You are on page 1of 54

System Modeling

AC Network

© 2013 ETAP & Operation Technology, Inc.


4 hrs 2 hrs 1 hr

One-Line Multi-
Layout & Advanced System Engineering Project
Topic Overview Dimensional Summary
Toolbars Modeling Representation Libraries Management
Database

System Manual Composite Library


Abstract Presentations Project Merge
Toolbar Method Networks Structure

GUI AC & DC
Composite Library
Elements Auto-Connect Configurations Import Excel
Summary Motors Management
Toolbar

System Auto-Build Viewing Library Other DataX


Data Revisions Datablocks
Manager & Rule Book Data Methods

Theme
Dumpster Data Manager Adding Devices
Manager

Element
User Access
Property Exercise 3
Management
Defaults & IDs

Exercise 2
Templates Multi-
Dimensional DB

Exercise 1
Building Simple
One-Line

© 2013 ETAP & Operation Technology, Inc.


ETAP Overview

• One-Line Diagram • Mode Toolbar

• Toolbar Format • System Toolbar

• Dumpster • Study Case Toolbar

• Project View • Message Log

• Project Toolbar

© 2013 ETAP & Operation Technology, Inc.


Select Study Mode

Edit Toolbar
AC Elements
System Manager DC Elements
Instrument
Devices

System
Toolbar

One-Line Diagram Help Line


In Edit Mode Displays the
description for
every entry field.
Message Logger
View the latest
messages related to
ETAP Projects.
It can be expanded
or reduced.

© 2013 ETAP & Operation Technology, Inc.


Mode Toolbar Format

© 2013 ETAP & Operation Technology, Inc.


Analysis Toolbar Format
Analysis toolbars have the following sections:

1. Run the Calculation


2. Stop the Calculation
3. Display Alerts
4. Result Analyzer and Output Reports
5. Display Options
6. Get On-Line Data
7. Get Archived Data

All ETAP analysis toolbars follow this general format.

© 2013 ETAP & Operation Technology, Inc.


Cursor Auto connection
Bus 3W XFMR
Cursor Bus
2W XFMR Voltage Regulator
Open Delta XFMR Cable
Trans. Line
Cable Impedance
Reactor Impedance Converter
Generator
Power Grid Battery PV Array
PV
Wind Turbine Gen Synch. Motor
Motor Static Load
Induction Machine MOV
Lumped Load Capacitor Lumped Load Elementary Diagram
Static Load Harmonic Filter
Panels Composite
Phase Adapter Motor Composite Network
Remote Connector MG Set Fuse
CB
SVC HVDC
SPDT
SPST
Composite Motor Composite Network
UPS VFD
Fuse Contactor
HVCB LVCB Charger
Recloser Ground Switch
Inverter
Overload Heater In-Line Overload Relay
SPST SPDT

Instrumentation Ground Grid

Display Options Schedule Report Manager

© 2013 ETAP & Operation Technology, Inc.


Current Transformer Potential Transformer
Voltmeter Ammeter
Multimeter CSD XFMR
Voltage Relay 27 / 59 Reverse Power Relay
Frequency Relay 81 Solid State Trip Relay
Motor Relay Overcurrent Relay 50/51/67
Overload Heater Multi Function Relay
Taglink

© 2013 ETAP & Operation Technology, Inc.


Run Load Flow Calculation
Auto Run
Stop Calculation
Display Options
Load Flow Alerts
Load Flow Result
Analyzer
Load Flow Report Manager

Get One-Line(RT) Data


Get Archived Data

Load Analyzer
© 2013 ETAP & Operation Technology, Inc.
3-Phase SC Duty Calculation
1-Phase SC Duty Calculation

½ Cycle Unbalanced LG, LL, LLG & 3-Phase

½ to 4 Cycle Unbalanced LG, LL, LLG & 3-Phase


30 Cycle Unbalanced LG, LL, LLG & 3-Phase

Short-Circuit Display Options


Short-Circuit Alerts for Buses & PDs
Short-Circuit Report Manager
Short Circuit Result Analyzer

Stop Calculation
Get On-Line Data
Get Archived Data

© 2013 ETAP & Operation Technology, Inc.


3-Phase SC IEC Duty Calculation

1-Phase SC IEC Duty Calculation

60909 Unbalanced LG, LL, LLG & 3-Phase

Transient IEC 61363

Short-Circuit Display Options

Short-Circuit Alerts for Buses & PDs

Short-Circuit Report Manager

IEC 363 Plots / Export COMTRADE

Short Circuit Result Analyzer

Stop SC Calculations
© 2013 ETAP & Operation Technology, Inc.
Run Arc Flash

Run Arc Flash 1-Phase

AF Fault Insertion
AF 1-Phase Seq. Of Ops

Create STAR View (TCC)

STAR View manager


Display options
Alert View
Report Manager
AF Result Analyzer
Stop AF Calculation
Get One-Line Data
Get Archived Data
© 2013 ETAP & Operation Technology, Inc.
Create a New Presentation

© 2013 ETAP & Operation Technology, Inc.


Auto Build
• Quick & Intuitive Single Line Generation
• No Need to Drag, Drop, Connect
• Auto-build without Leaving Equipment Palette
• Automatic spacing & Alignment Rules

© 2013 ETAP & Operation Technology, Inc.


Auto Build In Action

© 2013 ETAP & Operation Technology, Inc.


Voltage Propagation

© 2013 ETAP & Operation Technology, Inc.


The Remote Connector

© 2013 ETAP & Operation Technology, Inc.


Insert Protective Devices

Hint

Protective Devices can be inserted


Without breaking connection line

© 2013 ETAP & Operation Technology, Inc.


Move From Dumpster
• Elements can be moved from the Dumpster into
the one-line diagram with the same name IDs by
using the following methods:

1. Right-click on the one-line diagram and select


Move From Dumpster

2. Click on Edit on the Menu Bar and select “Move


From”

© 2013 ETAP & Operation Technology, Inc.


Move From Dumpster
• Rules:

• Move From Dumpster can be done only under


“Edit” mode and “Base” revision data

• Deleted Items (element groups) must be


present in Dumpster beforehand

• IDs of the moved elements, along with the


connections, status, and properties are
preserved

© 2013 ETAP & Operation Technology, Inc.


Move From Dumpster

• Move desired Dumpster cell group by selecting from


the Dumpster window

• Move From Dumpster capability also supported inside


Composite Networks

• Both sections of Remote Connector element must be


moved from the dumpster at the same time

© 2013 ETAP & Operation Technology, Inc.


Creating a Project
Using Auto Build or Auto Connect, enter four new elements into the
One-line diagram and proceed to enter the input data for each:

Power Grid
1250 MVAsc
X/R = 120

Transformer T1
Bus kV Rating 20 MVA
Bus 1 = 13.8 %Z=6
Bus 2 = 4.16 X/R = 17

Lumped Load
5 MVA
% PF = 80
Rated kV= 4
70% Motor Load

© 2013 ETAP & Operation Technology, Inc.


Run a Load Flow Calculation
Display units as shown;

© 2013 ETAP & Operation Technology, Inc.


•Using Auto Build or Auto
Connect enter four more
elements into the one-line
diagram as shown;

Cable
NEC EPR 133%
5.0kV Mag
3/C CU
Size= 4/0
Length=200ft

Transformer T2 Bus kV Rating


MVA= 1 Bus3= 4.16
Typical %Z & X/R Bus4= 0.480

Lumped Load Lump2


MVA= 1
%PF=85
Rated kV = 0.46
50% Motor Load

© 2013 ETAP & Operation Technology, Inc.


Once all the elements have
been connected and the
input data has been
entered, you may proceed
to run a Load Flow
Calculation.

© 2013 ETAP & Operation Technology, Inc.


• Add a Generator Gen1
• Rotate Gen1 180º
using <SHIFT+R>
• Connect & proceed to
enter required input
data for Load Flow

• Extend the length of Bus2


towards the right side.

Gen1
Rating:
5 MW
Voltage Control
%PF = 80
Generation Category:
Design
MW = 5
Qmax = 5
Qmin = 1

© 2013 ETAP & Operation Technology, Inc.


• Once the Generator has been
connected and the input data
has been entered, you may
proceed to run a Load Flow
Calculation

© 2013 ETAP & Operation Technology, Inc.


1. Extend the length of Bus1
towards the right side.

2. Copy elements T1,


Bus2, Lump1, Cable1,
T2, Bus4 and Lump2.

3. Move From Dumpster


4. Insert a normally
and connect them to
open Tie Breaker
main Bus1.
between LV-Buses

© 2013 ETAP & Operation Technology, Inc.


• Insert a Composite Network and connect between
4.16 kV Buses

• Open Composite Network and move elements


inside Network1 by Drag and Drop. Hold <Shift>

• Connect 5 kV cables back to system using


connection Pin

© 2013 ETAP & Operation Technology, Inc.


• Insert HV Circuit Breakers at the indicated
locations. (Double Click to insert multiple locations)

• Insert LV Circuit Breakers inside the Composite


network and place them before the Lumped Loads

© 2013 ETAP & Operation Technology, Inc.


One-Line Template
• Select All and create a One-Line Template (include the Composite network)

• Create a new Project and “Get” One-Line template created

© 2013 ETAP & Operation Technology, Inc.


Data Block
• Create a DataBlock for Bus elements to display the following:
-Bus Name (ID) -kW Loading
-Nominal Bus kV -Voltage Drop in kV

© 2013 ETAP & Operation Technology, Inc.


3D Database

© 2013 ETAP & Operation Technology, Inc.


Study Conditions
• Different Operating Requirements

Generator 1 in Voltage Generator 1 in Swing Mode


Control Mode
© 2013 ETAP & Operation Technology, Inc.
Study Conditions
• Different Loading Conditions

Summer Loading Winter Loading

© 2013 ETAP & Operation Technology, Inc.


Study Conditions
• Different Configurations

Configuration Normal Configuration GenOFF


© 2013 ETAP & Operation Technology, Inc.
Study Conditions
• Different Engineering Data

Revision Base Revision Sub2a Mod

© 2013 ETAP & Operation Technology, Inc.


3-D Database
Presentations Configurations
Symbol & CB, Fuse, Switch,
Annotation Load, & Motor
Visibility, Status
Location,
& Size

Properties

Nameplate,
Rating, Loading,
Settings, Dimension, etc.
Base & Revision Data
© 2013 ETAP & Operation Technology, Inc.
Presentations
Symbol &
Annotation
Visibility,
Location,
& Size

 One-Line Diagrams
 Impedance Diagrams
 Relay Diagrams
 Physical Diagrams
 Study Diagrams
© 2013 ETAP & Operation Technology, Inc.
Configurations
CB, Fuse, Switch,
Load, & Motor
Status

© 2013 ETAP & Operation Technology, Inc.


Properties
Properties

Nameplate,
Rating, Loading,
Settings, Dimension, etc.
Base & Revision Data
© 2013 ETAP & Operation Technology, Inc.
User Access Management
Group 1 Functions
Move Elements
Change Element Size
Change Element Symbol
Change Element Orientation
Edit Engineering Properties
Change Operating Status
Hide or Show Protective Devices
Autoroute Connections
Change Bus to Node Symbols
Purge Data Revisions
Merge Data Revisions to Other Revisions

© 2013 ETAP & Operation Technology, Inc.


User Access Management
Group 2 Functions
Add (Drop) Elements
Cut (Delete) Elements to Dumpster
Copy Elements from Dumpster
Paste Elements from Dumpster
Move Elements from Dumpster
Connect Elements
Purge Elements from Dumpster
Re-sizing Elements (UGS)
Merge Data Revision to Base Data
Graphical Adjustment of STAR
Views
© 2013 ETAP & Operation Technology, Inc.
User Access Management

Group 3 Functions
Change Phase/Ground mode in
Star View.
Compute Time Difference in Star
View.
View Alerts.
View Device Setting Reports.

© 2013 ETAP & Operation Technology, Inc.


User Access Management
Project Editor
Can Cannot
Change Change
User Access Management X
Project Data / Defaults X
Base Data X
Revision Data X
Group 1 Changes X
Group 2 Changes X
Group 3 Changes X
Configuration Status X
Library Data X
Library Path X
© 2013 ETAP & Operation Technology, Inc.
User Access Management
Base Editor
Can Cannot
Change Change
User Access Management X
Project Data / Defaults X
Base Data X
Revision Data X
Group 1 Changes X
Group 2 Changes X
Group 3 Changes X
Configuration Status X
Library Data X
Library Path X
© 2013 ETAP & Operation Technology, Inc.
User Access Management
Revision Editor
Can Cannot
Change Change
User Access Management X
Project Data / Defaults X
Base Data X
Revision Data X
Group 1 Changes X
Group 2 Changes X
Group 3 Changes X
Configuration Status X
Library Data X
Library Path X
© 2013 ETAP & Operation Technology, Inc.
User Access Management
Checker
Can Cannot
Check Change
User Access Management X
Project Data / Defaults X
Base Data X X
Revision Data X X
Group 1 Changes X
Group 2 Changes X
Group 3 Changes – Can Change
Configuration Status X
Library Data X
Library Path X
© 2013 ETAP & Operation Technology, Inc.
Circuit Arrangements

• Radial System
• Loop System
• Primary Selective System
• Secondary Selective System

© 2013 ETAP & Operation Technology, Inc.


Radial System

• Simple or Expanded Radial


• Inverted tree
• No duplications
• Least Expensive
• Simple in operation
• Easy to analyze

© 2013 ETAP & Operation Technology, Inc.


Loop System

• Interconnected / Open Point


• Loads are tapped of the loop
• Loop could be open or closed
• More difficult for analysis
• Reliable

© 2013 ETAP & Operation Technology, Inc.


Primary Selective System

• Each transformer is supplied by two sources


• Normal operation is to supply half the load
from one source
• Manual or Automatic transfer of load
• Recommended

© 2013 ETAP & Operation Technology, Inc.


Primary Selective System
© 2013 ETAP & Operation Technology, Inc.
Secondary Selective System

• Each load can be supplied from either one of


the transformers
• The tie breaker is usually normally open
• If one of the transformers is out of service, the
tie breaker is closed and the total load is
supplied by the remaining transformer
• Very reliable system

© 2013 ETAP & Operation Technology, Inc.

You might also like