DATE: 5/22/2023
GROUP IV
GROUP IV 1
5/22/23
ASSN #1: Case Study
A. With respect to commercial terms, the type of contract is a cost+fixed percentage fee contract
B. The actual cost of the completed project amounted to $11,275,000. Since the contractor's fee
is fixed at the estimated amount and not the final rate of the completed project, the owner has to
pay $11,275,000 to the contractor.
C. According to circumstance B, the entire transaction agreed upon by both parties was a
maximum sum of $12,962,000. Therefore, 12,962,000 - 11,275,000 = $1,687,000.
The contractor lost $1,687,000 from the entire transaction.
D. If the project costs had been $13,625,000, the owner would have paid $12,962,000, as it was
the maximum amount that both parties agreed upon if the cost rose from the estimated
$12,250,000.
E. According to circumstance D, the agreed-upon maximum project cost paid by the owner is
$12,962,000, and the completed cost is $13,625,000. Therefore, 12,962,000 - 13,625,000 =
$663,000. The contractor lost $663,000.