China Petroleum Pipeline Bureau (Sudan)

中国石油天然气管道局(苏丹)

Project Planning
Package
CPP

Provision of Pipeline Repair (Phase II)

Contract No.: PDOC/32/14-1303C Document No.: PRPII-PM-004 Page: 1 OF 2

Project Planning Package


For Provision of Pipeline Repair (Phase II) Project

A 5/02/2017 He Li Xiao Xu Tian Xuesong Project Manager Project Manager

PMC Client
Rev. Date Prepared by Reviewed by Approved by
Approved by Approved by
China Petroleum Pipeline Bureau (Sudan)
中国石油天然气管道局(苏丹)

Project Execution Plan


CPP
Provision of Pipeline Repair (Phase II)
Contract No.: PDOC/32/14-1303C

Document No.: PRPII-PM-004 Rev. A Page: 2 OF 2

Document Attachment No. Document Attachment Title REV. Attached


1 Updated Project Execution Sched D
ule
2 Work breakdown Structure A

Remark:
China Petroleum Pipeline Bureau (Sudan)

中国石油天然气管道局(苏丹)

PROJECT EXECUTION SCHEDULE


For
PROVISION OF PIPELINE REPAIR
PHASE II
ID WBS Task Name Duration Start Finish 2016 September 2017 May
September Beginning January Beginning May Beginning September Beginning January Beginning
7/3 8/28 10/23 12/18 2/12 4/9 6/4 7/30 9/24 11/19 1/14
1
2 P1 Enginerring 122 days '16 Sep 1 '16 Dec 31
3 P1.1 Establish the project team 7 days '16 Sep 1 '16 Sep 7

4 P1.2 Design Type-B mechanical 10 days '16 Sep 14 '16 Sep 23


sleeve & choose the
material of sleeve

5 P1.3 PMC review and approve the 38 days '16 Oct 7 '16 Nov 13
type-B sleeve drawing

6 P1.4 PMC review and aprrove the 74 days '16 Oct 18 '16 Dec 30
Preliminary WPS
7 P1.5 PMC review and approve WQT 94 days '16 Sep 28 '16 Dec 30
proposal
8 P1.6 PMC review and approve PEP 90 days '16 Oct 2 '16 Dec 30

9 P1.7 PMC reviw and approve the 102 days '16 Sep 21 '16 Dec 31
data sheets of matrials

10 P1.8 PMC review and approve 51 days '16 Nov 10 '16 Dec 30
other project documents
11 P2 Procuement 260 days '16 Sep 12 '17 May 29
12 P2.1 Type-B sleeve 92 days '17 Jan 28 '17 May 29
13 P2.1.1 Make the PO 10 days '17 Jan 28 '17 Feb 6
14 P2.1.2 Manufacture and 38 days '17 Feb 27 '17 Apr 5
shipment of the first
batch type-B sleeve
15 P2.1.3 Manufacture and 58 days '17 Mar 6 '17 May 2
shipment of the second
batch type-B sleeve

16 P2.1.4 Manufacture and 58 days '17 Apr 2 '17 May 29


shipment of the third
batch type-B sleeve
17 P2.2 Composite material 68 days '17 Jan 25 '17 May 1
18 P2.2.1 Make the PO for the 5 days '17 Jan 25 '17 Jan 29
first batch of composit
materila
19 P2.2.2 Manufacure for the 45 days '17 Jan 30 '17 Mar 15
first batch composite
material
20 P2.2.3 Shipment and Costums 47 days '17 Mar 16 '17 May 1
Clearance for the
second batch composite
material
21 P2.3 Coating Material 63 days '16 Nov 17 '17 Apr 5
22 P2.3.1 Make the PO for the 3 days '16 Nov 17 '16 Nov 19
first batch material
23 P2.3.2 Manufactur of the first 15 days '16 Nov 28 '16 Dec 12
batch coating material

24 P2.3.3 Shipment and customs 30 days '16 Dec 25 '17 Jan 23


clearance of the first
batch coating material

25 P2.3.4 Make the PO for the 5 days '17 Jan 25 '17 Jan 29
second batch material
26 P2.3.5 Manufactur of the 30 days '17 Jan 30 '17 Feb 28
second batch coating
material
27 P2.3.6 Shipment and customs 36 days '17 Mar 1 '17 Apr 5
clearance of the
second batch coating
material
28 P2.4 Equipmet procument 48 days '16 Sep 12 '16 Nov 16
29 P2.4.1 Make the PO 3 days '16 Sep 12 '16 Sep 14
30 P2.4.2 Manufacture 10 days '16 Sep 19 '16 Sep 28

Page 1
ID WBS Task Name Duration Start Finish 2016 September 2017 May
September Beginning January Beginning May Beginning September Beginning January Beginning
7/3 8/28 10/23 12/18 2/12 4/9 6/4 7/30 9/24 11/19 1/14
31 P2.4.3 Shipment and customs 35 days '16 Oct 13 '16 Nov 16
clearance of the
equipments
32 P2.5 Auxiliary tools 48 days '16 Sep 16 '16 Nov 16
33 P2.5.1 Make the PO 15 days '16 Sep 16 '16 Sep 30
34 P2.5.2 Transportation in China 15 days '16 Sep 16 '16 Sep 30

35 P2.5.3 Shipment and customs 35 days '16 Oct 13 '16 Nov 16


clearance in Sudan
36 P3 Construction 188 days '17 Jan 7 '17 Nov 22
37 P3.1 Preparation 90 days '17 Jan 7 '17 Apr 12
38 P3.1.1 WPS 15 days '17 Jan 7 '17 Jan 21
39 P3.1.2 WQT for the first batch 15 days '17 Jan 7 '17 Jan 21
of welder
40 P3.1.3 FAT 15 days '17 Jan 7 '17 Jan 21
41 P3.1.4 Manpower Traning and 7 days '17 Apr 6 '17 Apr 12
Qualification for
STOPAQ and 3X products

42 P3.1.5 Setup the camp 3 days '17 Apr 26 '17 Apr 28


43 P3.2 Manpower mobilization 90 days '17 Apr 29 '17 Jun 6

44 P3.2.1 The manpower for 7 days '17 Apr 29 '17 May 5


preparation
45 P3.2.2 The second team of 3 days '17 Jun 4 '17 Jun 6
constructors
46 P3.3 Pipeline repair 120 days '17 May 8 '17 Nov 22
47 P3.3.1 Feature Points located 35 days '17 May 8 '17 Jun 11
before PS#3
48 P3.3.2 Feature Points located 116 days '17 Jun 12 '17 Oct 5
up to 40km from PS#3

49 P3.3.3 Feature Points after 45 days '17 Oct 8 '17 Nov 21


40km from PS#3
50 P4 Finalize the project 45 days '17 Dec 4 '18 Jan 24
51 P4.1 Manpower demobilization 5 days '18 Jan 20 '18 Jan 24
52 P4.2 Equipments demobilization 46 days '17 Dec 4 '18 Jan 18

53 P4.3 Submit the completion 35 days '17 Nov 22 '17 Dec 26


documents

Page 2
China Petroleum Pipeline Bureau (Sudan)

中国石油天然气管道局(苏丹)

WORK BREAKDOWN STRUCTURE


For
PROVISION OF PIPELINE REPAIR
PHASE II