of Vehicles No. of Vehicles (including ETC
( In Rs.) ( In Rs.) (in Rs.) ( In Rs.)
Traffic)
1 2 3 4 5 6 7 8 9
One Way 0 0 378176 43768340 110 367132 42317770
(A) Car
Return 0 0 188251 10353805 55 188913 10390215
One Way 0 0 32184 5829250 175 31510 5654075
(B) LCV
Return 0 0 17139 1456815 85 17083 1452055
One Way 0 0 12991 4652985 355 13276 4743865
(C) Bus Return 0 0 10869 1956420 180 11304 2034720
One Way 0 0 46585 16666540 355 45611 16284560
(D) Truck
Return 0 0 14817 2667060 180 14648 2636640
(E) Multi-
One Way 0 0 79076 43278995 545 77014 42090350
axle
Return 0 0 20673 5685075 275 19272 5299800
Truck
(F) Oversized One Way 0 0 200 141085 695 86 59770
vehicle Return 0 0 155 53475 345 58 20010
Total 0 0 801116 136509845 3355 785907 132983830

MONTHLY PROGRESS REPORT JANUARY -2023. 48


M/s L.N. Malviya Infra Projects Pvt Ltd
INDEPENDENT ENGINEER SERVICES DURING
OPERATION & MAINTENANCE PERIOD OF 5 YEARS FOR “SIX LANINGOF DELHI-AGRA SECTION FROM KM.
20.500 TO KM. 200 IN THE STATE OF HARYANA AND U.P ON DBFOT BASIS.

Karman Toll Plaza


SCHEDULE- M
MONTHLY FEE STATEMENT
Project Highways :-Delhi Agra Toll Road Pvt. Ltd. NH-2
Month :- January - 2023
Fee Plaza Name ( Chainage) :- Karman Fee Plaza, Palwal at CH- 94.00 KM
For the Corresponding Month
For Proceeding Month
of Previous year (January - For the Month reported upon (January - 2023)
(December - 2022)
Types of 2022)
Travel Type
Vehicles Fee Per No. of Vehicles
No. of Fee collected No. of Fee collected Double Traffic Fee collected
Vehicles (in (including ETC
Vehicles ( In Rs.) Vehicles ( In Rs.) Payment ( In Rs.)
Rs.) Traffic)

1 2 3 4 5 6 7 8 9 10

One Way 359997 32028085 85 336156 14311 29789695


(A) Car
Return 137961 6208245 45 130901 0 5890545

One Way 31657 4504220 140 30680 322 4340280


(B) LCV
Return 7833 548310 70 7427 0 519890

One Way 14301 4172230 290 14642 73 4267350


(C) Bus
Return 7767 1126215 145 7825 0 1134625

One Way 89592 26031270 290 87267 170 25356730


(D) Truck
Return 5874 851730 145 5153 0 747185

One Way 181699 82745845 455 172233 130 78425165


(E) Multi-axle
Truck
Return 6121 1407830 230 6036 0 1388280

(F) Oversized One Way 127 71040 555 105 0 58275


vehicle
Return 43 12040 280 36 0 10080

Total 0 0 842972 159707060 798461 15006 151928100

MONTHLY PROGRESS REPORT JANUARY -2023. 49


M/s L.N. Malviya Infra Projects Pvt Ltd
INDEPENDENT ENGINEER SERVICES DURING
OPERATION & MAINTENANCE PERIOD OF 5 YEARS FOR “SIX LANINGOF DELHI-AGRA SECTION FROM KM.
20.500 TO KM. 200 IN THE STATE OF HARYANA AND U.P ON DBFOT BASIS.

Mahuvan Toll Plaza

SCHEDULE- M
MONTHLY FEE STATEMENT
Project Highways :-Delhi Agra Toll Road Pvt. Ltd. NH-2
Month :-January 2023
Fee Plaza Name ( Chainage) :- Mahuvan Toll Plaza Mathura at CH- 164.500 KM

For the Corresponding Month of For Proceeding Month


For the Month reported upon (December 2022)
Previous year (December 2021) (November 2022)
Types of
Travel Type
Vehicles Fee Per No. of Vehicles
Fee collected No. of Fee collected Double Traffic Fee collected
No. of Vehicles Vehicles (in (including ETC
( In Rs.) Vehicles ( In Rs.) Payment ( In Rs.)
Rs.) Traffic)

1 2 3 4 5 6 7 8 9 10

One Way 185044 21731710 256828 25465985 95 234863 9395 23204510


(A) Car
Return 78744 4330920 108008 4860360 45 100845 4538025

One Way 29884 5470380 32448 4941150 150 30754 237 4648650
(B) LCV
Return 6816 613440 7256 580480 80 6611 528880

One Way 13059 4959375 16560 5365440 320 16275 33 5218560


(C) Bus
Return 7944 1509360 9750 1511250 155 9572 1483660

One Way 83417 31342125 93064 29809280 320 91762 76 29388160


(D) Truck
Return 7560 1436400 8587 1330985 155 8004 1240620

(E) Multi-axle One Way 175240 103489540 191415 95757500 500 181934 90 91012000
Truck
Return 9235 2724325 12365 3091250 250 10619 2654750

(F) Oversized One Way 66 48620 66 39930 605 55 0 33275


vehicle
Return 1 360 0 0 305 0 0

Total 597010 177656555 736347 172753610 691294 9831 163951090

MONTHLY PROGRESS REPORT JANUARY -2023. 50


M/s L.N. Malviya Infra Projects Pvt Ltd
INDEPENDENT ENGINEER SERVICES DURING
OPERATION & MAINTENANCE PERIOD OF 5 YEARS FOR “SIX LANINGOF DELHI-AGRA SECTION FROM KM.
20.500 TO KM. 200 IN THE STATE OF HARYANA AND U.P ON DBFOT BASIS.

Gadpuri, Karman & Mahuvan Toll Plaza

SCHEDULE- M
MONTHLY FEE STATEMENT
Project Highways :-Delhi Agra Toll Road Pvt. Ltd. NH-2
Month :-Jan - 2023
For the Corresponding Month
For Proceeding Month For the Month reported up on
of Previous year (December
(Decemberr 2022) (Jan-2023)
Types of 2021)
Travel Type
Vehicles No. of Vehicles
No. of Fee collected No. of Fee collected Fee collected
(including ETC
Vehicles ( In Rs.) Vehicles ( In Rs.) ( In Rs.)
Traffic)
1 2 3 4 5 6 8 10

One Way 101262410 95311975


995001 938151
(A) Car
Return 21422410 20818785
434220 420659
One Way 15274620 14643005
96289 92944
(B) LCV
Return 2585605 2500825
32228 31121
One Way 14190655 14229775
43852 44193
(C) Bus
Return 4593885 4653005
28386 28701
One Way 72507090 71029450
229241 224640
(D) Truck
Return 4849775 4624445
29278 27805

(E) Multi-axle One Way 221782340 211527515


452190 431181
Truck
Return 10184155 9342830
39159 35927

(F) Oversized One Way 252055 151320


393 246
vehicle
Return 65515 30090
198 94
Total 0 0 2380435 468970515 2275662 448863020

MONTHLY PROGRESS REPORT JANUARY -2023. 51


M/s L.N. Malviya Infra Projects Pvt Ltd
INDEPENDENT ENGINEER SERVICES DURING
OPERATION & MAINTENANCE PERIOD OF 5 YEARS FOR “SIX LANINGOF DELHI-AGRA SECTION FROM KM.
20.500 TO KM. 200 IN THE STATE OF HARYANA AND U.P ON DBFOT BASIS.

SCHEDULE-V
[Referance clause 23 (D) of Appendix- IV]
Monthly User Fee Collection Statement -Part- A
Project Highways :-Delhi Agra Toll Road Pvt. Ltd. NH-2
Fee Plaza Name ( Chainage) :-Gadpuri Toll Plaza CH- 46 KM Month- Jan-23

Types of Vehicles Amount of user fee User Fee collected


Total Amount Collected Total Amount Deposited
Sr.N as per collected through tickets through Passess
Remarks
o. notification
provisions For the For the For the For the
Cummulative Cummulative Cummulative Cummulative
Month Month Month Month
2 Car 52707985 52707985 3531665 3531665 56239650 56239650 56239650 56239650
4 LCV 7106130 59814115 332790 3864455 7438920 63678570 7438920 63678570
5 Bus 6778585 66592700 450870 4315325 7229455 70908025 7229455 70908025
6 Truck 18921200 85513900 0 4315325 18921200 89829225 18921200 89829225
Multi-axle
7 47390150 132904050 0 4315325 47390150 137219375 47390150 137219375
Truck
Oversized
8 79780 132983830 0 4315325 79780 137299155 79780 137299155
vehicle
Total 132983830 132983830 4315325 4315325 137299155 137299155 137299155 137299155

MONTHLY PROGRESS REPORT JANUARY -2023. 52


M/s L.N. Malviya Infra Projects Pvt Ltd
INDEPENDENT ENGINEER SERVICES DURING
OPERATION & MAINTENANCE PERIOD OF 5 YEARS FOR “SIX LANINGOF DELHI-AGRA SECTION FROM KM.
20.500 TO KM. 200 IN THE STATE OF HARYANA AND U.P ON DBFOT BASIS.

SCHEDULE-V
[Referance clause 23 (D) of Appendix- IV]
Monthly User Fee Collection Statement -Part- B
Fee Plaza Name ( Chainage) :-Gadpuri Toll Plaza CH- 46 KM
Monthly Vehicle Passing Report
For the Month of :- Jan-23
Oversized
LCV, LGV, Mini Bus Truck (2 Multi-axle
No. Of Monthly Passes Car, Jeep, Van Bus vehicle (More Total
School Bus Axle) Truck ( More than 3 axle)
than 7 Axles)
No. of Passes 16897 49 38 0 0 0 16984
Revenue ( In Rs.) 3531665 332790 450870 4315325
Oversized
Truck (2 Multi-axle
Types of Vehicles as per Car, Jeep, Van LCV, LGV, Mini Bus Bus vehicle (More Total
Axle) Truck ( More than 3 axle)
notification than 7 Axles)
Nos Nos Nos Nos Nos Nos Nos
All types of singles entry
(Excluding commercial
Multiple Entry
Reusage of multiple
entry ticket
Reusage of monthly
passes
Single entry of
commercial vehicles
Exempted etc.
Grant Total

MONTHLY PROGRESS REPORT JANUARY -2023. 53


M/s L.N. Malviya Infra Projects Pvt Ltd
INDEPENDENT ENGINEER SERVICES DURING
OPERATION & MAINTENANCE PERIOD OF 5 YEARS FOR “SIX LANINGOF DELHI-AGRA SECTION FROM KM.
20.500 TO KM. 200 IN THE STATE OF HARYANA AND U.P ON DBFOT BASIS.

SCHEDULE-V
[Referance clause 23 (D) of Appendix- IV]
Monthly User Fee Collection Statement -Part- A
Project Highways :-Delhi Agra Toll Road Pvt. Ltd. NH-2
Fee Plaza Name ( Chainage) :-Karman Fee Plaza, Palwal at CH- 94.00 KM
Month- January 2023
Amount of user fee collected User Fee collected through
Types of Vehicles as Total Amount Collected Total Amount Deposited
through tickets Passess
Sr.No. per notification Remarks
provisions For the For the
For the Month Cummulative For the Month Cummulative Cummulative Cummulative
Month Month

2 Car 35680240 35680240 511470 511470 36191710 36191710 36191710 36191710

4 LCV 4860170 40540410 58395 569865 4918565 41110275 4918565 41110275

5 Bus 5401975 45942385 0 569865 5401975 46512250 5401975 46512250

6 Truck 26103915 72046300 0 569865 26103915 72616165 26103915 72616165

Multi-axle
7 79813445 151859745 258825 828690 80072270 152688435 80072270 152688435
Truck
Oversized
8 68355 151928100 0 828690 68355 152756790 68355 152756790
vehicle

Total 151928100 151928100 828690 828690 152756790 152756790 152756790 152756790

MONTHLY PROGRESS REPORT JANUARY -2023. 54


M/s L.N. Malviya Infra Projects Pvt Ltd
INDEPENDENT ENGINEER SERVICES DURING
OPERATION & MAINTENANCE PERIOD OF 5 YEARS FOR “SIX LANINGOF DELHI-AGRA SECTION FROM KM.
20.500 TO KM. 200 IN THE STATE OF HARYANA AND U.P ON DBFOT BASIS.

SCHEDULE-V
[Referance clause 23 (D) of Appendix- IV]
Monthly User Fee Collection Statement -Part- B
Fee Plaza Name ( Chainage) :-Karman Fee Plaza, Palwal at CH- 94.00 KM
Monthly Vehicle Passing Report
For the Month of :- January - 2023

Multi-axle Oversized
LCV, LGV, Mini
No. Of Monthly Passes Car, Jeep, Van Bus Truck (2 Axle) Truck ( More vehicle (More Total
Bus
than 3 axle) than 7 Axles)

No. of Passes 1586 15 0 0 17 0 1618

Revenue ( In Rs.) 511470 58395 0 0 258825 0 828690

Multi-axle Oversized
LCV, LGV, Mini
Car, Jeep, Van Bus Truck (2 Axle) Truck ( More vehicle (More Total
Types of Vehicles as per notification Bus
than 3 axle) than 7 Axles)

Nos Nos Nos Nos Nos Nos Nos

All types of singles entry (Excluding


commercial vehicles ragisterd in the
district where the fee plaza falls)

Multiple Entry

Reusage of multiple entry ticket

Reusage of monthly passes


Single entry of commercial vehicles
(Excluding vehicles playing under
national permit registered in the
district where the fee plaza falls.
Exempted etc.

Grant Total

MONTHLY PROGRESS REPORT JANUARY -2023. 55


M/s L.N. Malviya Infra Projects Pvt Ltd
INDEPENDENT ENGINEER SERVICES DURING
OPERATION & MAINTENANCE PERIOD OF 5 YEARS FOR “SIX LANINGOF DELHI-AGRA SECTION FROM KM.
20.500 TO KM. 200 IN THE STATE OF HARYANA AND U.P ON DBFOT BASIS.

SCHEDULE-V
[Referance clause 23 (D) of Appendix- IV]
Monthly User Fee Collection Statement -Part- A
Project Highways :-Delhi Agra Toll Road Pvt. Ltd. NH-2
Fee Plaza Name ( Chainage) :-Mahuvan Toll Plaza Mathura at CH- 164.500 KM
Month :-January 2023
Amount of user fee collected User Fee collected through
Types of Vehicles as Total Amount Collected Total Amount Deposited
through tickets Passess
Sr.No. per notification Remarks
provisions For the For the
For the Month Cummulative For the Month Cummulative Cummulative Cummulative
Month Month

2 Car 27742535 27742535 641035 641035 28383570 28383570 28383570 28383570

4 LCV 5177530 32920065 0 641035 5177530 33561100 5177530 33561100

5 Bus 6702220 39622285 0 641035 6702220 40263320 6702220 40263320

6 Truck 30628780 70251065 0 641035 30628780 70892100 30628780 70892100

Multi-axle
7 93666750 163917815 0 641035 93666750 164558850 93666750 164558850
Truck
Oversized
8 33275 163951090 0 641035 33275 164592125 33275 164592125
vehicle

Total 163951090 163951090 641035 641035 164592125 164592125 164592125 164592125

MONTHLY PROGRESS REPORT JANUARY -2023. 56


M/s L.N. Malviya Infra Projects Pvt Ltd
INDEPENDENT ENGINEER SERVICES DURING
OPERATION & MAINTENANCE PERIOD OF 5 YEARS FOR “SIX LANINGOF DELHI-AGRA SECTION FROM KM.
20.500 TO KM. 200 IN THE STATE OF HARYANA AND U.P ON DBFOT BASIS.

SCHEDULE-V
[Referance clause 23 (D) of Appendix- IV]
Monthly User Fee Collection Statement -Part- B
Fee Plaza Name ( Chainage) :-Mahuvan Toll Plaza Mathura at CH- 164.500 KM
Monthly Vehicle Passing Report
For the Month of :- January 2023

Multi-axle Oversized
LCV, LGV, Mini
No. Of Monthly Passes Car, Jeep, Van Bus Truck (2 Axle) Truck ( More vehicle (More Total
Bus
than 3 axle) than 7 Axles)

No. of Passes 1800 0 0 0 0 0 1800

Revenue ( In Rs.) 641035 0 0 0 0 0 641035

Multi-axle Oversized
LCV, LGV, Mini
Car, Jeep, Van Bus Truck (2 Axle) Truck ( More vehicle (More Total
Types of Vehicles as per notification Bus
than 3 axle) than 7 Axles)

Nos Nos Nos Nos Nos Nos Nos


All types of singles entry (Excluding
commercial vehicles ragisterd in the
district where the fee plaza falls)

Multiple Entry

Reusage of multiple entry ticket

Reusage of monthly passes


Single entry of commercial vehicles
(Excluding vehicles playing under
national permit registered in the
district where the fee plaza falls.
Exempted etc.

Grant Total

MONTHLY PROGRESS REPORT JANUARY -2023. 57


M/s L.N. Malviya Infra Projects Pvt Ltd
INDEPENDENT ENGINEER SERVICES DURING
OPERATION & MAINTENANCE PERIOD OF 5 YEARS FOR “SIX LANINGOF DELHI-AGRA SECTION FROM KM.
20.500 TO KM. 200 IN THE STATE OF HARYANA AND U.P ON DBFOT BASIS.

MONTHLY TRAFFIC CENSUS


GADPURI TOLL PLAZA
SCHEDULE-N
WEEKLY TRAFFIC CENSUS - Jan-2023
Project Highways :-Delhi Agra Toll Road Pvt. Ltd. NH-2
Fee Plaza Name ( Chainage) :-Gadpuri Toll Plaza,Palwal at CH- 46 KM Week Ending :-01-07 Jan"23
No of Vehicles using the Project Highway during
Shift Type of Vehicle Corresponding Week/Last Preceding Week
Week of Report Jan " 2023
Year. June'2021 Dec"- 2022
A Fee Paying Traffic
A1 CAR 0 149406 120824
A2 LCV 0 12274 13976
A3 BUS 0 5255 5295
A4 TRUCK 0 14456 13836
A5 MAV 0 23648 22124
A6 OSV 0 92 20
TOTAL (A) 0 205131 176075
B Local Users (Monthly Pass)
B1 CAR 0 74187 71354
B2 LCV 0 485 498
B3 BUS 0 429 427
B4 TRUCK 0 36 43
B5 MAV 0 62 55
B6 OSV 0 0 0
TOTAL (B) 0 75199 72377
C Exempted Vehicles
C1 Auto 0 28 19
C2 Tractor 0 3805 3293
C3 CAR 0 25655 22556
C4 LCV 0 114 106
C5 BUS 0 29 40
C6 TRUCK 0 158 170
C7 MAV 0 152 94
C8 OSV 0 1 0
TOTAL (C) 0 29942 22966
D Violations
D1 CAR 0 0 0
D2 LCV 0 0 0
D3 BUS 0 0 0
D4 TRUCK 0 0 0
D5 MAV 0 0 0
D6 OSV 0 0 0
TOTAL (D) 0 0 0
E Total Traffic (A+B+C+D+F)
E1 Auto 0 28 19
E2 Tractor 0 3805 3293
E3 CAR 0 249248 214734
E4 LCV 0 12873 14580
E5 BUS 0 5713 5762
E6 TRUCK 0 14650 14049
E7 MAV 0 23862 22273
E8 OSV 0 93 20
0
GRAND TOTAL 0 310272 274730

MONTHLY PROGRESS REPORT JANUARY -2023. 58


M/s L.N. Malviya Infra Projects Pvt Ltd
INDEPENDENT ENGINEER SERVICES DURING
OPERATION & MAINTENANCE PERIOD OF 5 YEARS FOR “SIX LANINGOF DELHI-AGRA SECTION FROM KM.
20.500 TO KM. 200 IN THE STATE OF HARYANA AND U.P ON DBFOT BASIS.

SCHEDULE-N
WEEKLY TRAFFIC CENSUS - Jan-2023
Project Highways :-Delhi Agra Toll Road Pvt. Ltd. NH-2

Fee Plaza Name ( Chainage) :-Gadpuri Toll Plaza,Palwal at CH- 46 KM Week Ending :-08-14 Jan"23
No of Vehicles using the Project Highway during
Shift Type of Vehicle Corresponding Week/Last Preceding Week
Week of Report Jan " 2023
Year. June'2021 Dec"- 2022
A Fee Paying Traffic
A1 CAR 0 134671 115688
A2 LCV 0 12235 14135
A3 BUS 0 5721 5547
A4 TRUCK 0 14504 14583
A5 MAV 0 22761 22678
A6 OSV 0 94 25
TOTAL (A) 0 189986 172656
B Local Users (Monthly Pass)
B1 CAR 0 78347 77076
B2 LCV 0 511 500
B3 BUS 0 511 413
B4 TRUCK 0 35 52
B5 MAV 0 48 85
B6 OSV 0 0 0
TOTAL (B) 0 79452 78126
C Exempted Vehicles
C1 Auto 0 19 24
C2 Tractor 0 3893 4277
C3 CAR 0 23736 23417
C4 LCV 0 111 120
C5 BUS 0 38 19
C6 TRUCK 0 200 164
C7 MAV 0 164 65
C8 OSV 0 1 0
TOTAL (C) 0 28162 0
D Violations
D1 CAR 0 0 0
D2 LCV 0 0 0
D3 BUS 0 0 0
D4 TRUCK 0 0 0
D5 MAV 0 0 0
D6 OSV 0 0 0
TOTAL (D) 0 0 0
E Total Traffic (A+B+C+D)
E1 Auto 0 19 24
E2 Tractor 0 3893 4277
E3 CAR 0 236754 216181
E4 LCV 0 12857 14755
E5 BUS 0 6270 5979
E6 TRUCK 0 14739 14799
E7 MAV 0 22973 22828
E8 OSV 0 95 25
GRAND TOTAL 0 297600 278868

MONTHLY PROGRESS REPORT JANUARY -2023. 59


M/s L.N. Malviya Infra Projects Pvt Ltd
INDEPENDENT ENGINEER SERVICES DURING
OPERATION & MAINTENANCE PERIOD OF 5 YEARS FOR “SIX LANINGOF DELHI-AGRA SECTION FROM KM.
20.500 TO KM. 200 IN THE STATE OF HARYANA AND U.P ON DBFOT BASIS.

SCHEDULE-N
WEEKLY TRAFFIC CENSUS - Jan-2023
Project Highways :-Delhi Agra Toll Road Pvt. Ltd. NH-2

Fee Plaza Name ( Chainage) :-Gadpuri Toll Plaza,Palwal at CH- 46 KM Week Ending :-15-21 Jan"23

No of Vehicles using the Project Highway during


Shift Type of Vehicle
Corresponding Week/Last Preceding Week
Week of Report Jan" 2023
Year. June'2021 Dec"- 2022
A Fee Paying Traffic
A1 CAR 0 115161 120492
A2 LCV 0 12197 13495
A3 BUS 0 5600 5886
A4 TRUCK 0 14148 15073
A5 MAV 0 22193 23236
A6 OSV 0 83 26
TOTAL (A) 0 169382 178208
B Local Users (Monthly Pass)
B1 CAR 0 75787 82281
B2 LCV 0 646 595
B3 BUS 0 550 458
B4 TRUCK 0 27 44
B5 MAV 0 56 75
B6 HCM/EME 0 0 0
TOTAL (B) 0 77066 83453
C Exempted Vehicles
C1 Auto 0 18 20
C2 Tractor 0 3911 4349
C3 CAR 0 20579 24624
C4 LCV 0 144 84
C5 BUS 0 38 13
C6 TRUCK 0 219 167
C7 MAV 0 139 46
C8 OSV 0 6 0
TOTAL (C) 0 25054 29303
D Violations
D1 CAR 0 0 0
D2 LCV 0 0 0
D3 BUS 0 0 0
D4 TRUCK 0 0 0
D5 MAV 0 0 0
D6 OSV 0 0 0
TOTAL (D) 0 0 0
E Total Traffic (A+B+C+D)
E1 Auto 0 18 20
E2 Tractor 0 3911 4349
E3 CAR 0 211527 227397
E4 LCV 0 12987 14174
E5 BUS 0 6188 6357
E6 TRUCK 0 14394 15284
E7 MAV 0 22388 23357
E8 OSV 0 89 26
GRAND TOTAL 0 271502 290964

MONTHLY PROGRESS REPORT JANUARY -2023. 60


M/s L.N. Malviya Infra Projects Pvt Ltd
INDEPENDENT ENGINEER SERVICES DURING
OPERATION & MAINTENANCE PERIOD OF 5 YEARS FOR “SIX LANINGOF DELHI-AGRA SECTION FROM KM.
20.500 TO KM. 200 IN THE STATE OF HARYANA AND U.P ON DBFOT BASIS.

SCHEDULE-N
WEEKLY TRAFFIC CENSUS - Jan-2023
Project Highways :-Delhi Agra Toll Road Pvt. Ltd. NH-2

Fee Plaza Name ( Chainage) :-Gadpuri Toll Plaza,Palwal at CH- 46 KM Week Ending :-22-28 Jan" 23

No of Vehicles using the Project Highway during


Shift Type of Vehicle
Corresponding Week/Last Preceding Week
Week of Report Jan" 2023
Year. June'2021 Dec"- 2022
A Fee Paying Traffic
A1 CAR 0 112989 135061
A2 LCV 0 12609 12962
A3 BUS 0 5504 5893
A4 TRUCK 0 13798 14153
A5 MAV 0 22339 21513
A6 OSV 0 59 29
TOTAL (A) 0 167298 189611
B Local Users (Monthly Pass)
B1 CAR 0 73744 78850
B2 LCV 0 529 480
B3 BUS 0 478 419
B4 TRUCK 0 27 39
B5 MAV 0 47 61
B6 OSV 0 0 0
TOTAL (B) 0 74,825 79,849
C Exempted Vehicles
C1 Auto 0 30 24
C2 Tractor 0 3582 3947
C3 CAR 0 21691 25430
C4 LCV 0 104 80
C5 BUS 0 30 18
C6 TRUCK 0 214 158
C7 MAV 0 144 52
C8 OSV 0 0 0
TOTAL (C) 0 25795 29709
D Violations
D1 CAR 0 0 0
D2 LCV 0 0 0
D3 BUS 0 0 0
D4 TRUCK 0 0 0
D5 MAV 0 0 0
D6 OSV 0 0 0
TOTAL (D) 0 0 0
E Total Traffic (A+B+C+D)
E1 Auto 0 30 24
E2 Tractor 0 3582 3947
E3 CAR 0 208424 239341
E4 LCV 0 13242 13522
E5 BUS 0 6012 6330
E6 TRUCK 0 14039 14350
E7 MAV 0 22530 21626
E8 OSV 0 59 29
GRAND TOTAL 0 267918 299169

MONTHLY PROGRESS REPORT JANUARY -2023. 61


M/s L.N. Malviya Infra Projects Pvt Ltd
INDEPENDENT ENGINEER SERVICES DURING
OPERATION & MAINTENANCE PERIOD OF 5 YEARS FOR “SIX LANINGOF DELHI-AGRA SECTION FROM KM.
20.500 TO KM. 200 IN THE STATE OF HARYANA AND U.P ON DBFOT BASIS.

SCHEDULE-N
WEEKLY TRAFFIC CENSUS - Jan-2023
Project Highways :-Delhi Agra Toll Road Pvt. Ltd. NH-2

Fee Plaza Name ( Chainage) :-Gadpuri Toll Plaza,Palwal at CH- 46 KM Week Ending :-29-31 Jan" 23

No of Vehicles using the Project Highway during


Shift Type of Vehicle Corresponding Week/Last Preceding Week
Week of Report Jan" 2023
Year. June'2021 Dec"- 2022
A Fee Paying Traffic
A1 CAR 0 50595 56757
A2 LCV 0 6689 5655
A3 BUS 0 2179 2523
A4 TRUCK 0 6171 6181
A5 MAV 0 10244 10093
A6 OSV 0 21 7
TOTAL (A) 0 75899 81216
B Local Users (Monthly Pass)
B1 CAR 0 31955 34253
B2 LCV 0 235 213
B3 BUS 0 206 165
B4 TRUCK 0 17 14
B5 MAV 0 24 16
B6 OSV 0 0 0
TOTAL (B) 0 32437 34661
C Exempted Vehicles
C1 Auto 0 11 10
C2 Tractor 0 1516 1598
C3 CAR 0 9738 10808
C4 LCV 0 51 37
C5 BUS 0 6 14
C6 TRUCK 0 77 74
C7 MAV 0 119 28
C8 OSV 0 3 0
TOTAL (C) 0 11521 0
D Violations
D1 CAR 0 0 0
D2 LCV 0 0 0
D3 BUS 0 0 0
D4 TRUCK 0 0 0
D5 MAV 0 0 0
D6 OSV 0 0 0
TOTAL (D) 0 0 0
E Total Traffic (A+B+C+D)
E1 Auto 0 11 10
E2 Tractor 0 1516 1598
E3 CAR 0 92288 101818
E4 LCV 0 6975 5905
E5 BUS 0 2391 2702
E6 TRUCK 0 6265 6269
E7 MAV 0 10387 10137
E8 OSV 0 24 7
GRAND TOTAL 0 119857 128446

MONTHLY PROGRESS REPORT JANUARY -2023. 62


M/s L.N. Malviya Infra Projects Pvt Ltd
INDEPENDENT ENGINEER SERVICES DURING
OPERATION & MAINTENANCE PERIOD OF 5 YEARS FOR “SIX LANINGOF DELHI-AGRA SECTION FROM KM.
20.500 TO KM. 200 IN THE STATE OF HARYANA AND U.P ON DBFOT BASIS.

KARMAN TOLL PLAZA


SCHEDULE-N
WEEKLY TRAFFIC CENSUS - January 2023
Project Highways :-Delhi Agra Toll Road Pvt. Ltd. NH-2
Fee Plaza Name ( Chainage) :-Karman Fee Plaza, Palwal at CH- 94.000 KM Week Ending :- 01-07
No of Vehicles using the Project Highway during
Corresponding
Shift Type of Vehicle Preceding Week Week of Report
Week/Last Year
December 2022 January-2023
January 2022
A Fee Paying Traffic
A1 CAR 0 123699 109178
A2 LCV 0 8995 8545
A3 BUS 0 4340 4894
A4 TRUCK 0 21568 19910
A5 MAV 0 44326 38734
A6 OSV 0 49 34
TOTAL (A) 0 202977 181295
B Local Users (Monthly Pass)
B1 CAR 0 8141 6529
B2 LCV 0 173 115
B3 BUS 0 0 0
B4 TRUCK 0 2 2
B5 MAV 0 89 272
B6 OSV 0 0 0
TOTAL (B) 0 8405 6918
C Return Journey Reuse
C1 CAR 0 0 0
C2 LCV 0 0 0
C3 BUS 0 0 0
C4 TRUCK 0 0 0
C5 MAV 0 0 0
C6 OSV 0 0 0
TOTAL (C) 0 0 0
D Exempt Vehicles
D1 CAR 0 11126 10154
D2 LCV 0 124 197
D3 BUS 0 34 38
D4 TRUCK 0 279 328
D5 MAV 0 321 297
D6 OSV 0 0 0
D7 Auto 0 1475 892
D8 Tractor 0 1003 461
TOTAL (D) 0 14362 12367
E Total Traffic (A+B+C+D)
E1 CAR 0 142966 125861
E2 LCV 0 9292 8857
E3 BUS 0 4374 4932
E4 TRUCK 0 21849 20240
E5 MAV 0 44736 39303
E6 OSV 0 49 34
E7 Auto 0 1475 892
E8 Tractor 0 1003 461
GRAND TOTAL 0 225744 200580

MONTHLY PROGRESS REPORT JANUARY -2023. 63


M/s L.N. Malviya Infra Projects Pvt Ltd
INDEPENDENT ENGINEER SERVICES DURING
OPERATION & MAINTENANCE PERIOD OF 5 YEARS FOR “SIX LANINGOF DELHI-AGRA SECTION FROM KM.
20.500 TO KM. 200 IN THE STATE OF HARYANA AND U.P ON DBFOT BASIS.

SCHEDULE-N
WEEKLY TRAFFIC CENSUS - January 2023
Project Highways :-Delhi Agra Toll Road Pvt. Ltd. NH-2

Fee Plaza Name ( Chainage) :-Karman Fee Plaza, Palwal at CH- 94.000 KM Week Ending :- 08-14

No of Vehicles using the Project Highway during


Corresponding
Shift Type of Vehicle Preceding Week Week of Report
Week/Last Year
December 2022 January-2023
January 2022
A Fee Paying Traffic
A1 CAR 0 115404 90369
A2 LCV 0 8694 8579
A3 BUS 0 5026 4977
A4 TRUCK 0 21807 21084
A5 MAV 0 42806 41680
A6 OSV 0 37 27
TOTAL (A) 0 193774 166716
B Local Users (Monthly Pass)
B1 CAR 0 8289 7211
B2 LCV 0 170 95
B3 BUS 0 0 0
B4 TRUCK 0 2 0
B5 MAV 0 126 281
B6 OSV 0 0 0
TOTAL (B) 0 8587 7587
C Return Journey Reuse
C1 CAR 0 0 0
C2 LCV 0 0 0
C3 BUS 0 0 0
C4 TRUCK 0 0 0
C5 MAV 0 0 0
C6 OSV 0 0 0
TOTAL (C) 0 0 0
D Exempt Vehicles
D1 CAR 0 10544 8906
D2 LCV 0 112 138
D3 BUS 0 36 14
D4 TRUCK 0 280 309
D5 MAV 0 297 323
D6 OSV 0 3 0
D7 Auto 0 1278 785
D8 Tractor 0 796 611
TOTAL (D) 0 13346 11086
E Total Traffic (A+B+C+D)
E1 CAR 0 134237 106486
E2 LCV 0 8976 8812
E3 BUS 0 5062 4991
E4 TRUCK 0 22089 21393
E5 MAV 0 43229 42284
E6 OSV 0 40 27
E7 Auto 0 1278 785
E8 Tractor 0 796 611
GRAND TOTAL 0 215707 185389

MONTHLY PROGRESS REPORT JANUARY -2023. 64


M/s L.N. Malviya Infra Projects Pvt Ltd
INDEPENDENT ENGINEER SERVICES DURING
OPERATION & MAINTENANCE PERIOD OF 5 YEARS FOR “SIX LANINGOF DELHI-AGRA SECTION FROM KM.
20.500 TO KM. 200 IN THE STATE OF HARYANA AND U.P ON DBFOT BASIS.

SCHEDULE-N
WEEKLY TRAFFIC CENSUS - January 2023
Project Highways :-Delhi Agra Toll Road Pvt. Ltd. NH-2

Fee Plaza Name ( Chainage) :-Karman Fee Plaza, Palwal at CH- 94.000 KM Week Ending :- 15-21

No of Vehicles using the Project Highway during


Shift Type of Vehicle Corresponding
Preceding Week Week of Report
Week/Last Year
December 2022 January-2023
January 2022
A Fee Paying Traffic
A1 CAR 0 104449 102176
A2 LCV 0 8839 8503
A3 BUS 0 5374 5093
A4 TRUCK 0 21710 21400
A5 MAV 0 42272 40792
A6 OSV 0 33 35
TOTAL (A) 0 182677 177999
B Local Users (Monthly Pass)
B1 CAR 0 7434 8103
B2 LCV 0 181 160
B3 BUS 0 0 0
B4 TRUCK 0 2 2
B5 MAV 0 196 365
B6 OSV 0 0 0
TOTAL (B) 0 7813 8630
C Return Journey Reuse
C1 CAR 0 0 0
C2 LCV 0 0 0
C3 BUS 0 0 0
C4 TRUCK 0 0 0
C5 MAV 0 0 0
C6 OSV 0 0 0
TOTAL (C) 0 0 0
D Exempt Vehicles
D1 CAR 0 9570 9971
D2 LCV 0 147 123
D3 BUS 0 42 11
D4 TRUCK 0 336 226
D5 MAV 0 300 299
D6 OSV 0 2 0
D7 Auto 0 798 769
D8 Tractor 0 1,150 706
TOTAL (D) 0 12345 12105
E Total Traffic (A+B+C+D)
E1 CAR 0 121453 120250
E2 LCV 0 9167 8786
E3 BUS 0 5416 5104
E4 TRUCK 0 22048 21628
E5 MAV 0 42768 41456
E6 OSV 0 35 35
E7 Auto 0 798 769
E8 Tractor 0 1150 706
GRAND TOTAL 0 202835 198734

MONTHLY PROGRESS REPORT JANUARY -2023. 65


M/s L.N. Malviya Infra Projects Pvt Ltd
INDEPENDENT ENGINEER SERVICES DURING
OPERATION & MAINTENANCE PERIOD OF 5 YEARS FOR “SIX LANINGOF DELHI-AGRA SECTION FROM KM.
20.500 TO KM. 200 IN THE STATE OF HARYANA AND U.P ON DBFOT BASIS.

SCHEDULE-N
WEEKLY TRAFFIC CENSUS - January 2023
Project Highways :-Delhi Agra Toll Road Pvt. Ltd. NH-2

Fee Plaza Name ( Chainage) :-Karman Fee Plaza, Palwal at CH- 94.000 KM Week Ending :- 22-28

No of Vehicles using the Project Highway during


Corresponding
Shift Type of Vehicle Preceding Week Week of Report
Week/Last Year
December 2022 January-2023
January 2022
A Fee Paying Traffic
A1 CAR 0 103475 117662
A2 LCV 0 8876 8677
A3 BUS 0 5230 5302
A4 TRUCK 0 21109 20962
A5 MAV 0 40748 39691
A6 OSV 0 35 33
TOTAL (A) 0 179473 192327
B Local Users (Monthly Pass)
B1 CAR 0 7162 8217
B2 LCV 0 181 149
B3 BUS 0 0 0
B4 TRUCK 0 0 0
B5 MAV 0 235 191
B6 OSV 0 0 0
TOTAL (B) 0 7578 8557
C Return Journey Reuse
C1 CAR 0 0 0
C2 LCV 0 0 0
C3 BUS 0 0 0
C4 TRUCK 0 0 0
C5 MAV 0 0 0
C6 OSV 0 0 0
TOTAL (C) 0 0 0
D Exempt Vehicles
D1 CAR 0 9526 10714
D2 LCV 0 144 135
D3 BUS 0 42 27
D4 TRUCK 0 349 243
D5 MAV 0 488 258
D6 OSV 0 1 0
D7 Auto 0 1178 549
D8 Tractor 0 762 741
TOTAL (D) 0 12490 12667
E Total Traffic (A+B+C+D)
E1 CAR 0 120163 136593
E2 LCV 0 9201 8961
E3 BUS 0 5272 5329
E4 TRUCK 0 21458 21205
E5 MAV 0 41471 40140
E6 OSV 0 36 33
E7 Auto 0 1178 549
E8 Tractor 0 762 741
GRAND TOTAL 0 199541 213551

MONTHLY PROGRESS REPORT JANUARY -2023. 66


M/s L.N. Malviya Infra Projects Pvt Ltd
INDEPENDENT ENGINEER SERVICES DURING
OPERATION & MAINTENANCE PERIOD OF 5 YEARS FOR “SIX LANINGOF DELHI-AGRA SECTION FROM KM.
20.500 TO KM. 200 IN THE STATE OF HARYANA AND U.P ON DBFOT BASIS.

SCHEDULE-N
WEEKLY TRAFFIC CENSUS - January 2023
Project Highways :-Delhi Agra Toll Road Pvt. Ltd. NH-2

Fee Plaza Name ( Chainage) :-Karman Fee Plaza, Palwal at CH- 94.000 KM Week Ending :- 29-31

No of Vehicles using the Project Highway during


Corresponding
Shift Type of Vehicle Preceding Week Week of Report
Week/Last Year
December 2022 January-2023
January 2022
A Fee Paying Traffic
A1 CAR 0 50931 47672
A2 LCV 0 4086 3803
A3 BUS 0 2098 2201
A4 TRUCK 0 9272 9064
A5 MAV 0 17668 17372
A6 OSV 0 16 12
TOTAL (A) 0 84071 80124
B Local Users (Monthly Pass)
B1 CAR 0 2799 3323
B2 LCV 0 75 60
B3 BUS 0 0 0
B4 TRUCK 0 0 0
B5 MAV 0 47 36
B6 OSV 0 0 0
TOTAL (B) 0 2921 3419
C Return Journey Reuse
C1 CAR 0 0 0
C2 LCV 0 0 0
C3 BUS 0 0 0
C4 TRUCK 0 0 0
C5 MAV 0 0 0
C6 OSV 0 0 0
TOTAL (C) 0 0 0
D Exempt Vehicles
D1 CAR 0 4940 4147
D2 LCV 0 72 55
D3 BUS 0 15 8
D4 TRUCK 0 143 110
D5 MAV 0 155 113
D6 OSV 0 0 1
D7 Auto 0 362 219
D8 Tractor 0 342 206
TOTAL (D) 0 6029 4859
E Total Traffic (A+B+C+D)
E1 CAR 0 58670 55142
E2 LCV 0 4233 3918
E3 BUS 0 2113 2209
E4 TRUCK 0 9415 9174
E5 MAV 0 17870 17521
E6 OSV 0 16 13
E7 Auto 0 362 219
E8 Tractor 0 342 206
GRAND TOTAL 0 93021 88402

MONTHLY PROGRESS REPORT JANUARY -2023. 67


M/s L.N. Malviya Infra Projects Pvt Ltd
INDEPENDENT ENGINEER SERVICES DURING
OPERATION & MAINTENANCE PERIOD OF 5 YEARS FOR “SIX LANINGOF DELHI-AGRA SECTION FROM KM.
20.500 TO KM. 200 IN THE STATE OF HARYANA AND U.P ON DBFOT BASIS.

MAHUVAN TOLL PLAZA


SCHEDULE-N
WEEKLY TRAFFIC CENSUS - January 2023
Project Highways :-Delhi Agra Toll Road Pvt. Ltd. NH-2
Week Ending :- 01-07
Fee Plaza Name ( Chainage) :-Mahuvan toll plaza, Mathura at CH- 164.500 KM
January-2023
No of Vehicles using the Project Highway during
Corresponding
Shift Type of Vehicle Preceding Week Week of Report
Week/Last Year
December- 2022 January- 2023
January 2022
A Fee Paying Traffic
A1 CAR 70367 89403 79271
A2 LCV 8543 9216 8370
A3 BUS 4740 5607 5574
A4 TRUCK 19446 22881 21423
A5 MAV 41097 47516 42236
A6 OSV 13 16 17
TOTAL (A) 144206 174639 156891
B Local Users (Monthly Pass)
B1 CAR 7277 8697 7016
B2 LCV 0 15 18
B3 BUS 0 0 0
B4 TRUCK 10 3 26
B5 MAV 8 71 36
B6 OSV 0 0 0
TOTAL (B) 7295 8786 7096
C Return Journey Reuse
C1 CAR 0 0 0
C2 LCV 0 0 0
C3 BUS 0 0 0
C4 TRUCK 0 0 0
C5 MAV 0 0 0
C6 OSV 0 0 0
TOTAL (C) 0 0 0
D Exempt Vehicles
D1 CAR 6716 7268 5728
D2 LCV 470 409 587
D3 BUS 9 23 28
D4 TRUCK 221 270 281
D5 MAV 123 184 157
D6 OSV 0 0 0
D7 Auto 190 197 334
D8 Tractor 1680 1438 888
TOTAL (D) 9409 9789 8003
E Total Traffic (A+B+C+D)
E1 CAR 84360 105368 92015
E2 LCV 9013 9640 8975
E3 BUS 4749 5630 5602
E4 TRUCK 19677 23154 21730
E5 MAV 41228 47771 42429
E6 OSV 13 16 17
E7 Auto 190 197 334
E8 Tractor 1680 1438 888
GRAND TOTAL 160910 193214 171990

MONTHLY PROGRESS REPORT JANUARY -2023. 68


M/s L.N. Malviya Infra Projects Pvt Ltd
INDEPENDENT ENGINEER SERVICES DURING
OPERATION & MAINTENANCE PERIOD OF 5 YEARS FOR “SIX LANINGOF DELHI-AGRA SECTION FROM KM.
20.500 TO KM. 200 IN THE STATE OF HARYANA AND U.P ON DBFOT BASIS.

SCHEDULE-N
WEEKLY TRAFFIC CENSUS - January 2023
Project Highways :-Delhi Agra Toll Road Pvt. Ltd. NH-2
Week Ending :- 08-14
Fee Plaza Name ( Chainage) :-Mahuvan toll plaza, Mathura at CH- 164.500 KM
January-2023
No of Vehicles using the Project Highway during
Corresponding
Shift Type of Vehicle Preceding Week Week of Report
Week/Last Year
December- 2022 January- 2023
January 2022
A Fee Paying Traffic
A1 CAR 52784 83783 67113
A2 LCV 8188 8716 8474
A3 BUS 4789 6020 5645
A4 TRUCK 20837 23303 22789
A5 MAV 41063 46689 45150
A6 OSV 15 15 8
TOTAL (A) 127676 168526 149179
B Local Users (Monthly Pass)
B1 CAR 7076 8772 7080
B2 LCV 0 20 6
B3 BUS 0 0 0
B4 TRUCK 10 39 19
B5 MAV 12 155 2
B6 OSV 0 0 0
TOTAL (B) 7098 8986 7107
C Return Journey Reuse
C1 CAR 0 0 0
C2 LCV 0 0 0
C3 BUS 0 0 0
C4 TRUCK 0 0 0
C5 MAV 0 0 0
C6 OSV 0 0 0
TOTAL (C) 0 0 0
D Exempt Vehicles
D1 CAR 5419 6497 5249
D2 LCV 464 495 609
D3 BUS 8 20 15
D4 TRUCK 208 251 290
D5 MAV 90 218 162
D6 OSV 0 0 1
D7 Auto 183 128 184
D8 Tractor 1419 1441 910
TOTAL (D) 7791 9050 7420
E Total Traffic (A+B+C+D)
E1 CAR 65279 99052 79442
E2 LCV 8652 9231 9089
E3 BUS 4797 6040 5660
E4 TRUCK 21055 23593 23098
E5 MAV 41165 47062 45314
E6 OSV 15 15 9
E7 Auto 183 128 184
E8 Tractor 1419 1441 910
GRAND TOTAL 142565 186562 163706
MONTHLY PROGRESS REPORT JANUARY -2023. 69
M/s L.N. Malviya Infra Projects Pvt Ltd
INDEPENDENT ENGINEER SERVICES DURING
OPERATION & MAINTENANCE PERIOD OF 5 YEARS FOR “SIX LANINGOF DELHI-AGRA SECTION FROM KM.
20.500 TO KM. 200 IN THE STATE OF HARYANA AND U.P ON DBFOT BASIS.

SCHEDULE-N
WEEKLY TRAFFIC CENSUS - January 2023
Project Highways :-Delhi Agra Toll Road Pvt. Ltd. NH-2
Week Ending :- 15-21
Fee Plaza Name ( Chainage) :-Mahuvan toll plaza, Mathura at CH- 164.500 KM
January-2023
No of Vehicles using the Project Highway during
Corresponding
Shift Type of Vehicle Preceding Week Week of Report
Week/Last Year
December- 2022 January- 2023
January 2022
A Fee Paying Traffic
A1 CAR 53534 73896 71713
A2 LCV 8196 8876 8325
A3 BUS 4774 6212 5984
A4 TRUCK 20666 22958 23179
A5 MAV 41537 46040 43852
A6 OSV 15 17 15
TOTAL (A) 128722 157999 153068
B Local Users (Monthly Pass)
B1 CAR 7576 8111 8744
B2 LCV 0 10 8
B3 BUS 0 0 0
B4 TRUCK 13 45 22
B5 MAV 16 173 9
B6 OSV 0 0 0
TOTAL (B) 7605 8339 8783
C Return Journey Reuse
C1 CAR 0 0 0
C2 LCV 0 0 0
C3 BUS 0 0 0
C4 TRUCK 0 0 0
C5 MAV 0 0 0
C6 OSV 0 0 0
TOTAL (C) 0 0 0
D Exempt Vehicles
D1 CAR 5444 5571 5884
D2 LCV 468 516 508
D3 BUS 24 28 20
D4 TRUCK 151 264 198
D5 MAV 83 166 149
D6 OSV 0 0 0
D7 Auto 175 238 211
D8 Tractor 1484 1448 1122
TOTAL (D) 7829 8231 8092
E Total Traffic (A+B+C+D)
E1 CAR 66554 87578 86341
E2 LCV 8664 9402 8841
E3 BUS 4798 6240 6004
E4 TRUCK 20830 23267 23399
E5 MAV 41636 46379 44010
E6 OSV 15 17 15
E7 Auto 175 238 211
E8 Tractor 1484 1448 1122
GRAND TOTAL 144156 174569 169943
MONTHLY PROGRESS REPORT JANUARY -2023. 70
M/s L.N. Malviya Infra Projects Pvt Ltd
INDEPENDENT ENGINEER SERVICES DURING
OPERATION & MAINTENANCE PERIOD OF 5 YEARS FOR “SIX LANINGOF DELHI-AGRA SECTION FROM KM.
20.500 TO KM. 200 IN THE STATE OF HARYANA AND U.P ON DBFOT BASIS.

SCHEDULE-N
WEEKLY TRAFFIC CENSUS - January 2023
Project Highways :-Delhi Agra Toll Road Pvt. Ltd. NH-2
Week Ending :- 22-28
Fee Plaza Name ( Chainage) :-Mahuvan toll plaza, Mathura at CH- 164.500 KM
January-2023
No of Vehicles using the Project Highway during
Corresponding
Shift Type of Vehicle Preceding Week Week of Report
Week/Last Year
December- 2022 January- 2023
January 2022
A Fee Paying Traffic
A1 CAR 59449 81653 82430
A2 LCV 8111 8880 8527
A3 BUS 4725 6050 6162
A4 TRUCK 20418 22471 22517
A5 MAV 41508 44206 42505
A6 OSV 14 14 13
TOTAL (A) 134225 163274 162154
B Local Users (Monthly Pass)
B1 CAR 7829 8057 8450
B2 LCV 6 21 4
B3 BUS 0 0 0
B4 TRUCK 10 39 16
B5 MAV 51 221 2
B6 OSV 0 0 0
TOTAL (B) 7896 8338 8472
C Return Journey Reuse
C1 CAR 0 0 0
C2 LCV 0 0 0
C3 BUS 0 0 0
C4 TRUCK 0 0 0
C5 MAV 0 0 0
C6 OSV 0 0 0
TOTAL (C) 0 0 0
D Exempt Vehicles
D1 CAR 6012 5978 6100
D2 LCV 491 551 411
D3 BUS 17 26 13
D4 TRUCK 192 249 212
D5 MAV 49 151 109
D6 OSV 0 0 0
D7 Auto 470 226 172
D8 Tractor 1260 1188 997
TOTAL (D) 8491 8369 8014
E Total Traffic (A+B+C+D)
E1 CAR 73290 95688 96980
E2 LCV 8608 9452 8942
E3 BUS 4742 6076 6175
E4 TRUCK 20620 22759 22745
E5 MAV 41608 44578 42616
E6 OSV 14 14 13
E7 Auto 470 226 172
E8 Tractor 1260 1188 997
GRAND TOTAL 150612 179981 178640

MONTHLY PROGRESS REPORT JANUARY -2023. 71


M/s L.N. Malviya Infra Projects Pvt Ltd
INDEPENDENT ENGINEER SERVICES DURING
OPERATION & MAINTENANCE PERIOD OF 5 YEARS FOR “SIX LANINGOF DELHI-AGRA SECTION FROM KM.
20.500 TO KM. 200 IN THE STATE OF HARYANA AND U.P ON DBFOT BASIS.

SCHEDULE-N
WEEKLY TRAFFIC CENSUS - January 2023
Project Highways :-Delhi Agra Toll Road Pvt. Ltd. NH-2
Week Ending :- 29-31
Fee Plaza Name ( Chainage) :-Mahuvan toll plaza, Mathura at CH- 164.500 KM
January-2023
No of Vehicles using the Project Highway during
Corresponding
Shift Type of Vehicle Preceding Week Week of Report
Week/Last Year
December- 2022 January- 2023
January 2022
A Fee Paying Traffic
A1 CAR 27654 36102 35181
A2 LCV 3662 4081 3761
A3 BUS 1975 2438 2435
A4 TRUCK 9610 10039 9858
A5 MAV 19270 19329 18810
A6 OSV 10 4 2
TOTAL (A) 62181 71993 70047
B Local Users (Monthly Pass)
B1 CAR 3418 3192 3436
B2 LCV 2 5 9
B3 BUS 0 0 0
B4 TRUCK 10 13 13
B5 MAV 30 65 6
B6 OSV 0 0 0
TOTAL (B) 3460 3275 3464
C Return Journey Reuse
C1 CAR 0 0 0
C2 LCV 0 0 0
C3 BUS 0 0 0
C4 TRUCK 0 0 0
C5 MAV 0 0 0
C6 OSV 0 0 0
TOTAL (C) 0 0 0
D Exempt Vehicles
D1 CAR 2800 2568 2624
D2 LCV 213 257 181
D3 BUS 5 11 6
D4 TRUCK 95 92 91
D5 MAV 54 67 50
D6 OSV 0 0 0
D7 Auto 78 84 94
D8 Tractor 700 551 332
TOTAL (D) 3945 3630 3378
E Total Traffic (A+B+C+D)
E1 CAR 33872 41862 41241
E2 LCV 3877 4343 3951
E3 BUS 1980 2449 2441
E4 TRUCK 9715 10144 9962
E5 MAV 19354 19461 18866
E6 OSV 10 4 2
E7 Auto 78 84 94
E8 Tractor 700 551 332
GRAND TOTAL 69586 78898 76889

MONTHLY PROGRESS REPORT JANUARY -2023. 72


Project : DA Toll Road
Toll Plaza : Srinagar
Stretch : Delhi - Agra
Stretch Chainage : KM 20+500 To 93+800
State : Haryana
District : Fariadabad, Palwal
Police stations : Faridabad, Ballabgarh Sadar Thana, Palwal Sadar Thana Mundkati & Hodal
Month & Year : Jan-23
A B C D E F G H No. of affected persons No of
Help provided by
Time of Accident animals
S. No Date Village Name Classificatio Intersectio Vehicle Responsible Ambulance / Patrolling
(am/pm) Nature of Road Road Weather Non Killed if
33. Accident Report

Accident Location n of Causes n Type and Fatal Grevious Minor Vehicle


Accident Feature Condition Condition Injured any
Accident Control
Classificatio
Nature of Road
n of Causes
Accident Feature
Accident

1 01.01.2023 8:45 PM Near Baghola Prithla 51+170/RHS 8 2 1 3 1 1 1 Bike & Pedistrain 1 1 No Ambulance

2 02.01.2023 8:45 PM Near Softa Village 44+500/RHS 2 2 2 3 1 1 1 Car & Auto 1 No RPV & Hydra

3 04.01.2023 7:28 PM Near Andata Hotel 70+060 RHS 3 3 2 3 1 1 1 Picup & Unknown 1 No RPV

4 05.01.2023 5:50 AM Near Bata Chowk 31+330/LHS 3 1 2 3 1 1 2 Bike & Unknown 1 No Ambulance & RPV

5 05.01.2023 7:50 AM Near Seekri Village 43+470/RHS 1 4 3 3 1 1 2 Picup 1 No RPV & Hydra

MONTHLY PROGRESS REPORT JANUARY -2023.


6 05.01.2023 7:30 PM Near V.P.O Bhulwana 90+500/LHS 3 4 2 3 1 1 1 Truck & Unknown vehicle 1 No RPV2 & Hydra karman

7 06.01.2023 8:05 PM Near Ratan Truck Dhabha 81+840/LHS 2 2 4 3 1 1 2 Bike & Unknown 2 No RPV

8 07.01.2023 21:50 pm Near saria Village 78+300/RHS 1 4 3 3 1 1 1 Picup 1 No RPV2 & Hydra karman

9 09.01.2023 4:05 AM Near hodal 87+570/RHS 1 3 3 3 1 1 2 Truck 1 No RPV & Hydra

10 09.01.2023 6:25 AM Near saria Village 77+030/LHS 3 2 2 3 1 1 2 Auto & LCV 3 1 No Ambulance

11 09.01.2023 8:05 AM Near Banchari Village 83+330/RHS 3 1 2 3 1 1 2 Car & Truck 1 1 No Ambulance
M/s L.N. Malviya Infra Projects Pvt Ltd

ACCIDENT DATA HARYANA

12 09.01.2023 4:05 AM Near Prithla Village 48+200/RHS 3 2 2 3 1 1 2 Bike & Lcv 1 No Ambulance

13 10.01.2023 10:30 PM Near Samrat Hospital Seekri 44+660/LHS 6 3 1 3 1 1 1 Bike 1 No Ambulance

14 12.01.2023 1:10 AM Near Bhagola Village 50+790/RHS 2 2 8 3 2 1 1 Lcv 1 No RPV & Hydra

15 12.01.2023 6:40 AM Near YMCA Collage 32+740/LHS 3 4 2 3 1 1 1 Car & Truck 1 No RPV & Hydra

16 13.01.2023 4:30 AM Near Ballabgarh Bus Stand 36+020/LHS 8 4 3 3 1 1 1 LCV 1 No RPV & Hydra
20.500 TO KM. 200 IN THE STATE OF HARYANA AND U.P ON DBFOT BASIS.

17 13.01.2023 4:00 PM Near Gadpuri Toll Plaza 36+020/LHS 4 3 2 3 1 1 1 Car & Bike 1 No Ambulance

18 13.01.2023 5:28 PM Near Shrinagar Village 75+840/RHS 8 3 3 3 1 1 1 Mini LCV 1 No Ambulance

19 13.01.2023 6:20 PM Near Kushlipur Village 64+060/LHS 2 2 4 3 1 1 1 Mini LCV 1 1 No RPV


INDEPENDENT ENGINEER SERVICES DURING

85+860/LHS

73
20 13.01.2023 2:54 PM Near Hodal 3 3 2 3 1 1 1 Bike & Picup 2 No Ambulance
OPERATION & MAINTENANCE PERIOD OF 5 YEARS FOR “SIX LANINGOF DELHI-AGRA SECTION FROM KM.
M/s L.N. Malviya Infra Projects Pvt Ltd
INDEPENDENT ENGINEER SERVICES DURING
OPERATION & MAINTENANCE PERIOD OF 5 YEARS FOR “SIX LANINGOF DELHI-AGRA SECTION FROM KM.
20.500 TO KM. 200 IN THE STATE OF HARYANA AND U.P ON DBFOT BASIS.

MONTHLY PROGRESS REPORT JANUARY -2023. 74


Stretch : DA Toll Road
Toll Plaza Name : Mahuvan
Stretch Name : Delhi - Agra
Stretch Chainage : Km 93+800 to Km 200+000
State : UP
District : Mathura,Agra
Police Station : Koshi, Chhata, Mathura Refinary, Farah, Runakta,Sikandra, New Agra
Month & Year : Jan-22
A B C D E F G H No of affected persons
No of Help provided by
Sr. No Date Time of Accident Village Name Intersection Vehicle Responsible animals if Ambulance /
Nature of Classification Road Road Non-
Accident Location Causes Type & Weather condition Fatal Grievous Minor any killed patrol vehicle
Accident of Accident Feature condition injured
Control

Bike Reg No. Our Ambulance


HR51AE4316 & Bike
1 01.01.2023 14:19 hrs Brij Ki Rasoi (Farah) 169+030 RHS 4 3 3 3 1 4 1 1 2 Local Public &
Reg
No.UP80DQ3047 Police staff

RPV-03 Local
Car Reg
2 01.01.2023 14:33 hrs Highway Thana 146.440 LHS 8 3 3 3 1 4 1 1 Public & Police
No.UP85AN2671
Staff

Unknown Vehicle & Goverdhan


3 01.01.2023 18:06 hrs Jait Village 131+900 RHS 4 2 2 3 1 4 1 Bike Reg No. 1 1 Ambulance &
RJ02BY7998 Police Staff

Car Reg RPV-05 & Police


4 01.01.2023 22:21 hrs Chhata 110+67 LHS 8 4 3 3 1 4 2 1
No.UP85BR3457 Staff

5 02.01.2023 01:15 hrs Kheetam Jheel 181+400 RHS 3 1 2 3 1 4 2 Unknown Vehicle 1 Police Staff

A truck reg-

MONTHLY PROGRESS REPORT JANUARY -2023.


ourAmbulance ,
HR55AH5567 , A
6 04.01.2023 11:30 hrs kurkande cut 162+160 RHS 3 4 2 3 1 4 1 1 our hydra, RPV-
Truck Reg-
RJ14GN4571 3

bike reg no.- Our Ambulance


7 04.01.2023 19:37 hrs LV Motors farah 168+580 RHS 2 2 4 3 2 4 1 2
UP85BV6434 & Local Public

Car Reg No-


8 05.01.2023 04:05 hrs Guru Ka Tal 193+360 LHS 4 4 3 3 1 4 2 1 RPV-4 staff
UP80FH2451
ACCIDENT DATA UP

Our Ambulance,
truck Reg No- Dial 108
9 05.01.2023 14:48 hrs Dwapar Restorent 162+090 LHS 3 3 2 3 1 4 1 1
RJ25GA3125
M/s L.N. Malviya Infra Projects Pvt Ltd

Ambulance &
Our Hydra

RPV-3, our
10 06.01.2023 21:50 hrs Jaint Thana 132+830 LHS 1 4 3 3 2 4 2 Tractor Trolly 1
Hydra & Police

RPV-3,Jaint
truck Reg no- Ambulance,
11 07.01.2023 04:02 hrs Jaint Thana 132+760 LHS 3 3 3 3 2 4 2 1 5
HR39E0749 RPV-5 Police
staff, Pvt Hydra
Karman
Bus Reg No- Ambulance,
12 07.01.2023 20:22 hrs Chhata Underpass 112+880 LHS 4 2 2 3 1 4 1 4
UP85BT1719 RPV-5,Police
staff & Pvt

Eicher canter Reg


20.500 TO KM. 200 IN THE STATE OF HARYANA AND U.P ON DBFOT BASIS.

13 08.01.2023 01:32 hrs Township 151+740 LHS 1 4 3 3 2 4 2 1 RPV-3


No-UP81AF7900

Car Reg
RPV-3 & Local
14 08.01.2023 17:07 hrs Nawada 149.260 RHS 3 4 3 3 3 4 1 No.DL3CCN5586&un 1
known Vehicle Public
INDEPENDENT ENGINEER SERVICES DURING

Bike Reg Our Ambulance

75
15 08.01.2023 22:05 hrs Refinery Gate No-09 159.810 LHS 8 3 1 3 3 4 2 1
No.UP85BZ4470 & Police Staff
OPERATION & MAINTENANCE PERIOD OF 5 YEARS FOR “SIX LANINGOF DELHI-AGRA SECTION FROM KM.
Bike Reg. No: Our Ambulance
16 09.01.2023 15:15 hrs Fateha villege 167.270 LHS 2 1 2 3 1 4 1 1 1
UP85AX3269 & Police Staff

RPV-04, Policr
Bus Reg No-
17 10.01.2023 08:33 hrs Shahjad Pur 175.000 RHS 3 4 3 3 1 4 2 4 Staff & Our
UP85AH9654
Hydra

RPV-04, Our
Truck Reg No-
18 12.01.2023 18:28 hrs PNC Flyover 177.100 RHS 3 3 2 3 2 4 1 2 Ambulance &
NL01AD0035
Our Hydra

RPV-4, Police
Eicher canter Reg.
19 13.01.2023 21:30 hrs PNC Flyover 176.460 LHS 3 4 3 3 1 4 2 1 staff & Pvt.
No: UP80ET4515
Hydra
RPV-3, Dial108
Eicher canter Reg Ambulance, pvt
20 14.01.2023 04:25 hrs GLA 129.350 RHS 1 3 3 3 1 4 1 1
No-HR55AF7164 hydra & Police
staff

Bike Reg. No. Our Ambulance


21 14.01.2023 16:08 hrs SWB RHS 164.040 LHS 3 2 2 3 1 4 1 2
UP85BM3383 & Police Staff

22 14.01.2023 18:30 hrs HP Petrol Pump Arsena 179+510 LHS 4 4 4 3 1 4 1 Animal 1 1 RPV-4 & JCB

RPV-
Bike Reg
05.Ambulance,L
23 15.01.2023 09:24 hrs Sugar Mil Chhata 114.400 LHS 4 2 3 3 1 4 1 No.UP80GJ2657 & 1 1

MONTHLY PROGRESS REPORT JANUARY -2023.


CNG Reg No. A/F ocal Public &
Police Staff
Bike Reg
No.UP85AH3311 & Our Ambulance
24 15.01.2023 17:34 hrs Fauji Dhaba Mahuvan 163+420 LHS 4 3 3 3 1 4 1 3 2
Bike Reg & Local Public
No.UP85AF8223
Our ambulance
Auto Reg. No. - & Hydra ,RPV
25 16.01.2023 18:50 hrs Township Flyover 152+090 RHS 2 3 4 3 1 4 1 1
UP85CT9307 staff & Police
staff
RPV-5 , Our
Tata magic Reg. No:
M/s L.N. Malviya Infra Projects Pvt Ltd

26 17.01.2023 03:08 hrs K.D. Chauki 122+730 LHS 8 4 3 3 1 4 1 1 hydra & Police
DL1LV0375
staff

RPV-4, Pvt
Truck Reg. No:
27 17.01.2023 18:43 hrs Near Khndari Flyover 196+280 LHS 1 4 3 3 1 4 1 1 Hydra & Police
RJ52GA1325
staff

Truck Reg No-


28 18.01.2023 01:40 hrs Near sanskriti University 115+030 LHS 1 4 8 3 1 4 1 1 RPV-5
RJ40GA0665

RPV-4, Our
Truck Reg no-
29 18.01.2023 17:33 hrs Brij Ki Rasoi (Farah) 169+220 LHS 3 2 2 3 1 4 1 1 Ambulance &
NL01AA4317
20.500 TO KM. 200 IN THE STATE OF HARYANA AND U.P ON DBFOT BASIS.

Police staff

RPV-5, Jaint
Max Pickup Reg No-
30 19.01.2023 04:58 hrs Chhatikara 133+950 LHS 1 3 8 3 1 4 1 1 1 Ambulance &
DL1LAF6334
Police staff
RPV-5, Jaint
INDEPENDENT ENGINEER SERVICES DURING

Eicher canter Reg Ambulance, Pvt

76
31 21.01.2023 04:00 hrs Agra Gwalior Dhaba Chauma 124+940 RHS 3 3 6 3 1 4 2 2 1
No-PB18AW8662 Hydra & Police
staff
OPERATION & MAINTENANCE PERIOD OF 5 YEARS FOR “SIX LANINGOF DELHI-AGRA SECTION FROM KM.
RPV-4, Our
Bike Reg No-
32 21.01.2023 23:22 hrs Brij Ki Rasoi (Farah) 169+050 RHS 6 2 1 3 1 4 1 1 Ambulance &
UP86AE6591
Police staff
Our Ambulane,
Eicher Canter Reg RPV-3, JCB,
33 22.01.2023 01:45 hrs HP Petrol Pump Refinery 159+990 RHS 3 2 2 3 1 4 1 2 1
no-DL1MA2030 Our Hydra &
Police staff.

Max Pickup Reg No- RPV-3 & Our


34 22.01.2023 03:42 hrs OLD RTO 148+810 RHS 1 4 3 3 1 4 1 1
MP07GB0498 Hydra

RPV-5 , Our Jait


Max Pickup Reg No-
35 23.01.2023 05:55 hrs GLA University 128+780 RHS 1 3 3 3 1 4 1 1 1 ambulance &
UP81CT5634
Our Hydra

Unknown vehicle & Ambulance &


36 23.01.2023 19:22 hrs LV Motors Farah 168+570 LHS 4 3 3 3 1 4 1 Bike Reg No. 2 1
UP80DE8447 Local Public

Car Reg RPV-5, Karman


No.RJ23CD5417 & Ambulance, Our
37 23.01.2023 19:24 hrs Sri Ji Baba Collage (Nari Semri) 117+780 LHS 4 3 3 3 1 4 1 1 2
Recovery Crane Reg Hydra & Police
No.UP85CT5222
staff
RPV-3, Our
Truck Reg
38 23.01.2023 19:37 hrs Jai Guru Petrol Pump 146+420 LHS 8 4 1 3 1 4 1 1 Hydra & Police
No.NL01AA6454
staff

Bike Reg. No: Our Ambulance


39 26.01.2023 18:08 hrs Fatiha Flyover 166+240 LHS 6 2 3 3 1 4 1 1
UP80FH9202 & Local Public

Unknown Vehicle & RPV-03 & Our


40 27.01.2023 00:45 hrs Petrol Pump (Kurkande) 163.070 RHS 4 3 2 3 1 4 1 2
Bike A/F Ambulance

Truck Reg

MONTHLY PROGRESS REPORT JANUARY -2023.


RPV-04, Police
Truck Reg No.UP53ET7181 & No.UP53ET7181 &
41 27.01.2023 04:13 hrs 190.690 LHS 4 4 3 3 1 4 1 3 Staff & Pvt
Truck Reg No.DL1GC1099 Truck Reg
No.DL1GC1099 Hydra

Bike Reg No- Our Ambulance


42 27.01.2023 18:55 hrs Kurkande cut 162+780 RHS 2 3 4 3 1 4 1 2
UP85BR6348 & Local Public

Our karman
Bike Reg No- AMB & RPV
43 28.01.2023 16:05 hrs Chhata Thana 112+280 RHS 2 3 4 3 1 4 1 2
UP85CD5807 staff ,Local
public & police
Our jait
truck ambulance ,
44 29.01.2023 12:20 hrs Chaumuha Villege 125+140 RHS 2 1 2 3 1 4 1 1
Reg.No.RJ52GA6979 Local public &
M/s L.N. Malviya Infra Projects Pvt Ltd

Police staff
Our Jait AMB ,
45 29.01.2023 01:04 hrs GLA University 128+860 LHS 2 1 2 3 1 4 1 Unknown Vehicle 1 RPV -5 & Police
Staff

Eicher canter Reg RPV-3 & Our


46 29.01.2023 01:05 hrs Baad Villege 153+560 LHS 1 4 3 3 1 4 1 1
No-HR73B5450 Hydra staff

RPV-03,
Goverdhan
47 29.01.2023 22:49 hrs Radha Vally 140.090 LHS 8 2 1 3 1 4 1 Thar Reg No. A/F 2 2
Ambulance,
Local Persons,
Our Jait
Ambulance ,
48 31.01.2023 19:00 hrs Near By GLA 129+760 LHS 8 1 4 3 1 4 1 Unknown 1
Local public &
20.500 TO KM. 200 IN THE STATE OF HARYANA AND U.P ON DBFOT BASIS.

Police staff
B 1- Overturning, 2- Head on collision, 3- Rear end collision, 4- Collision Brush / Slide wipe, 5- Right turn collision, 6- Skidding, 7- Left turn collision, 8- Others

C 1 - Fatal, 2 - Grievous injury, 3 - Minor injury, 4 - Non injury

D 1 - Drunken, 2 - Over speeding, 3 - Vehicle out of control, 4 - Fault of driver of motor vehicle/driver of other vehicle/cyclist/pedestrian/passenger, 5 - Defect in mechanical condition of motor vehicle/road condition, 6 - Dense Fog, 7- Road condition, 8-Dozed off

E 1 - Single lane, 2 - Two lanes, 3 - Three lanes or more with central divider (median), 4 - F lanes or more with central divider

F 1 - Straight road, 2 - Slight curve, 3 - Sharp curve, 4 - Flat road, 5 - Gentle incline, 6 - Steep incline, 7 - Hump, 8 - Dip
INDEPENDENT ENGINEER SERVICES DURING

G 1 - T-Junction, 2 - Y-Junction, 3 - F arm junction, 4 - Staggered junction, 5 - Junction with more than 4 arms, 6 - Roundabout junction, 7 - Manned rail crossing, 9 - Unmanned rail crossing.

77
H 1 - Fine, 2 - Mist/Fog, 3 - Cloudy, 4 - Light rain, 5 - Heavy rain, 6 - Hall/Sleet, 7 - Snow, 8 - Strong wind, 9 - Dust storm, 10 - Very hot, 11 - Very cold, 12 - Other extraordinary weather condition.
OPERATION & MAINTENANCE PERIOD OF 5 YEARS FOR “SIX LANINGOF DELHI-AGRA SECTION FROM KM.
M/s L.N. Malviya Infra Projects Pvt Ltd
INDEPENDENT ENGINEER SERVICES DURING
OPERATION & MAINTENANCE PERIOD OF 5 YEARS FOR “SIX LANINGOF DELHI-AGRA SECTION FROM KM.
20.500 TO KM. 200 IN THE STATE OF HARYANA AND U.P ON DBFOT BASIS.

34. Detail of Complaints

Issue Descriptio

Long
Queue/Wait
at Toll Plaza - Delhi
29- Non (New rodelhi@nhai.org
Jan-23 Deepak 7459515 Jan-23 Emergency gadpuri Delhi) rodelhi01@gmail.com Mathura mat@nhai.org

Delhi
Rahul 29- Misbehaviour (New rodelhi@nhai.org
Jan-23 Chwal 7460621 Jan-23 by plaza staff Karman Delhi) rodelhi01@gmail.com Mathura mat@nhai.org

Road Delhi
29- Conditions of (New rodelhi@nhai.org
Jan-23 Sohail 7460516 Jan-23 the NH Badarpur Delhi) rodelhi01@gmail.com Mathura mat@nhai.org

Road Delhi
30- Conditions of (New rodelhi@nhai.org
Jan-23 Naveen 7462985 Jan-23 the NH Gadpuri Delhi) rodelhi01@gmail.com Mathura mat@nhai.org

Complaining Delhi
30- About NH (New rodelhi@nhai.org
Jan-23 Naveen 7463014 Jan-23 Services Gadpuri Delhi) rodelhi01@gmail.com Mathura mat@nhai.org
Caller is comp

Monthly Pass Delhi


Balbir 30- Discount Not (New rodelhi@nhai.org
Jan-23 Singh 7466347 Jan-23 Received Gadpuri Delhi) rodelhi01@gmail.com Mathura mat@nhai.org
31- Monthly Pass Delhi rodelhi@nhai.org mat@Caller is complaint that while crossed th
Jan-23 Heeralal 7472027 Jan-23 Discount Not Mahuvan (New rodelhi01@gmail.com Mathura
nhai.org

MONTHLY PROGRESS REPORT JANUARY -2023. 78


M/s L.N. Malviya Infra Projects Pvt Ltd
INDEPENDENT ENGINEER SERVICES DURING
OPERATION & MAINTENANCE PERIOD OF 5 YEARS FOR “SIX LANINGOF DELHI-AGRA SECTION FROM KM.
20.500 TO KM. 200 IN THE STATE OF HARYANA AND U.P ON DBFOT BASIS.

Received Delhi)

35. Encroachment List

List of encroachment enclosed sent in MIR

36. Lane Closure Report

Nil

37.Annexure

1.3.2 Project Milestones


1.3.2.1 Project Milestone I – The Concessionaire shall commence the construction of project
highway and spend not less than 10% (Ten Percent) of the total contract cost. This shall occur on
the 255th (Two Hundred Fifty Fifth) day from the appointed date. (From 16-10.2012 to27.06.2013)
1.3.2.2 Project Milestone II – The Concessionaire shall commence the construction of the project
highway and should not spend less than 35% (Thirty Five percent) of the total contract cost. This
shall occur on the 510th (Five Hundred and Tenth) day from the appointed date. (From 16-10.2012
to 09.03.2014)
1.3.2.3 Project Milestone III – This shall occur on the date of falling on the 770th (Seven
Hundred and Seventeenth) day from the appointed date. Prior to the occurrence of the project mile
stone III, the Concessionaire shall have commenced and expended not less than 70% (Seventy
Percent) of the total capital cost set forth in the financial package.(From 16-10.2012 to 24.11.2014)
1.3.2.4 Concession period 26 years: - (Including the construction period of 912 daysfrom the
appointed date to completion date 15.04.2015
Extension of Time
First Milestone has been lapsed on 27.06.2013 and progress achievement by that time was almost
NIL. The Project Director NHAI has issued a show cause notice under clause 12.4.2 of CA vide letter
No NHAI/CMU/MTR/6-laning/2013/D-32686 dated 25.06.2013.Subsequently the engineer has
recommended to Authority vide letter no. dated 15.11.2013 to invoke the provision in clause 12.4.2
of the Concession Agreement.

MONTHLY PROGRESS REPORT JANUARY -2023. 79


M/s L.N. Malviya Infra Projects Pvt Ltd
INDEPENDENT ENGINEER SERVICES DURING
OPERATION & MAINTENANCE PERIOD OF 5 YEARS FOR “SIX LANINGOF DELHI-AGRA SECTION FROM KM.
20.500 TO KM. 200 IN THE STATE OF HARYANA AND U.P ON DBFOT BASIS.

Second Milestone has been lapsed on 09.03.2014 and achievement by that time was 2% only. Now
the Concessionaire has submitted EOT of Milestone–II vide letter No DATR/SITE/IE/2014/2031
dated 26th December 2014,
Third MileStone: -has been lapsed on 10.07.2016 a notice under clause 12.4.2 has been issued vide
Independent Engineer IE's letter no. URSSWI/PMG/N1852/18/454 dated 08.10.2016
Schedule Six Laning Date: - Punch list for balance items for completion of project highway has
been prepared and has been submitted to the Authority and Concessionaire vide Independent
Engineer letter no. URSSWI/PMG/N1852/IE Delhi-Agra/2022/706 dated 28 th April 2022.
The I.E has issued the PCOD with punch list A and B vide URSSWI/PMG/IE Delhi-
AGRA/2022/818 dated 20.05.22
EOT Recommended
Achievement date as Total EOT on account of
Sl. On account of
Description envisaged in Concession proportionate delay of 637 days due
No. delay in Revised Mile
Agreement to non- availability of front on
environment Stones date
account of acquisition of land and
Clearance
tree cutting
Project Mile 255 days from the appointed (637-363)/912 x 255 = 77 days
1 363 days Sep 10, 2014
Stone-I date i.e. 27.06.2013 363+77= 440 days

Project Mile 510 days from the appointed (637-363)/912 x 510 = 153 days
2 363 days August 07, 2015
Stone-II date i.e. 09.03.2014 363+153= 516 days

Project Mile 770 days from the appointed (637-363)/912 x 770 = 231 days
3 363 days July 10, 2016
Stone-III date i.e. 24.11.2014 363+231= 594 days

Schedule Six 912 days from the appointed


4 363 days 22.05.2022
Laning Date date i.e. 15.04.2015

EOT Application –I Submitted by EOT Application –II Submitted by


Concessionaire Concessionaire
Recommendation of
Original IE has been
Concessionaire Recommendation Concessionaire
date of approved by the
Application by IE Application
completion NHAI vide letter no.
as per CA 39499 dt. 09.02.2016
Revised Date as Revised Date as
Revised Date as Revised Date as per
per Application - per Application -
per Application -I Application –II
I II
Milestone 1 27.06.2013 25.06.2014 26.03.2014 27.12.2014 Sep 10, 2014
Milestone 2 09.03.2014 07.03.2015 29.12.2014 10.03.2016 August 07, 2015
Milestone 3 24.11.2014 22.11.2015 01.06.2017 July 10, 2016
01-Feb-18
Project End 15.04.2015 12.04.2016 20.05.2022

MONTHLY PROGRESS REPORT JANUARY -2023. 80

You might also like