Professional Documents
Culture Documents
in sub-assembly workshop
8/7/2020
Incident Summary
Description:
A T-Bar [Length: 17.28m / Weight: 3T] was dropped accidentally from approx. 0.5m to ground level in shipyard sub-assembly
workshop.
The T-bar was lifted during a trial lift aimed to adjust the rigging before the T-bar could be loaded onto a flatbed trailer.
The T-Bar was being rigged up by using 2 X 5T vertical plate clamps but minimum requirements for gripping length in the throat of
the clamp is 107mm and the T-bar face plate only offer effective gripping length of 64mm.
One clamp became loose resulting the T-Bar to be dropped from this end.
This sudden jerk caused the second clamp at the other end to release its grip on the T-Bar as well.
No one was injured in this incident.
The DROPS calculation showed that this event had the potential to lead to a fatal incident thus leading to a HiPo Near Miss Tier 1
investigation.
The work was stopped immediately and the scene was secured by HSSE Dept from buyer and builder.
A Safety stand-down was conducted on October 15th during the morning toolbox talk for all lifting and rigging crews.
On October 15th, 9AM, an incident investigation team was created with representatives of builder and buyer under the direction of
Regional HSSE/QRM Manager.
The objective of the investigation are to:
- Determine the timeline of events leading to the incident
- Determine the missing or broken barriers leading to the event
- Determine and analyze the root causes
- Determine the corrective actions
8/7/2020 2
Incident Scene
8/7/2020 3
Tap Root® Investigation
Sequence of events
8/7/2020 4
Tap Root® Investigation
Sequence of events
8/7/2020 5
Investigation Findings
Fact
Causal Factor
Wrong type of vertical clamps were chosen and used by the rigger during the lifting of this T-Bar.
Clamps used required at least 107mm of contact point inside the throat of clamps while face plate of T-Bar is only 64mm.
This activity is not a normal work and is not included in the work plan for that day.
No evidence of last minute risk assessment conducted for any new work instruction and lead whereby team leader or foreman could define work procedure,
safe work method statement, right tools and equipment as well as PPEs and address to all crew members.
Position
Rigger used tagline and was controlling the load from 2m away.
Next personnel (inspectors) were distant 5m away from the lifted load.
Rigger and workshop gantry crane operator have clear view of each other.
Part
All lifting gears and devices used in this lifting activity are in good condition.
Correct types of plate clamps not available at that particular time due to procurement is still on-going.
Two skips full of defective and sub-standards lifting clamps were previously put out of service following a lifting/rigging audit conducted by project team.
People
Paper
8/7/2020 6
SRS Investigation
Root Cause Determination
Possible Immediate Causes
ACTION
Use of Tools or Equipment > Tools were used for activities which they were not designed for of did not meet the requirement.
The rigger was using the wrong type of plate clamps.
Inattention / Lack of Awareness > The situation was wrongly judged and the wrong decision was made.
The rigger did not ensure the right plate clamps were used when he found that they were not available.
CONDITION
Tools, Equipment and Vehicles > The tools were not adequate, or the proper tools were not supplied.
The suitable plate clamps QYW-3A or Horizontal plate clamps were not available during the event.
Tools, Equipment and Vehicles > The right tools were not prepared before the job.
No TBT/RA discussed after lunch after new work instruction was given to ensure right tools were prepared.
8/7/2020 7
SRS Investigation
Corrective actions
Proposed corrective actions to address root causes:
1. Issue work instruction to foreman and supervisors to systematically reassess the risks and clarify instructions to workers in case of
change of work program (LMRA – Last Minute Risk Assessment).
2. Extend Front Line Supervision (FLS) training to subcontractors together with guidance note for supervisor / foreman for the type of
task to be perform.
3. Audit the shipyard training process program and verification of competence of supervisors.
4. Audit the shipyard management system for lifting aids and tools.
8/7/2020 8
SRS Investigation
Corrective actions status
CA1 – Issue work instruction to foreman and supervisors to systematically reassess the risks and clarify instructions to
workers in case of change of work program(LMRA-Last Minute Risk Assessment)
Shipyard completed their own internal investigation and the list of recommendation corrective actions was distributed to all
Department Heads for dissemination. Work Instruction including clear and precise communication on the correct type of
rigging using the predetermined rigging devices.
8/7/2020 9
SRS Investigation
Corrective actions status
CA1 – Issue work instruction to foreman and supervisors to systematically reassess the risks and clarify instructions to
workers in case of change of work program.
Shipyard completed TBT refresher training for all the supervisors and foremen on 2nd Nov, special requirements for the LMRA
was highlighted in the training, the record for the LMRA shall be written on the TBT book by foreman/supervisor for all non-
routine or last minute changes work activities.
Non-routine activities
8/7/2020 10
SRS Investigation
Corrective actions status
CA2 – Extend Front Line Supervision (FLS) training to subcontractors together with guidance note for supervisor / foreman for
the type of task to be perform.
Shipyard completed an internal Frontline Supervision Training on 02 Nov 2019. See below pictures for the attendees list and
training evaluation forms.
Attendees
List
Evaluation
forms for the
training
8/7/2020 11
SRS Investigation
Corrective actions status
CA3 – Audit the shipyard training process program and verification of competence of supervisors
• Training audit was conducted by HSSE, no significant non-compliance found. Project training procedure and matrix had been developed
and approved and being implemented at site according to the plan.
• Trainers are discipline supervisors from shipyard PMT, VOC witnessed by HSSE, the effect of training was good.
Example:
All Rigging and Lifting crew members attending a special refresher training on Safe Lifting and Rigging Practices on 29th October 2019.
This special training was conducted by a 3rd Party service provider J&L who are specialising in supplying lifting and rigging devices to the
Shipyard.
3rd party
training
Project training
matrix
CMHI’s internal
training materials
Attendees Evaluation forms
List for the training
8/7/2020 12
SRS Investigation
Corrective actions status
C4 – Audit the shipyard management system for lifting aids and tools
• Audit conducted by HSSE, no significant non-compliance found during the audit, suggested shipyard to post daily inspection record for
the Lifting and Rigging appliances.
• All Lifting and Rigging appliances will be stored at dedicated storage rack instead of kept by subcontractors.
• Weekly Thematic Inspection (joint inspection) on Lifting and Rigging is on-going and the frequency will be conducted on weekly basis.
Monthly
Color coding
scheme
Weekly
Thematic
Inspection
Daily
inspection
record
8/7/2020 13
SRS Investigation
Corrective actions status
C4 – Audit the shipyard management system for lifting aids and tools
8/7/2020 14
Investigation
Corrective actions status
Both buyer and builder are performing evaluation and assessment of the daily TBT for all of their Sub-
contractors. HSSE Dept is monitoring this trend on weekly basis.
8/7/2020 15
Investigation
Corrective actions status
Issue the TBT booklet to all the subcontractors, assessment of knowledge transfer via TBT evaluation form by
various Discipline Supervisors.
TBT
TBT booklet evaluation
form
TBT
evaluation
feedback
Main issues:
TBT • Some workers not wearing gloves
evaluation Good findings:
by • 2 ways communication
discipline • Safety, quality and production all
supervisor involved
8/7/2020 16