You are on page 1of 4

Project Name : Mivida

Project Manager :Turner


Main Consultant :EHAF Consulting Engineers
Main Contractor : Alshafar Genral Contracting

Mivida PROJECT

1.1/1.DAILY CONSTRUCTION REPORT


Date: December 15, 2020
S S M T W TH F
Day: a
Package: 72

Contractor: Al Shafar General Contracting


Report No. 508
Contract: MIVIDA PK72- Parcel 10
Work in Progress
Location Date
Activity # Description of Work % Comp. Remarks
Bld Flr Started
ACT#1 Wooden Doors Installation 1 GF 9/Jul/2017 50%

ACT#2 HDF Flooring 1 1st 22/Jun/2017 50%

ACT#3 Painting 2nd Coat 1 2nd 28/Jun/2017 50%

ACT#4 Stairs & Shafts Painting 1 STR 7/May/2017 100%

ACT#5 Thermal Proofing 1 ROOF 28/Mar/2017 100%

ACT#7 Suspended Ceiling Final fix 2 1st 9/Jul/2017 50%

ACT#8 Cement Tiles for HDF 2 4th 25/May/2017 100%

ACT#9 Ceramic Works 2 4th 10/Jun/2017 80%

ACT#10 Roof Plastering 2 ROOF 1/Jul/2017 60%

ACT#11 Access Shaft & Steel ladder 3 ROOF 9/Jun/2017 70%

ACT#12 Wooden Doors Installation 3 4th 18/May/2017 85%

ACT#13 Doors Hardware 3 4th 11/Jun/2017 30%

ACT#14 Painting 2nd Coat 3 4th 22/Jun/2017 80%

ACT#15 Clay Roof Tiles 4 Roof 18/Jun/2017 20%

ACT#16 Suspended Ceiling 1st Fix 4 1st 29/Apr/2017 100%

ACT#17 Stairs Marble 4 STR 10/May/2017 90%

ACT#18 Stairs & Shafts Painting 5 2nd 12/May/2017 65%

ACT#19 Aluminum Doors Installation 5 2nd 14/Jun/2017 80%

ACT#20 Painting 2nd Coat 5 2nd 15/Jun/2017 60%

ACT#21 Thermal Proofing 5 ROOF 9/May/2017 50%

ACT#22 Wooden Doors Installation 6 1st 17/Jul/2017 80%

ACT#23 Painting 2nd Coat 6 2nd 9/Jun/2017 60%

ACT#24 Vertical Expansion 6 ELV1 18/Jun/2017 100%

ACT#25 Access Shaft & Steel ladder 7 ROOF 29/May/2017 100%

ACT#26 External painting final coat 7 ELV4 16/Jul/2017 80%

ACT#27 Painting 1st Coat 7 4th 15/Mar/2017 100%

ACT#28 Marble Flooring 8 4th 18/Apr/2017 90%

ACT#29 Suspended Ceiling Final fix 8 2nd 19/Jun/2017 50%

ACT#30 Ceramic Wall Installation 8 4th 4/Apr/2017 90%

ACT#31 Metal Doors 8 4th 25/May/2017 100%

ACT#32 Painting Final Coat 8 ELV1 19/Jun/2017 100%

ACT#33 Painting 2nd Coat 9 4th 7/Jun/2017 80%

ACT#34 Doors Hardware 9 2nd 26/Jun/2017 70%

ACT#35 VL Expansion Installation 9 ElV 1 18/May/2017 100%

ACT#36 Sloped Concrete 10 ROOF 8/Apr/2017 100%

ACT#37 Ceramic Walls Installation 10 4th 8/Jun/2017 50%

ACT#38 Cement Tiles for HDF 10 GF 18/May/2017 100%

ACT#39 Marble Flooring 10 4th 6/Jun/2017 100%

ACT#40 Aluminum Windows Installation 10 ELV1 16/Apr/2017 45%

CONTRACTOR'S SIGNATURE-------------------------------------
Project Name : Mivida
Project Manager :Turner
Main Consultant :EHAF Consulting Engineers
Main Contractor : Alshafar Genral Contracting

MIVIDA PROJECT

1.1/2.DAILY CONSTRUCTION REPORT


Date: December 15, 2020

S S M T W TH F
Day: a
Package : 72

Contractor: Al Shafar General Contracting Report No.


508
Contract: MIVIDA PK72- Parcel 10

Manpower available at site


Staff Labor Daily Cum
Occupation Occupation
Contract Actual Skilled Unskilled Total Total
Project Manager 1 Carpenter 6
Construction Manager 2 Rebar Fixers
Planning Engineer 2 Carpenter (Helper) 7
Civil Engineer 9 Structural Steel 9
Architect 2 Welder 3
MEP Maneger 1 Scaffolding 45
Mechanical Engineer (Plum.) 1 Joiner
Mechanical Engineer (HVAC) Marble Fixer 49
Electrical Manager 1 Ceramic 42
Electrical Engineer (MEP) 2 Hashma Fixer 38
QS Eng 1 Store 8
Technical Manager 1 Precast
Technical Engineer 3 Aluminum 36
Accountant 1 Painter 69
HR coordinator 1 False Ceiling 59
Time Keeper 3 Glazing
DC 5 Plasterer(s) 45
SafetyManeger 1 Plumber 67
Assistant Safety Officer 7 Plumber helper 68
Q.C. Manager 1 HVAC 56
Q.C. Engineer 2 Electrician 89
Secretary / Clerk 1 Electrician (helper) 21 2
General Foreman 1 Labours 112
Civil Foreman 10 Builder 20 8
Electrical Foreman 1 Smith
Mechanical Foreman(Plum) 1 Plasterer(helper)
Mechanical Foreman(HVAC) Builder (helper)
Surveyors 5 Concrete Finsher 15
Assistant Surveyor 3 CEL Lab 4
Drivers 3
Machine Operators 2
Others (Specify)
Store keeper 2
Marine Engineer
Site Supervision:

Total 868 10
Total 878

Total 76

CONTRACTOR'S SIGNATURE-------------------------------------
Project Name : Mivida
Project Manager :Turner
Main Consultant :EHAF Consulting Engineers
Main Contractor : Alshafar Genral Contracting

MIVIDA PROJECT

1.1/3.DAILY CONSTRUCTION REPORT


Date: December 15, 2020
a a a

S S M T W TH F
Day
a
Package: 72
Contractor: Al Shafar General Contracting Report No.
508
Contract: MIVIDA PK72- Parcel 10
Temp. °C Weather
0 - 30 30 - 40 40 - 50 50 up Bright Sun Clear Overcast Rain Dust

Sea Humidity Wind


Still Moder. High Dry Moder. Humid Still Moder. High

Machinery Used

Compressor (s) Hoist (s) Trailer (s) Vibrator (s) Welding Traffic Pickup(s)
Machine (s) Car(s)
Size

No. On Site 3 3
Down Time

Dumper(s) Level(s) Total Station(s) Compactor(s) Grader(s) Roller(s) Concrete


Pump
Size

No. On Site 2 2 2
Down Time

Bending Wood/Marble Welding Bobcat(s) Generator(s)


Shovel Telescopic for Kelfet
Machine(s) Brick Cutter(s) Machines
Size

No. On Site 1 2 5 2

Down Time

Tower Crane(s) Crane (s) Backhoe(s) Backhoe (s) Transmit Dump Truck(s) 6-Wheel
With Jack Concrete Mixer Truck (s)
Size

No. On Site 1 1 4

Down Time

Material & Equipments Delivered to Site


Description Quantity Units Origin / Manufacturer

CONTRACTOR'S SIGNATURE-------------------------------------
MIVIDA PROJECT

1.1/4.DAILY CONSTRUCTION REPORT

Date:
S S M T W TH F

Package #: 72 Day

Contracto Al Shafar General Contracting Report No.

Contract: MIVIDA PK72- Parcel 10


XXXX
Manpower Allocation
Location Manpower
Activity # Description of Work Remarks
Bldg Flr Area Group# Craft Hours

Remarks

DATE:

You might also like