ID Task Name Duration Start Finish Resource Names Remarks 24 Jun '17 15 Jul '17 05 Aug '17 26 Aug

source Names Remarks 24 Jun '17 15 Jul '17 05 Aug '17 26 Aug '17 16 Sep '17 07 Oct '17 28 Oct '17 18 Nov '17 09 Dec '17 30 Dec '17
26 04 12 20 28 05 13 21 29 06 14 22 30 08 16 24 01 09 17 25 03 11 19 27 04
1 EGA Tanks Revised Painting Schedule Rev. 3 126 days 27 Jun '17 20 Nov '17
2 Storage tanks - 20 Nos. 126 days 27 Jun '17 20 Nov '17
3 230TK10040 38 days 27 Jun '17 09 Aug '17
4 Scaffolding Modification and encapsulation 10 days 27 Jun '17 08 Jul '17
5 Modification 4 days 27 Jun '17 01 Jul '17
6 Sheeting 6 days 02 Jul '17 08 Jul '17

7 Blasting and Painting 28 days 09 Jul '17 09 Aug '17


8 Surface Preparation and priming of roof 2 days 09 Jul '17 10 Jul '17 Blasters[3],Sprayer,Semi Skilled[4] Blasters[3],Sprayer,Semi Skilled[4]
9 Surface Preparation and priming of shell and 2 days 11 Jul '17 12 Jul '17 Blasters[9],Sprayer[2],Semi Blasters[9],Sprayer[2],Semi Skilled[7]
structures Skilled[7]
10 BPJV Stopped blasting due to dust emission 1 day 13 Jul '17 13 Jul '17 Blasters,Semi Skilled[5],Sprayer[3] Blasters,Semi Skilled[5],Sprayer[3]

11 BPJV Stopped blasting due to dust emission 1 day 14 Jul '17 14 Jul '17 Blasters[5],Semi Skilled[6] Blasters[5],Semi Skilled[6]

12 BPJV Stopped blasting due to dust emission 1 day 15 Jul '17 15 Jul '17 Blasters[7],Semi Blasters[7],Semi Skilled[18],Sprayer[4]
Skilled[18],Sprayer[4]
13 BPJV Stopped blasting due to dust emission 1 day 16 Jul '17 16 Jul '17 Blasters[3],Semi Skilled[6] Blasters[3],Semi Skilled[6]

14 BPJV Stopped blasting due to dust emission 1 day 17 Jul '17 17 Jul '17 Blasters[5],Semi Blasters[5],Semi Skilled[19],Sprayer[5]
Skilled[19],Sprayer[5]
15 Surface Preparation and priming of shell and 3 days 18 Jul '17 20 Jul '17 Blasters[9],Sprayer[2],Semi Blasters[9],Sprayer[2],Semi Skilled[7]
structures Skilled[7]
16 IDLE Due to industrial hygienic test 1 day 21 Jul '17 21 Jul '17 Blasters,Semi Skilled[3],Sprayer[3] Blasters,Semi Skilled[3],Sprayer[3]

17 Mobilization delay from LOT #5 to Tank 230/40 1 day 21 Jul '17 21 Jul '17 Blasters[3],Semi Skilled,Sprayer Blasters[3],Semi Skilled,Sprayer

18 IDLE Due to industrial hygienic test 1 day 22 Jul '17 22 Jul '17 Blasters[7],Semi Blasters[7],Semi Skilled[10],Sprayer[2]
Skilled[10],Sprayer[2]
19 IDLE Due to industrial hygienic test 1 day 23 Jul '17 23 Jul '17 Blasters[6],Semi Blasters[6],Semi Skilled[5],Sprayer[2]
Skilled[5],Sprayer[2]
20 IDLE Due to industrial hygienic test 1 day 24 Jul '17 24 Jul '17 Semi Skilled[4] Semi Skilled[4]

21 Mobilization delay from LOT #5 to Tank 230/40 1 day 24 Jul '17 24 Jul '17 Semi Semi Skilled[2],Blasters[3],Sprayer[3]
Skilled[2],Blasters[3],Sprayer[3]
22 IDLE Due to industrial hygienic test 1 day 25 Jul '17 25 Jul '17 Blasters[9],Semi Skilled[8] Blasters[9],Semi Skilled[8]

23 Mobilization delay from LOT #5 to Tank 230/40 1 day 25 Jul '17 25 Jul '17 Blasters[2],Semi Skilled[6] Blasters[2],Semi Skilled[6]

24 IDLE Due to industrial hygienic test 1 day 26 Jul '17 26 Jul '17 Blasters[9],Semi Blasters[9],Semi Skilled[18],Sprayer[9],Chargehand
Skilled[18],Sprayer[9],Chargehand
25 IDLE Due to industrial hygienic test 1 day 27 Jul '17 27 Jul '17 Blasters,Semi Skilled[4],Sprayer[7] Blasters,Semi Skilled[4],Sprayer[7]

26 Cleaning and Touch up 3 days 29 Jul '17 31 Jul '17 Semi Skilled[7],Blasters[6] Semi Skilled[7],Blasters[6]
27 1st stripe coat and inspection 4 days 01 Aug '17 05 Aug '17 Semi Skilled[7] Semi Skilled[7]
28 Final coat, touch up and inspection 4 days 06 Aug '17 09 Aug '17 Sprayer[2],Semi Skilled[7] Sprayer[2],Semi Skilled[7]
29 230TK10020 42 days 10 Jul '17 27 Aug '17
30 Scaffolding Modification and encapsulation 7 days 10 Jul '17 17 Jul '17
31 Modification 4 days 10 Jul '17 13 Jul '17
32 Sheeting 3 days 15 Jul '17 17 Jul '17 2 days delay for sheeting
33 Blasting and Painting 35 days 18 Jul '17 27 Aug '17
34 BPJV Stopped blasting due to dust emission 1 day 18 Jul '17 18 Jul '17 Blasters[7],Semi Blasters[7],Semi Skilled[19],Sprayer[5]
Skilled[19],Sprayer[5]

Page 1
ID Task Name Duration Start Finish Resource Names Remarks 24 Jun '17 15 Jul '17 05 Aug '17 26 Aug '17 16 Sep '17 07 Oct '17 28 Oct '17 18 Nov '17 09 Dec '17 30 Dec '17
26 04 12 20 28 05 13 21 29 06 14 22 30 08 16 24 01 09 17 25 03 11 19 27 04
35 IDLE Due to industrial hygienic test 1 day 19 Jul '17 19 Jul '17 Blasters[3],Semi Blasters[3],Semi Skilled[20],Sprayer[5]
Skilled[20],Sprayer[5]
36 IDLE Due to industrial hygienic test 1 day 20 Jul '17 20 Jul '17 Blasters[4],Semi Blasters[4],Semi Skilled[15],Sprayer[5]
Skilled[15],Sprayer[5]
37 IDLE Due to industrial hygienic test 1 day 22 Jul '17 22 Jul '17 Blasters[3],Semi Skilled[6],Sprayer Blasters[3],Semi Skilled[6],Sprayer

38 IDLE Due to industrial hygienic test 1 day 23 Jul '17 23 Jul '17 Blasters[5],Semi Blasters[5],Semi Skilled[6],Sprayer[4]
Skilled[6],Sprayer[4]
39 IDLE Due to industrial hygienic test 1 day 24 Jul '17 24 Jul '17 Blasters[4],Semi Blasters[4],Semi Skilled[4],Sprayer[2]
Skilled[4],Sprayer[2]
40 IDLE Due to industrial hygienic test 1 day 25 Jul '17 25 Jul '17 Semi Skilled,Sprayer[7] Semi Skilled,Sprayer[7]

41 Surface Preparation and priming of roof 1 day 26 Jul '17 26 Jul '17 Blasters[3],Sprayer[2],Semi Skilled[6] Blasters[3],Sprayer[2],Semi Skilled[6]
42 IDLE Due to industrial hygienic test 1 day 27 Jul '17 27 Jul '17 Semi Skilled[13],Chargehand Semi Skilled[13],Chargehand
43 Surface Preparation and priming of roof 4 days 29 Jul '17 01 Aug '17 Blasters[3],Sprayer[2],Semi Skilled[6] Blasters[3],Sprayer[2],Semi Skilled[6]
44 Surface Preparation and priming of shell and 5 days 02 Aug '17 07 Aug '17 Blasters[10],Sprayer[3],Semi Blasters[10],Sprayer[3],Semi Skilled[10]
structures Skilled[10]
45 TANK # 20-3.5 HRS IDLE DUE TO RT TEST 1 day 08 Aug '17 08 Aug '17 Blasters[5],Semi Skilled[3] Blasters[5],Semi Skilled[3]
46 Surface Preparation and priming of shell and 3 days 09 Aug '17 12 Aug '17 Blasters[10],Sprayer[3],Semi Blasters[10],Sprayer[3],Semi Skilled[10]
structures Skilled[10]
47 Cleaning and Touch up 4 days 13 Aug '17 16 Aug '17 Semi Skilled[8] Semi Skilled[8]
48 1st stripe coat and inspection 4 days 17 Aug '17 21 Aug '17 Semi Skilled[8] Semi Skilled[8]
49 Final coat, touch up and inspection 5 days 22 Aug '17 27 Aug '17 Sprayer[2],Semi Skilled[7] Sprayer[2],Semi Skilled[7]
50 230TK10060 41 days 15 Jul '17 30 Aug '17
51 Scaffolding Modification and encapsulation 9 days 15 Jul '17 24 Jul '17
52 Modification 4 days 15 Jul '17 18 Jul '17
53 Sheeting 5 days 19 Jul '17 24 Jul '17
54 Blasting and Painting 30 days 27 Jul '17 30 Aug '17
55 Washing 1 day 27 Jul '17 27 Jul '17
56 Surface Preparation and priming of roof 2 days 02 Aug '17 03 Aug '17 Blasters[3],Sprayer,Semi Skilled[4] Blasters[3],Sprayer,Semi Skilled[4]
57 Surface Preparation and priming of shell and 7 days 05 Aug '17 12 Aug '17 Blasters[8],Sprayer[2],Semi Blasters[8],Sprayer[2],Semi Skilled[7]
structures Skilled[7]
58 No Access for garnet shifting 1 day 04 Aug '17 04 Aug '17 Semi Skilled[5] Semi Skilled[5]
59 TANK # 60-2 HRS IDLE DUE TO RT TEST 1 day 06 Aug '17 06 Aug '17 Blasters[6],Semi Skilled[3] Blasters[6],Semi Skilled[3]
60 Cleaning and Touch up 1 day 13 Aug '17 13 Aug '17 Semi Skilled[9] Semi Skilled[9]
61 1st stripe coat and inspection 2 days 14 Aug '17 15 Aug '17 Semi Skilled[9] Semi Skilled[9]
62 Final coat 2 days 16 Aug '17 17 Aug '17 Sprayer[4],Semi Skilled[7] Sprayer[4],Semi Skilled[7]
63 Final coat, touch up and inspection 7 days 23 Aug '17 30 Aug '17 Sprayer[4],Semi Skilled[7] Sprayer[4],Semi Skilled[7]
64 330TK10510A 21 days 12 Aug '17 04 Sep '17
65 Scaffolding Modification and encapsulation 6 days 12 Aug '17 17 Aug '17
66 Modification 3 days 12 Aug '17 14 Aug '17
67 Sheeting 3 days 15 Aug '17 17 Aug '17
68 Blasting and Painting 15 days 19 Aug '17 04 Sep '17
69 Surface Preparation and priming of roof 2 days 19 Aug '17 20 Aug '17 Blasters[2],Sprayer,Semi Skilled[3] Blasters[2],Sprayer,Semi Skilled[3]
70 Surface Preparation and priming of shell and 4 days 21 Aug '17 24 Aug '17 Sprayer[2],Semi Sprayer[2],Semi Skilled[7],Blasters[8]
structures Skilled[7],Blasters[8]
71 Cleaning and Touch up 3 days 26 Aug '17 28 Aug '17 Semi Skilled[7] Semi Skilled[7]
72 1st stripe coat and inspection 3 days 29 Aug '17 31 Aug '17 Semi Skilled[7] Semi Skilled[7]
73 Final coat, touch up and inspection 3 days 02 Sep '17 04 Sep '17 Sprayer[2],Semi Skilled[7] Sprayer[2],Semi Skilled[7]
74 230TK10050 28 days 14 Aug '17 14 Sep '17
75 Scaffolding Modification and encapsulation 8 days 14 Aug '17 22 Aug '17
76 Modification 4 days 14 Aug '17 17 Aug '17

Page 2
ID Task Name Duration Start Finish Resource Names Remarks 24 Jun '17 15 Jul '17 05 Aug '17 26 Aug '17 16 Sep '17 07 Oct '17 28 Oct '17 18 Nov '17 09 Dec '17 30 Dec '17
26 04 12 20 28 05 13 21 29 06 14 22 30 08 16 24 01 09 17 25 03 11 19 27 04
77 Sheeting 4 days 19 Aug '17 22 Aug '17
78 Blasting and Painting 20 days 23 Aug '17 14 Sep '17
79 Surface Preparation and priming of roof 2 days 23 Aug '17 24 Aug '17 Blasters[3],Sprayer,Semi Skilled[5] Blasters[3],Sprayer,Semi Skilled[5]
80 Surface Preparation and priming of shell and 6 days 26 Aug '17 31 Aug '17 Blasters[8],Sprayer[2],Semi Blasters[8],Sprayer[2],Semi Skilled[7]
structures Skilled[7]
81 Cleaning and Touch up 4 days 02 Sep '17 05 Sep '17 Semi Skilled[6] Semi Skilled[6]
82 1st stripe coat and inspection 4 days 06 Sep '17 10 Sep '17 Semi Skilled[6] Semi Skilled[6]
83 Final coat, touch up and inspection 4 days 11 Sep '17 14 Sep '17 Sprayer[2],Semi Skilled[5] Sprayer[2],Semi Skilled[5]
84 250TK10030 67 days 15 Aug '17 31 Oct '17
85 Scaffolding Modification and encapsulation 8 days 15 Aug '17 23 Aug '17
86 Modification 5 days 15 Aug '17 20 Aug '17
87 Sheeting 3 days 21 Aug '17 23 Aug '17
88 Blasting and Painting of Shell 14 days 24 Aug '17 09 Sep '17
89 Surface Preparation and priming of shell and 5 days 24 Aug '17 29 Aug '17 Blasters[8],Sprayer[2],Semi Blasters[8],Sprayer[2],Semi Skilled[7]
structures Skilled[7]
90 Cleaning and Touch up 3 days 30 Aug '17 02 Sep '17 Semi Skilled[6] Semi Skilled[6]
91 1st stripe coat and inspection 3 days 03 Sep '17 05 Sep '17 Semi Skilled[6] Semi Skilled[6]
92 Final coat, touch up and inspection 3 days 06 Sep '17 09 Sep '17 Sprayer[2],Semi Skilled[5] Sprayer[2],Semi Skilled[5]
93 Blasting and Painting of Roof 10 days 21 Oct '17 31 Oct '17
94 Surface Preparation and priming of roof 2 days 21 Oct '17 22 Oct '17 Blasters[6],Sprayer[3],Semi Skilled[6] Blasters[6],Sprayer[3],Semi Skilled[6]
95 Cleaning and Touch up 2 days 23 Oct '17 24 Oct '17 Semi Skilled[6] Semi Skilled[6]
96 1st stripe coat and inspection 2 days 25 Oct '17 26 Oct '17 Semi Skilled[6] Semi Skilled[6]
97 Final coat, touch up and inspection 4 days 28 Oct '17 31 Oct '17 Sprayer[2],Semi Skilled[5] Sprayer[2],Semi Skilled[5]
98 330TK10510B 24 days 19 Aug '17 14 Sep '17
99 Scaffolding Modification and encapsulation 9 days 19 Aug '17 28 Aug '17
100 Modification 5 days 19 Aug '17 23 Aug '17
101 Sheeting 4 days 24 Aug '17 28 Aug '17
102 Blasting and Painting 15 days 29 Aug '17 14 Sep '17
103 Surface Preparation and priming of roof 2 days 29 Aug '17 30 Aug '17 Blasters[3],Sprayer,Semi Skilled[4] Blasters[3],Sprayer,Semi Skilled[4]
104 Surface Preparation and priming of shell and 4 days 31 Aug '17 04 Sep '17 Blasters[6],Sprayer[2],Semi Blasters[6],Sprayer[2],Semi Skilled[7]
structures Skilled[7]
105 Cleaning and Touch up 3 days 05 Sep '17 07 Sep '17 Semi Skilled[8] Semi Skilled[8]
106 1st stripe coat and inspection 3 days 09 Sep '17 11 Sep '17 Semi Skilled[8] Semi Skilled[8]
107 Final coat, touch up and inspection 3 days 12 Sep '17 14 Sep '17 Sprayer[2],Semi Skilled[7] Sprayer[2],Semi Skilled[7]
108 250TK10010 62 days 20 Aug '17 30 Oct '17
109 Scaffolding Modification and encapsulation 8 days 20 Aug '17 28 Aug '17
110 Modification 4 days 20 Aug '17 23 Aug '17
111 Sheeting 4 days 24 Aug '17 28 Aug '17
112 Blasting and Painting of shell 14 days 29 Aug '17 13 Sep '17
113 Surface Preparation and priming of shell and 4 days 29 Aug '17 02 Sep '17 Blasters[11],Sprayer[3],Semi Blasters[11],Sprayer[3],Semi Skilled[10]
structures Skilled[10]
114 Cleaning and Touch up 3 days 03 Sep '17 05 Sep '17 Semi Skilled[11] Semi Skilled[11]
115 1st stripe coat and inspection 3 days 06 Sep '17 09 Sep '17 Semi Skilled[11] Semi Skilled[11]
116 Final coat, touch up and inspection 4 days 10 Sep '17 13 Sep '17 Sprayer[3],Semi Skilled[8] Sprayer[3],Semi Skilled[8]
117 Blasting and Painting of Roof 10 days 19 Oct '17 30 Oct '17
118 Surface Preparation and priming of roof 2 days 19 Oct '17 21 Oct '17 Blasters[4],Sprayer[2],Semi Skilled[6] Blasters[4],Sprayer[2],Semi Skilled[6]
119 Cleaning and Touch up 2 days 22 Oct '17 23 Oct '17 Semi Skilled[8] Semi Skilled[8]
120 1st stripe coat and inspection 3 days 24 Oct '17 26 Oct '17 Semi Skilled[8] Semi Skilled[8]
121 Final coat, touch up and inspection 3 days 28 Oct '17 30 Oct '17 Sprayer[3],Semi Skilled[8] Sprayer[3],Semi Skilled[8]
122 230TK10010 22 days 28 Aug '17 21 Sep '17
123 Scaffolding Modification and encapsulation 7 days 28 Aug '17 04 Sep '17
124 Modification 4 days 28 Aug '17 31 Aug '17

Page 3
ID Task Name Duration Start Finish Resource Names Remarks 24 Jun '17 15 Jul '17 05 Aug '17 26 Aug '17 16 Sep '17 07 Oct '17 28 Oct '17 18 Nov '17 09 Dec '17 30 Dec '17
26 04 12 20 28 05 13 21 29 06 14 22 30 08 16 24 01 09 17 25 03 11 19 27 04
125 Sheeting 3 days 02 Sep '17 04 Sep '17
126 Blasting and Painting Shell 15 days 05 Sep '17 21 Sep '17
127 Surface Preparation and priming of roof 2 days 05 Sep '17 06 Sep '17 Blasters[3],Sprayer[2],Semi Skilled[5] Blasters[3],Sprayer[2],Semi Skilled[5]
128 Surface Preparation and priming of shell and 4 days 07 Sep '17 11 Sep '17 Blasters[13],Sprayer[4],Semi Blasters[13],Sprayer[4],Semi Skilled[12]
structures Skilled[12]
129 Cleaning and Touch up 3 days 12 Sep '17 14 Sep '17 Semi Skilled[8] Semi Skilled[8]
130 1st stripe coat and inspection 3 days 16 Sep '17 18 Sep '17 Semi Skilled[8] Semi Skilled[8]
131 Final coat, touch up and inspection 3 days 19 Sep '17 21 Sep '17 Sprayer[2],Semi Skilled[5] Sprayer[2],Semi Skilled[5]
132 260TK10040 63 days 04 Sep '17 15 Nov '17
133 Scaffolding Modification and encapsulation 10 days 04 Sep '17 14 Sep '17
134 Modification 6 days 04 Sep '17 10 Sep '17
135 Sheeting 4 days 11 Sep '17 14 Sep '17
136 Blasting and Painting Shell 12 days 16 Sep '17 28 Sep '17
137 Surface Preparation and priming of shell and 4 days 16 Sep '17 19 Sep '17 Blasters[12],Sprayer[4],Semi Blasters[12],Sprayer[4],Semi Skilled[16]
structures Skilled[16]
138 Cleaning and Touch up 2 days 20 Sep '17 21 Sep '17 Semi Skilled[15] Semi Skilled[15]
139 1st stripe coat and inspection 3 days 23 Sep '17 25 Sep '17 Semi Skilled[15] Semi Skilled[15]
140 Final coat, touch up and inspection 3 days 26 Sep '17 28 Sep '17 Sprayer[4],Semi Skilled[12] Sprayer[4],Semi Skilled[12]
141 Blasting and Painting Roof 10 days 05 Nov '17 15 Nov '17
142 Surface Preparation and priming of roof 2 days 05 Nov '17 06 Nov '17 Blasters[4],Sprayer[2],Semi Skilled[6] Blasters[4],Sprayer[2],Semi Skil
143 Cleaning and Touch up 2 days 07 Nov '17 08 Nov '17 Semi Skilled[15] Semi Skilled[15]
144 1st stripe coat and inspection 3 days 09 Nov '17 12 Nov '17 Semi Skilled[15] Semi Skilled[15]
145 Final coat, touch up and inspection 3 days 13 Nov '17 15 Nov '17 Sprayer[4],Semi Skilled[12] Sprayer[4],Semi Skilled[12]
146 260TK10020 65 days 06 Sep '17 20 Nov '17
147 Scaffolding Modification and encapsulation 10 days 06 Sep '17 17 Sep '17
148 Modification 6 days 06 Sep '17 12 Sep '17
149 Sheeting 4 days 13 Sep '17 17 Sep '17
150 Blasting and Painting Shell 12 days 18 Sep '17 01 Oct '17
151 Surface Preparation and priming of shell and 4 days 18 Sep '17 21 Sep '17 Blasters[14],Sprayer[3],Semi Blasters[14],Sprayer[3],Semi Skilled[12]
structures Skilled[12]
152 Cleaning and Touch up 2 days 23 Sep '17 24 Sep '17 Semi Skilled[13] Semi Skilled[13]
153 1st stripe coat and inspection 3 days 25 Sep '17 27 Sep '17 Semi Skilled[13] Semi Skilled[13]
154 Final coat, touch up and inspection 3 days 28 Sep '17 01 Oct '17 Sprayer[4],Semi Skilled[12] Sprayer[4],Semi Skilled[12]
155 Blasting and Painting Roof 10 days 09 Nov '17 20 Nov '17
156 Surface Preparation and priming of roof 2 days 09 Nov '17 11 Nov '17 Blasters[6],Sprayer[2],Semi Skilled[6] Blasters[6],Sprayer[2],Semi Sk
157 Cleaning and Touch up 2 days 12 Nov '17 13 Nov '17 Semi Skilled[10] Semi Skilled[10]
158 1st stripe coat and inspection 3 days 14 Nov '17 16 Nov '17 Semi Skilled[10] Semi Skilled[10]
159 Final coat, touch up and inspection 3 days 18 Nov '17 20 Nov '17 Sprayer[4],Semi Skilled[8] Sprayer[4],Semi Skilled[8]
160 250TK10040 16 days 09 Sep '17 26 Sep '17
161 Scaffolding Modification and encapsulation 6 days 09 Sep '17 14 Sep '17
162 Modification 3 days 09 Sep '17 11 Sep '17
163 Sheeting 3 days 12 Sep '17 14 Sep '17
164 Blasting and Painting 10 days 16 Sep '17 26 Sep '17
165 Surface Preparation and priming of roof 1 day 16 Sep '17 16 Sep '17 Blasters[6],Sprayer[2],Semi Skilled[5] Blasters[6],Sprayer[2],Semi Skilled[5]
166 Surface Preparation and priming of shell and 3 days 17 Sep '17 19 Sep '17 Blasters[13],Sprayer[4],Semi Blasters[13],Sprayer[4],Semi Skilled[11]
structures Skilled[11]
167 Cleaning and Touch up 2 days 20 Sep '17 21 Sep '17 Semi Skilled[6] Semi Skilled[6]
168 1st stripe coat and inspection 2 days 23 Sep '17 24 Sep '17 Semi Skilled[6] Semi Skilled[6]
169 Final coat, touch up and inspection 2 days 25 Sep '17 26 Sep '17 Sprayer[4],Semi Skilled[7] Sprayer[4],Semi Skilled[7]
170 250TK10050 17 days 13 Sep '17 02 Oct '17
171 Scaffolding Modification and encapsulation 6 days 13 Sep '17 19 Sep '17
172 Modification 3 days 13 Sep '17 16 Sep '17

Page 4
ID Task Name Duration Start Finish Resource Names Remarks 24 Jun '17 15 Jul '17 05 Aug '17 26 Aug '17 16 Sep '17 07 Oct '17 28 Oct '17 18 Nov '17 09 Dec '17 30 Dec '17
26 04 12 20 28 05 13 21 29 06 14 22 30 08 16 24 01 09 17 25 03 11 19 27 04
173 Sheeting 3 days 17 Sep '17 19 Sep '17
174 Blasting and Painting 11 days 20 Sep '17 02 Oct '17
175 Surface Preparation and priming of roof 1 day 20 Sep '17 20 Sep '17 Blasters[6],Sprayer[2],Semi Skilled[8] Blasters[6],Sprayer[2],Semi Skilled[8]
176 Surface Preparation and priming of shell and 4 days 21 Sep '17 25 Sep '17 Blasters[7],Sprayer[2],Semi Blasters[7],Sprayer[2],Semi Skilled[7]
structures Skilled[7]
177 Cleaning and Touch up 2 days 26 Sep '17 27 Sep '17 Semi Skilled[9] Semi Skilled[9]
178 1st stripe coat and inspection 2 days 28 Sep '17 30 Sep '17 Semi Skilled[9] Semi Skilled[9]
179 Final coat, touch up and inspection 2 days 01 Oct '17 02 Oct '17 Sprayer[4],Semi Skilled[7] Sprayer[4],Semi Skilled[7]
180 230TK10030 27 days 14 Sep '17 15 Oct '17
181 Scaffolding Modification and encapsulation 7 days 14 Sep '17 21 Sep '17
182 Modification 4 days 14 Sep '17 18 Sep '17
183 Sheeting 3 days 19 Sep '17 21 Sep '17
184 Blasting and Painting 20 days 23 Sep '17 15 Oct '17
185 Surface Preparation and priming of roof 2 days 23 Sep '17 24 Sep '17 Blasters[3],Sprayer[2],Semi Skilled[5] Blasters[3],Sprayer[2],Semi Skilled[5]
186 Surface Preparation and priming of shell and 6 days 25 Sep '17 01 Oct '17 Blasters[9],Sprayer,Semi Skilled[7] Blasters[9],Sprayer,Semi Skilled[7]
structures
187 Cleaning and Touch up 4 days 02 Oct '17 05 Oct '17 Semi Skilled[7] Semi Skilled[7]
188 1st stripe coat and inspection 4 days 07 Oct '17 10 Oct '17 Semi Skilled[7] Semi Skilled[7]
189 Final coat, touch up and inspection 4 days 11 Oct '17 15 Oct '17 Sprayer[2],Semi Skilled[5] Sprayer[2],Semi Skilled[5]
190 321TK10030 27 days 19 Sep '17 19 Oct '17
191 Scaffolding Modification and encapsulation 7 days 19 Sep '17 26 Sep '17
192 Modification 4 days 19 Sep '17 23 Sep '17
193 Sheeting 3 days 24 Sep '17 26 Sep '17
194 Blasting and Painting 20 days 27 Sep '17 19 Oct '17
195 Surface Preparation and priming of roof 2 days 27 Sep '17 28 Sep '17 Blasters[4],Sprayer,Semi Skilled[3] Blasters[4],Sprayer,Semi Skilled[3]
196 Surface Preparation and priming of shell and 4 days 30 Sep '17 03 Oct '17 Blasters[4],Sprayer,Semi Skilled[3] Blasters[4],Sprayer,Semi Skilled[3]
structures
197 Cleaning and Touch up 5 days 04 Oct '17 09 Oct '17 Semi Skilled[4] Semi Skilled[4]
198 1st stripe coat and inspection 4 days 10 Oct '17 14 Oct '17 Semi Skilled[4] Semi Skilled[4]
199 Final coat, touch up and inspection 5 days 15 Oct '17 19 Oct '17 Sprayer[4],Semi Skilled[4] Sprayer[4],Semi Skilled[4]
200 240TK10020A 22 days 21 Sep '17 16 Oct '17
201 Scaffolding Modification and encapsulation 7 days 21 Sep '17 28 Sep '17
202 Modification 4 days 21 Sep '17 25 Sep '17
203 Sheeting 3 days 26 Sep '17 28 Sep '17
204 Blasting and Painting 15 days 30 Sep '17 16 Oct '17
205 Surface Preparation and priming of roof 2 days 30 Sep '17 01 Oct '17 Blasters[3],Sprayer[2],Semi Skilled[5] Blasters[3],Sprayer[2],Semi Skilled[5]
206 Surface Preparation and priming of shell and 4 days 02 Oct '17 05 Oct '17 Blasters[13],Sprayer[2],Semi Blasters[13],Sprayer[2],Semi Skilled[10]
structures Skilled[10]
207 Cleaning and Touch up 3 days 07 Oct '17 09 Oct '17 Semi Skilled[10] Semi Skilled[10]
208 1st stripe coat and inspection 3 days 10 Oct '17 12 Oct '17 Semi Skilled[10] Semi Skilled[10]
209 Final coat, touch up and inspection 3 days 14 Oct '17 16 Oct '17 Sprayer[2],Semi Skilled[8] Sprayer[2],Semi Skilled[8]
210 260TK10010 25 days 26 Sep '17 24 Oct '17
211 Scaffolding Modification and encapsulation 10 days 26 Sep '17 07 Oct '17
212 Modification 6 days 26 Sep '17 02 Oct '17
213 Sheeting 4 days 03 Oct '17 07 Oct '17
214 Blasting and Painting 15 days 08 Oct '17 24 Oct '17
215 Surface Preparation and priming of roof 2 days 08 Oct '17 09 Oct '17 Blasters[4],Sprayer[2],Semi Skilled[6] Blasters[4],Sprayer[2],Semi Skilled[6]
216 Surface Preparation and priming of shell and 4 days 10 Oct '17 14 Oct '17 Blasters[10],Sprayer[3],Semi Blasters[10],Sprayer[3],Semi Skilled[11]
structures Skilled[11]
217 Cleaning and Touch up 3 days 15 Oct '17 17 Oct '17 Semi Skilled[14] Semi Skilled[14]
218 1st stripe coat and inspection 3 days 18 Oct '17 21 Oct '17 Semi Skilled[14] Semi Skilled[14]
219 Final coat, touch up and inspection 3 days 22 Oct '17 24 Oct '17 Sprayer[4],Semi Skilled[11] Sprayer[4],Semi Skilled[11]

Page 5
ID Task Name Duration Start Finish Resource Names Remarks 24 Jun '17 15 Jul '17 05 Aug '17 26 Aug '17 16 Sep '17 07 Oct '17 28 Oct '17 18 Nov '17 09 Dec '17 30 Dec '17
26 04 12 20 28 05 13 21 29 06 14 22 30 08 16 24 01 09 17 25 03 11 19 27 04
220 240TK10020B 22 days 27 Sep '17 22 Oct '17
221 Scaffolding Modification and encapsulation 7 days 27 Sep '17 04 Oct '17
222 Modification 4 days 27 Sep '17 01 Oct '17
223 Sheeting 3 days 02 Oct '17 04 Oct '17
224 Blasting and Painting 15 days 05 Oct '17 22 Oct '17
225 Surface Preparation and priming of roof 2 days 05 Oct '17 07 Oct '17 Blasters[3],Sprayer[2],Semi Skilled[5] Blasters[3],Sprayer[2],Semi Skilled[5]
226 Surface Preparation and priming of shell and 4 days 08 Oct '17 11 Oct '17 Blasters[13],Sprayer[4],Semi Blasters[13],Sprayer[4],Semi Skilled[12]
structures Skilled[12]
227 Cleaning and Touch up 3 days 12 Oct '17 15 Oct '17 Semi Skilled[8] Semi Skilled[8]
228 1st stripe coat and inspection 3 days 16 Oct '17 18 Oct '17 Semi Skilled[8] Semi Skilled[8]
229 Final coat, touch up and inspection 3 days 19 Oct '17 22 Oct '17 Sprayer[2],Semi Skilled[8] Sprayer[2],Semi Skilled[8]
230 250TK10020 23 days 30 Sep '17 25 Oct '17
231 Scaffolding Modification and encapsulation 8 days 30 Sep '17 08 Oct '17
232 Modification 4 days 30 Sep '17 03 Oct '17
233 Sheeting 4 days 04 Oct '17 08 Oct '17
234 Blasting and Painting 15 days 09 Oct '17 25 Oct '17
235 Surface Preparation and priming of roof 2 days 09 Oct '17 10 Oct '17 Blasters[6],Sprayer[2],Semi Skilled[5] Blasters[6],Sprayer[2],Semi Skilled[5]
236 Surface Preparation and priming of shell and 4 days 11 Oct '17 15 Oct '17 Blasters[11],Sprayer[3],Semi Blasters[11],Sprayer[3],Semi Skilled[10]
structures Skilled[10]
237 Cleaning and Touch up 3 days 16 Oct '17 18 Oct '17 Semi Skilled[8] Semi Skilled[8]
238 1st stripe coat and inspection 3 days 19 Oct '17 22 Oct '17 Semi Skilled[8] Semi Skilled[8]
239 Final coat, touch up and inspection 3 days 23 Oct '17 25 Oct '17 Sprayer[2],Semi Skilled[7] Sprayer[2],Semi Skilled[7]
240 260TK10030 27 days 03 Oct '17 02 Nov '17
241 Scaffolding Modification and encapsulation 10 days 03 Oct '17 14 Oct '17
242 Modification 6 days 03 Oct '17 09 Oct '17
243 Sheeting 4 days 10 Oct '17 14 Oct '17
244 Blasting and Painting 17 days 15 Oct '17 02 Nov '17
245 Surface Preparation and priming of roof 2 days 15 Oct '17 16 Oct '17 Blasters[4],Sprayer[2],Semi Skilled[6] Blasters[4],Sprayer[2],Semi Skilled[6]
246 Surface Preparation and priming of shell and 4 days 17 Oct '17 21 Oct '17 Blasters[12],Sprayer[3],Semi Blasters[12],Sprayer[3],Semi Skilled[1
structures Skilled[16]
247 Cleaning and Touch up 3 days 22 Oct '17 24 Oct '17 Semi Skilled[14] Semi Skilled[14]
248 1st stripe coat and inspection 4 days 25 Oct '17 29 Oct '17 Semi Skilled[14] Semi Skilled[14]
249 Final coat, touch up and inspection 4 days 30 Oct '17 02 Nov '17 Sprayer[4],Semi Skilled[11] Sprayer[4],Semi Skilled[11]

Page 6