October ‐ 2021
to be change
Owner : National Highways Authority of India
Employer/ Concessioner: IRCON Davanagere Haveri Highway Limited
Independent Engineer : Aarvee Associates Architects Engineers & Consultants Pvt., Ltd.,
Contractor : M/s G R Engineers and Contractors
CONTENTS
2.0 Maps
6.0 Appendix
6.6 Schedule-K 37 - 38
has entrusted National Highways Authority of India (NHAI) under the prestigious National
Highways Development Project (NHDP) Phase-III Programme, for taking up 4-laning work
Transfer (DBFOT) basis of the existing 2-lane National Highway No. 59, connecting
National Highway No. 59, connecting Ahmadabad with Indore, is one of the important
Ahmadabad important cities with its rich hinterland part of Gujarat and Madhya Pradesh.
NH-59, which originates from Ahmadabad and ends at Indore, en route passing through
very important cities & Towns like Kanba, Kathlal, Balasinor, Sevaliya, Timba, Godhra,
Piplod, Limkheda, Dahod, Katwara, Jhabua, Rajgarh, Dhar and Lebad travelling a
distance of 376 Km. through the state of Gujarat (212 Km) and Madhya Pradesh (164
NH-59 in the state of Gujarat. The project corridor starts from KM 128.117 near Godhra
(the Tender Notice) for short listing of Bidders for “Construction, Operation and
on DBFOT basis”. The NHAI shortlisted certain bidders and finally awarded the work to
M/s BSCPL Infrastructure Limited. The selected bidder M/s BSCPL Infrastructure
Limited, later formed a SPV Company i.e. M/s BSCPL GODHRA TOLLWAYS LIMITED
as a concessionaire to undertake and perform the obligations and exercises the rights of
the selected bidder under the LOA. M/s BSCPL GODHRA TOLLWAYS LIMITED acting as
[1]
a special purpose vehicle
[2]
(concessionaire) has been incorporated for implementing the project on Design, Build,
Finance, Operate and Transfer (DBFOT) basis for a Concession Period of twenty seven
(27) years. The concession agreement was signed between NHAI and M/s BSCPL
BSCPL Infrastructure Limited as their EPC Contractor for carrying out and implements the
NHAI has also appointed M/s Intercontinental Consultants and Technocrats Private
Limited to act as the Independent Engineer for this Project, who got mobilized on 15 th
January, 2011.The concessionaire and SBI Capital Markets Limited (the Lead Arranger)
have approached the State Bank of India (SBI) for financing the project debt. The
Consortium of lenders with State Bank of India as Senior Lenders have agreed to finance
the debt capital for the Project and the Financial Closure was achieved on 14 th May,
Engineers to oversee the Project Implementation and monitor the work progress.The
Appointed Date of the Project was declared by the NHAI after having a joint meeting of the
Project Director, NHAI, the Independent Engineer and the Concessionaire at NHAI Head
Office, Dwarka on 09th March, 2011 and declared the Appointed Date as 01 st March, 2011.
The Concessionaire has executed the project more than 75% and Provisional Certificate
171+300 ROB) by ICT on 25.09.2015 and PCOD-2 has been issued by NHAI on
28.09.2015. The Toll Rates are revised for the PCOD-2 and the rates are effected from
30-09-2015.
[3]
1.2 KEY ORGANIZATIONS
[4]
1.3 Project Data
Signing of Concession
Agreement: 8th October 2021
[5]
1.4 Operation and Maintenance activities
Independent Consultant during this reporting period of October 2021. This is the 1st
Initial Rates: The Concessionaire after completing the 78.271km out of 87.102km i.e.
pursuant to Article 14.3.2 of the C. A. The Independent Engineer has obtained the consent
of the Authority and issued the provisional certificate and the commercial operation has
been started at 5:00 a.m. on 02nd day of November 2013 after publishing the user fee rates
in one English and one in Gujarati (vernacular) language leading newspapers on 1 st day of
November 2013.
Revised Rates: The annual revision of user fee have been implemented from 01 st April
2014 after publishing the NHAI approved revised user fee rates in one English and one in
PCOD-2 Revised Rates: The Concessionaire after completing the 85.467km out of
pursuant to Article 14.3.2 of the C. A. The Authority and issued the provisional certificate
and the toll revised rates are started from 30th September 2015 after publishing the user
fee rates in one English and one in Gujarati (vernacular) language leading
[6]
2.0 Maps
3.0 O & M General
MSR (O and M) [10] October-21
MONTHLY STATUS REPORT (O&M)
October 2021
Monthly Status Report (O&M)
October 2021
3.2 Equipment’s Deployed at Site
1 Ambulance No. 3
4 Broomer No. 1
5 Tractors No. 2
6 Tippers No. 1
7 JCB No. 2
S.
Description 1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22 23 24 25 26 27 28 29 30 Remarks
No.
VISUAL INSPECTION
1 O&M
Unpaved Shoulder G G G G G G G G G G G G G G G G G G G G G G G G G G G G G G
Carriageway Cleaning G G G G G G G G G G G G G G G G G G G G G G G G G G G G G G
- Pot Hole N N N N N N N N N N N N N N N N N N N N N N N N N N N N N N
2 MEDIAN
-Median Maintenace G G G G G G G G G G G G G G G G G G G G G G G G G G G G G G
3 SIDE SLOPE
- Shape G G G G G G G G G G G G G G G G G G G G G G G G G G G G G G
- Pakka Drain G G G G G G G G G G G G G G G G G G G G G G G G G G G G G G
- Kaccha Drain G G G G G G G G G G G G G G G G G G G G G G G G G G G G G G
Legend:
G - Good F - Fair P - Poor N - Nil
S.
Description 1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22 23 24 25 26 27 28 29 30 Remarks
No.
VISUAL INSPECTION
1 Safety Barrier
Damaged Barrier N N N N N N N N N N N N N N N N N N N N N N N N N N N N N N
Signs G G G G G G G G G G G G G G G G G G G G G G G G G G G G G G
Marking G G G G G G G G G G G G G G G G G G G G G G G G G G G G G G
Delineator G G G G G G G G G G G G G G G G G G G G G G G G G G G G G G
Lighting G G G G G G G G G G G G G G G G G G G G G G G G G G G G G G
3 Traffic Condition G G G G G G G G G G G G G G G G G G G G G G G G G G G G G G
4 Encroachment N N N N N N N N N N N N N N N N N N N N N N N N N N N N N N
Legend:
G - Good F - Fair P - Poor N - Nil
S. Severity
Description Category Comment Remarks
No. Poor Fair Good
1 VISUAL INSPECTION
A Side Slope
2 CLOSE INSPECTION
A Riding Surface
BMedian
CDrainage
D Bridges
S. Severity
Description Category Comment Remarks
No. Poor Fair Good
F Other facilities
Removal of unwanted vegetation and replacement of dead trees
Vegetation Civil NA NA NA
with new plants is in progress.
S. Severity
Description Category Comment Remarks
No. Poor Fair Good
C Encroachment
S. Severity
Description Category Comment Remarks
No. Poor Fair Good
C Encroachment
3 03/09/2015 3 Km 142+060 to Km 144+400 Avenue Plantation 90 days Replanted with in time limit
9 09/09/2015 9 Km 185+000 to Km 187+000 Unwanted Vegetation 15 days Removed within time limit
11 11/09/2015 11 Km 197+000 to Km 198+000 Median Plantation 90 days Replanted with in time limit
12 12/09/2015 12 Km 152+650 to Km 153+900 Avenue Plantation 90 days Replanted with in time limit
14 14/09/2015 14 Km 199+600 to Km 201+000 Median Plantation 90 days Replanted with in time limit
15 15/09/2015 15 Km 161+650 to Km 161+750 Unwanted Vegetation 15 days Removed within time limit
16 16/09/2015 16 Km 194+900 to Km 196+000 Avenue Plantation 90 days Replanted with in time limit
19 19/09/2015 19 Km 211+200 to Km 212+000 Avenue Plantation 90 days Replanted with in time limit
21 21/09/2015 21 Km 211+000 to Km 212+000 Unwanted Vegetation 15 days Removed within time limit
23 23/09/2015 23 Km 139+500 to Km 140+100 Avenue Plantation 90 days Replanted with in time limit
24 24/09/2015 24 Km 156+650 to Km 157+950 Avenue Plantation 90 days Replanted with in time limit
25 25/09/2015 25 Km 202+000 to Km 205+000 Median Plantation 90 days Replanted with in time limit
26 26/09/2015 26 Km 212+210 to Km 213+400 Avenue Plantation 90 days Replanted with in time limit
27 27/09/2015 27 Km 197+000 to Km 198+000 Unwanted Vegetation 15 days Removed within time limit
28 28/09/2015 28 Km 166+300 to Km 166+400 Unwanted Vegetation 15 days Removed within time limit
29 29/09/2015 29 Km 167+890 to Km 168+200 Avenue Plantation 90 days Replanted with in time limit
30 30/09/2015 30 Km 173+000 to Km 174+000 Median Plantation 90 days Replanted with in time limit
S. Concrete 7 Days' Strength 28 Days' 7 Days' Strength 28 Days' 7 Days' Strength 28 Days'
Remarks
No. Grade Up to Up to (Set) Strength (Set) Strength (Set) Strength
Aug-14 (Set) (Set) (Set)
July-14 Aug-14
Required Casted Required Casted Required Casted Required Casted Required Casted Required Casted
Shri R.K.Bansal, Chief General Manager (Tech) & RO,Gandhinagar visited project site
on 01.09.2015.
The Independent Engineer carried out regular inspection for monitoring of maintenance
work. The daily updates are enclosed in this report in “Operation and Maintenance stage”.
The regular meetings were also being conducted during month to have proper
coordination for the project.
S. No. Particular
Around 10,500 vehicles other than two wheelers, three wheelers and tractors have
1 been exempted in this month due to and during conflict with local villagers on toll fee
exemption issues. Which is turn into a great fiscal loss in this month.
A tendency has been found that Owners / Drivers of Class-1 and Class-2 vehicles are
2 trying to escape without paying toll fee. They are gaining high speed at the time of
escape, leaving scope of accidental hazard near / around toll complex.
As per the report / observations of the local RTO & Police officials, a considerable
numbers of traffic diverting / escaping through alternative routs from Devgarh Bariya
3
and from Santroad to avoid Toll Tax. This tendency in turn contributing to a great
financial loss subsequently.
1 ‐ 4 1 3 4 4 ‐ 1 6&1 1 ‐ ‐ ‐ ‐
2 ‐ 2 1 2 4 4 ‐ 1 1&1 2 2 ‐ ‐ ‐
3 ‐ 1 1 2 4 2 ‐ 1 1&2 1 ‐ ‐ ‐ ‐
4 ‐ 4 1 3 4 2 ‐ 1 6&5 1 ‐ ‐ ‐ ‐
5 ‐ 4 3 3 4 4 ‐ 1 6&5 ‐ ‐ 1 ‐ ‐
6 ‐ 3 2 2 4 4 ‐ 1 3&5 ‐ 3 ‐ ‐ ‐
Legend:
A: Urban / Rural and details of surrounding land use
B: 1‐ Overturning, 2‐ Head‐on‐Collision, 3‐ Rear end collision, 4‐ Collision brush / side wipe, 5‐ Right turn collision, 6‐ Skidding, 7‐ Others
C: 1‐ Fatal, 2‐ Grevious Injury, 3‐ Minor Injured, 4‐ Non Injury
D: 1‐ Drunken, 2‐ Overspeeding, 3‐ Vehicle out of control, 4‐ Fault of driver of motor vehicle / cyclist / pedestrian / passenger 5‐ Defect in mechanical condition of motor vehicle / road condition
E: 1‐ Single lane, 2‐ Two lane, 3‐ Three lane or more without central divider, 4‐ Four lanes or more with central divider
F: 1‐Straight road, 2‐ Slight curve, 3‐ Sharp curve, 4‐ Flat road, 5‐ Gentle incline, 6‐ Steep incline, 7‐ Hump, 8‐ Dip
G: 1‐T Junction, 2‐ Y Junction, 3‐ Four arm Junction, 4‐ staggered junction, 5‐ Junction with more than four arms, 6‐ Roundabout Junction, 7‐ Manned rail crossing, 8‐ Unmanned rail crossing
H: 1‐Fine, 2‐Mist/Fog, 3‐Cloudy, 4‐Light Rain, 5‐Heavy Rain, 6‐ Hail / sleet, 7‐ Snow, 8‐ Strong Wind, 9‐ Dust Storm, 10‐ Very Hot, 11‐ Very cold, 12‐ Other extraordinary weather condition
J: 1‐ Car, 2‐ LCV/LGV, 3‐ Minibus, 4‐ Bus / Truck (2A), 5‐ Truck/HMV/EME/MAV (3‐6A), 6‐ OSV, 7‐ 2 wheelers, 8‐ Pedestrian
Sl.
Letter No. Date Subject To From
No.
10
11
12
13
Sl.
Letter No. Date Subject To From
No.
14
15
16
17
10
11
12
13