Pashta Kahan & Garambowad PIS SubProject

Pashta Kahan
1 weir on working
2 Pashta Kahan Main Left Channel complete
3 Feeder Lower Ahengry Right Channel Channel complete
4 Syphon-1 complete
5 Right Lower Ahengry Channel complete
6 Feeder Right Channel complete
7 Syphon-2 complete
8 Upper Manglabad Channel complete
9 STR on working
10 Flood Protection Bund on working