Id Activity Duration Start Finish 8 oct '17 15 oct '17 22 oct '17 29 oct '17

LMX J V S D LMX J V S D LMX J V S D LMX J V S D


1 ModuleNumber3 11days 24/10/17 03/11/17

2 Fitandweldstiffeners4walls 2days 24/10/17 25/10/17

3 Erect4walls 1day 26/10/17 26/10/17

4 Fitandweldhopper 1day 27/10/17 27/10/17

5 Weldbaghousecomplete 1day 29/10/17 29/10/17

6 Sandblast 2days 30/10/17 31/10/17

7 Painting 2days 01/11/17 02/11/17

8 Shipping 1day 03/11/17 03/11/17

Project: Baghouses project, O

Date; 24/10/17