Professional Documents
Culture Documents
By
Dr. Mehmet Cigla
1
1
1/03/2023
2
1/03/2023
3
1/03/2023
4
1/03/2023
10
10
5
1/03/2023
Mining
Methods
MINE4401
MINE4503
Underground Mining 1
Surface Mining
Underground
Surface Mining
Mining
Methods
Methods
11
11
Mining
Methods
Underground
Surface Mining Mining
Methods Methods
12
12
6
1/03/2023
Mining
Methods
Underground
Surface Mining Mining
Methods Methods
http://i5tradings.com/coal-mining.html
13
13
Mining
Methods
Underground
Surface Mining Mining
Methods Methods
http://www.marmidicarrara.com/cave_apuane.html
14
14
7
1/03/2023
Mining
Methods
Underground
Surface Mining Mining
Methods Methods
15
15
Mining
Methods
Underground
Surface Mining Mining
Methods Methods
16
16
8
1/03/2023
Spatial aspects of the ore body (e.g. size, shape, attitude, and depth)
• Mine size
17
17
• Geological considerations such as mineralogy, petrography, structure, hydrology, distribution of ore grades, etc.
Mineral processing or metallurgical aspects, blending requirements, water bodies and pumping requirements
Pit slope angles, bench height, haul road designs, etc. and support requirement for underground operations
18
18
9
1/03/2023
• Ore dilution
19
19
Environmental and social impacts – during and after mining Economics, safety, and environment address the context of
• Reclamation and restoration requirements and costs sustainable development of mining operations
20
20
10
1/03/2023
• Some deposits are best mined initially as open pits, with production shifting to an underground method as deeper portions of the
ore body are extracted.
• Break-even depth?
21
21
22
22
11
1/03/2023
1. Topography
2. Climatic conditions
(a) Altitude
(b) Temperatures - Extremes
Monthly averages
(c) Precipitation - Average annual precipitation
Average monthly rainfall
Average monthly snowfall
Run-off
Normal
Flood
Slides – snow and mud
(d) Wind - Maximum recorded
Prevailing direction
Hurricanes, tornados, cyclones, etc.
(e) Humidity - Effect on installations, i.e. electrical motors, etc.
(f) Dust
(g) Fog and cloud conditions
23
23
4. Geologic structure
(a) Within mine area
(b) Surrounding areas
(c) Dam locations
(d) Earthquakes
(e) Effect on pit slopes - Maximum predicted slopes
(f) Estimate on foundation conditions
24
24
12
1/03/2023
(a) Depth
(b) Quantity
(c) Method of drainage
6. Surface
25
25
26
26
13
1/03/2023
10. Roads
27
27
12. Smelting
(a) Availability
(b) Method of shipping concentrate
(c) Rates
(d) If company on site smelting – effect of smelter gases
(e) Concentrate freight rates
(f) Railroads and dock facility
14. Government
28
28
14
1/03/2023
29
29
30
30
15
1/03/2023
31
31
32
32
16
1/03/2023
Exploitation – excavate ore body Core logging should include the following:
•Lithological description
Rock type
Color
Texture
Mineralogy
Alterations
•Core Loss
•Assays
33
33
34
34
17
1/03/2023
35
35
36
36
18
1/03/2023
Order of Feasibility
Pre-Feasibility
Magnitude Study
Study
Scoping Absolute studies;
Comparative and/or
Conceptual or reserve based
re-engineering studies
desktop study (bankable)
3-Month Plan
Strategic Budget/ 1-Month Plan
Life-of-Mine Plan
Review Re-Forecast 1-Week Plan
1-Day Plan
37
37
Financial Optimisation
Capital and operating summation
Revenue
Cash flow statement
Marginal ore utilisation
Rate of return
Production Scheduling
Pre-production costs
Equipment and Facilities
Working room
Capital intensive
Stripping ratios
Equipment selection
Sequencing
Operation costs
Reclamation
Capital depreciation
Operating schedules
Selective mining
Financial
Constraints
Dohm, G.C., Jr. 1979. Circular analysis–Open pit optimization. Chapter 21 in Open Pit Mine Planning and Design (J.T. Crawford, III and William A. Hustrulid, editors). AIME. Pp 281-310. 38
38
19
1/03/2023
Ore is a natural aggregation of one or more solid minerals that can be mined, processed and sold at a profit.
$/lb or $/t
Profits = Material sold (units) × (Price/unit − Cost/unit)
39
39
Order of • Feasibility
Pre-Feasibility Study
Pre-Feasibility
Magnitude Study
Study
Scoping Absolute studies;
Comparative and/or
Conceptual or
re-engineering studies based
–reserve basedon
current knowledge, what’s the most profitable
desktop study (bankable)
means of mining (within acceptable risk)
– includes mine extensions 3-Month Plan
Strategic Life-of-Mine Budget/ 1-Month Plan
Review Plan Re-Forecast 1-Week Plan
• Strategic Reviews 1-Day Plan
40
40
20
1/03/2023
Order of ➢ LessFeasibility
detailed than tactical or operational plans
Pre-Feasibility Long-time frames being considered
Magnitude ▪ Study
Study indicative,
Scoping Absolute
▪ studies; not definitive
Comparative and/or
Conceptual or reserve based
re-engineering studies
desktop study ➢ (bankable)
Plans evaluated by economic measures
▪ NPV and Return on investment considered key measures
3-Month Plan
Strategic Life-of-Mine
➢ Include Budget/
inferred resources and closure costs 1-Month Plan
Review Plan Re-Forecast 1-Week Plan
➢ Sanity checks throughout 1-Day Plan
41
41
42
42
21
1/03/2023
43
43
44
44
22
1/03/2023
45
45
3-Month Plan
➢ Budget
Strategic Budget/ 1-Month Plan
Life-of-Mine Plan
▪ Review
Life-of-Mine Year 1, detailed revenue- Re-Forecast 1-Week Plan
expenditure 1-Day Plan
➢ Budget Re-Forecast
▪ Multiple
early warning of potential variance,
Base & Plus
corrective actions options/scenar
ios Cases
▪ manage stakeholder expectations,
including investors
46
46
23
1/03/2023
47
47
48
48
24
1/03/2023
➢ Daily Plan
Multiple
▪ focus on resource assignments to achieve
options/scenar
weekly
Base & Plus plan
Cases
▪ update start-of-shift, ios
24-hour horizon
49
49
Multiple
➢ Plans evaluated by physicals
options/scenar
& resourcing
Base & Plus
ios Cases
50
50
25
1/03/2023
51
51
Order of Feasibility
Pre-Feasibility
Magnitude Study
Study
Scoping Absolute studies;
Comparative and/or
Conceptual or reserve based
re-engineering studies
desktop study (bankable)
3-Month Plan
Strategic Budget/ 1-Month Plan
Life-of-Mine Plan
Review Re-Forecast 1-Week Plan
1-Day Plan
52
52
26
1/03/2023
We, mining engineers, define feasible as ‘The practicable and possible relate to not only the
physical aspects of resource exploitation (technical) but also to the economics of the project
(financial)’
Chapter 3 ➔ Page 21-40 Chapter 4.2 ➔ Page 396-423 Chapter 1 ➔ Page 4-19
Chapter 2 ➔ Page 24-27
53
53
54
54
27
1/03/2023
55
55
56
56
28
1/03/2023
Process Product
Mine
Ore Sag Mill
Ball mill
Concentrate
Refinery Metal Economy
Flotation
Waste Waste
57
57
Stockpile
Reclaim
Process Product
Mine
Ore Sag Mill
Ball mill
Concentrate
Refinery Metal Economy
Flotation
Waste Waste
58
58
29
1/03/2023
Reclaim Product
Stockpile Heap Leach Metal
Reclaim
Process Product
Mine
Ore Sag Mill
Ball mill
Concentrate
Refinery Metal Economy
Flotation
Waste Waste
59
59
60
60
30
1/03/2023
61
61
Production Scheduling
Pre-production costs
Equipment and Facilities
Working room
Capital intensive
Stripping ratios
Equipment selection
Sequencing
Operation costs
Reclamation
Capital depreciation
Operating schedules
Selective mining
Financial
Constraints
Dohm, G.C., Jr. 1979. Circular analysis–Open pit optimization. Chapter 21 in Open Pit Mine Planning and Design (J.T. Crawford, III and William A. Hustrulid, editors). AIME. Pp 281-310. 62
62
31
1/03/2023
Mine
Design
Mine STRATEGIC
Scheduling
Iterating
for Value
Maximisation
Mining Cost
Estimation
TACTICAL
OoM 35-50%;
50-70% probability of positive NPV Economic
PFS ±25%;
Evaluation
85% probability of positive NPV
FS, SR ±15% OPERATIONAL
Planning process
should be flexible
LoM ±10%
to change &
sensitivities Reporting
Budget ±5%
63
63
64
64
32
1/03/2023
65
65
1. To provide a comprehensive framework of established and detailed facts concerning the mineral project.
2. To present an appropriate scheme of exploitation with designs and equipment lists taken to a degree of detail
sufficient for accurate prediction of costs and results.
3. To indicate to the project’s owners and other interested parties the likely profitability of investment in the project if
equipped and operated as the report specifies.
4. To provide this information in a form intelligible to the owner and suitable for presentation to prospective partners
or to sources of finance.
66
66
33
1/03/2023
67
67
68
68
34
1/03/2023
69
69
70
70
35
1/03/2023
71
71
72
72
36
1/03/2023
73
73
74
74
37