I. Equipment Design Specifications:
JOB NAME:VILLA LA ESTANCIA Model #:
CVHE040FA3FW3UR2225Q1E5L1C0000000FA000000010002C0
LOCATION :CABO SAN LUCAS B.C.S. Serial #: L01A06701 Tag #: 1
NAMEPLATE: 460 volts 231RLA 60 HERZ
DESIGN: 460 volts 231RLA 60 HERZ 400 TONS
Caution: Changes to the chiller settings should be made by authorized personnel who are familiar with the installation and the
effects which these changes may produce.
II. Chiller Report:
A. B. C.
1. Operating Mode: Line 1
2. Operating Mode: Line 2
3. Active Chilled Water SP Deg Deg Deg
Page 1
29. Evap Approach Temp Deg Deg Deg
30. Cond Approach Temp Deg Deg Deg
Page 2
IV. Compressor Report:
A. B. C.
1. Differential Oil Pressure
2. Oil Tank Temperature Deg Deg Deg
3. Discharge Oil Pressure
4. Oil Tank Pressure
5. Inlet Guide Vane Position % Open % Open % Open
6. Inlet Guide Vane Position Degrees Degrees Degrees
7. Compressor Phase Phase A % Phase A % Phase A %
Currents: %RLA Phase B % Phase B % Phase B %
Phase C % Phase C % Phase C %
8. Compressor Phase Currents: Phase A Amps Phase A Amps Phase A Amps
Amps Phase B Amps Phase B Amps Phase B Amps
Phase C Amps Phase C Amps Phase C Amps
9. (Opt) Compressor Phase AB Volts AB Volts AB Volts
Voltages BC Volts BC Volts BC Volts
CA Volts CA Volts CA Volts
10. (Opt) Compressor %PF % Power Factor % Power Factor % Power Factor
11. (Opt) Compressor KW KW KW KW
12. Comp Winding Temps W1 Deg F/C W1 Deg F/C W1 Deg F/C
W2 Deg F/C W2 Deg F/C W2 Deg F/C
W3 Deg F/C W3 Deg F/C W3 Deg F/C
12. Compressor Starts: Starts Starts Starts
13. Compressor Running Time: Hrs Min Hrs Min Hrs Min
14. Solid state starter heat sink F F F
V. Additional Information:
A. B. C.
1.Oil Level:
O O O
O O O
2. Chilled Water PD:
4. Cond Water PD:
4. Evp Press W/Test Gauge
5. Cnd PressW/Test Gauge
NOTAS Y COMENTARIOS:
______________________ _________________________
FREONIX SERVICIO Dpto. Mantenimiento
LOS CABOS Caboland Villa la Estancia
Page 3