Professional Documents
Culture Documents
Chapter 16
Footings and Foundations
Conducted by –
Dr. Kyaw Zeyar Win
Professor and Head
Department of Civil Engineering
1
1
Prepared by - Dr. Kyaw Zeyar Win
Figure 16.1.
Types of spread footing
3
2
Prepared by - Dr. Kyaw Zeyar Win
where, ω = 1.3 if the wind load is calculated based on ASCE/SEI 7 and 1.0
otherwise.
5
2P
qmax =
3bm
3
Prepared by - Dr. Kyaw Zeyar Win
1
Mu = qu b − a 2 ⇒ along section 1−1
8
b−a
Vu = qu −d
2
7
4
Prepared by - Dr. Kyaw Zeyar Win
14000+10000
Required footing area = = 5.93 ft2
4050
5.93
Width of the footing = = 5.93 ft ≈ 6 ft
1
Select 6 ft wide footing.
Determination of thickness of footing
Factored Load 1.2×14+1.6×10
Ultimate bearing capacity, qu = = = 5.47 ksf
Area 6×1
Shear force at critical section,
b−a 6− 16ൗ12 d
Vu = qu − d = 5.47× − = 12.76 − 0.46d
2 2 12
Design shear strength,
1
ϕVc = ϕ×2λ f′c bd = 0.75×2×1× 4000×12×d × = 1.138d
1000 9
Vu = ϕVc
12.76 − 0.46d = 1.138d
d = 7.98 in
Assume clear cover = 3 in
h = 7.98 + 3 + 0.5 = 11.48 in ≈ 12 in
Use h = 12 in, d = 12 – 3.5 = 8.5 in
Determination of Steel Area
2
1 1 16
B.M at critical section, Mu = qu b − a 2 = ×5.47× 6− ×12
8 8 12
= 178.69 k−in/ ft
Mu 178.69
= = 229 psi
ϕbd2 0.9×12× 8.52
From Graph A1-b, ρ = 0.0038 10
5
Prepared by - Dr. Kyaw Zeyar Win
Check
As (max) = ρmaxbd = 0.0206 × 12 × 8.5 = 2.10 in2/ft
As (min)< As< As (max)
ld fy ψ t ψ e 60000 ×1 ×1
= = =37.95
db 25 f′c 25 4000
ld = 37.95×0.625 = 23.72 in ≈ 24 in
11
6×12 −16
Available Length = −3 = 25 in > Ld
2
16"
12"
6'-0"
12
6
Prepared by - Dr. Kyaw Zeyar Win
Column Footings
14
7
Prepared by - Dr. Kyaw Zeyar Win
(a) Shear
Two different types of shear strength are distinguished in
footings:
i. two-way, or punching shear and
ii. one-way, or beam, shear.
➢ For case in which the ratio of critical perimeter to slab depth b0/d is very
large,
αs d
Vc = +2 λ f′c bo d
b0
8
Prepared by - Dr. Kyaw Zeyar Win
9
Prepared by - Dr. Kyaw Zeyar Win
Dowel Bars
Column Bar
0.02fy db
Development length of dowel bars, ldc = ≥ 0.0003fy db
f′c
Splice length, lp ≥ ldc
lp ≥ 0.0005fy db
➢ When different size are lap-spliced in compression, the splice length is to
be the larger of the development length of the larger bar and the splice
length of the smaller bars.
Bending Moment, Reinforcement and Bond
➢ In square footings, the reinforcement is uniformly distributed over the
width of the footing in each of the two layers; that is, the spacing of the
bars is constant.
➢ The moments for which the two layers are designed are the same.
However, the effective depth d for the upper layer is less by 1 bar diameter
than that of the lower layer. 20
10
Prepared by - Dr. Kyaw Zeyar Win
21
11
Prepared by - Dr. Kyaw Zeyar Win
3 f′c 200bw d
Minimum flexural steel, As min = b d≥
fy w fy
23
12
Prepared by - Dr. Kyaw Zeyar Win
18+d 2 18+d 2
= qu B2 − = 6.1 9.5 2 −
144 144
1
ϕVc = 0.75×4×1× 4000×4× 18+d d× = 0.76× 18+d d
1000
ϕVc = Vu 1 18 18.5
9 .5 − − = 2 .46 '
2 12 12
18+d 2 g
0.76× 18+d d = 6.1 9.5 2 −
f
144 d
one-way shear area a b
d = 18.07 in d/2
18+d
9.5'
h = 18.07 + 4.5 = 22.57 in ≈ 23 in d/2
18"x18" abcd is punching shear area
d c
Use h = 23 in, d = 23 – 4.5 = 18.5 in 18+d
e h 25
9.5'
13
Prepared by - Dr. Kyaw Zeyar Win
2Mu 2×5563.2
a = d− d2 − = 18.5 − 18.52 − = 0.883 in
′
0.765fc b 0.765×4×9.5×12
Mu 5563.2
As = a = = 5.705in2
ϕfy d − ൗ2 0.9×60× 18.5 – 0.883ൗ
2
As min = ρmin bd = 0.0033bd = 0.003×9.5×12×18.5 = 6.96 in2
∴As min > As req
∴ Use As = 6.96 in2
Choose 12-No.7 bars in both directions. (As(prov) = 7.2 in 2 > As(reqd))
Check ld
l
From Table A−10, d = 47 ⇒ ld = 47×0.875 = 41.25 in
db
9.5×12−18
Available length = − 3 = 45 in > ld (OK)
2
27
A2
Bearing strength = ϕ0.85f′c ≤ ϕ0.85f′c ×2
A1
9.5×9.5 144
= 0.65×0.85×4× or 0.65×0.85×4×2 = 14 ksi or 4.42 ksi
18×18
14
Prepared by - Dr. Kyaw Zeyar Win
Splice Length
29
23"
9'-6"
9'-6"
9'-6" 30
15
Prepared by - Dr. Kyaw Zeyar Win
Combined Footings
➢ Spread footings that support more than one column or wall are
known as combined footings.
➢ They can be divided into two categories: those that support two
columns and those that support more than two (generally large
numbers of) columns.
➢ When the bearing capacity of the subsoil is low so that large
bearing areas become necessary, individual footings are
replaced by continuous strip footings that support more than
two columns and usually all columns in a row.
➢ Sometimes such strips are arranged in both directions, in which
case a grid foundation is obtained, as shown in Fig. 16.13.
➢ Strip footings can be made to develop a much larger bearing
area much more economically than can be done by single
footings 31
16
Prepared by - Dr. Kyaw Zeyar Win
33
17
Prepared by - Dr. Kyaw Zeyar Win
Two-column Footings
➢ It is desirable to design combined footings so that the centroid of
the footing area coincides with the resultant of the two column
loads.
➢ This produces uniform bearing pressure over the entire area and
forestalls a tendency for the footings to tilt.
➢ In plan, such footings are rectangular, trapezoidal, or T-shaped, the
details of the shape being arranged to produce coincidence of
centroid and resultant.
✓ If a single footing cannot be centered under an exterior column is
to place the exterior column footing eccentrically and to connect it
with the nearest interior column footing by a beam or strap.
✓ This strap, being counterweighted by the interior column load,
resists the tilting tendency of the eccentric exterior footing and
equalizes the pressure under it. Such foundations are known as
strap, cantilever, or connected footings. 35
36
18
Prepared by - Dr. Kyaw Zeyar Win
18"×24" 24"×24"
18'-0"
38
19
Prepared by - Dr. Kyaw Zeyar Win
9" x
750
39
40
20
Prepared by - Dr. Kyaw Zeyar Win
3.5 ft
18.75 ft
1.2x170+1.6x130 1.2x250+1.6x200
= 412 kips = 620 kips
x=7.78'
SFD
x=8.47' 155.1
345.4
272 k-ft
BMD
259 k-ft
1602.66 k-ft
41
Vu = ϕVc
d
376−44.4× = 6.408d
12
d = 37.2 in
Required h = d + 3 + 0.5db = 37.2 + 3 + 0.5 = 40.7 in
Use h = 41 in, d = 41 – 3.5 = 37.5 in
42
21
Prepared by - Dr. Kyaw Zeyar Win
37.5
18 + = 36.75"
2
24 + 37.5 = 61.5"
Under exterior column
b0 = (2×36.75) + 61.5 = 135 in
Vu = (1.2D+1.6L) - qu(Punching shear area)
36.75×61.5
= 412 − 6.83× = 304.8 kips
144
1
ϕVc = ϕ4λ fc′ b0 d = 0.75×4×1× 3000×135×37.5×
1000
= 831.85 kips >Vu = 304.8 kips (OK) 43
2Mu 2×1602.66×12
a = d − d2 − = 37.5− 37.5 2 − = 2.98 in
0.765f′c b 0.765×3×6.5×12
Mu 1602.66×12
As = a = = 9.89 in2
ϕfy d − ൗ2 0.9×60× 37.5− 2.98ൗ
2
As(min) = ρminbd = 0.0033×6.5×12×37.5 = 9.65 in2
Use As = 9.89 in2
Use 10-No.9 bars (As(prov) = 10 in2 > As(req) = 9.89 in2)
44
22
Prepared by - Dr. Kyaw Zeyar Win
Check ld
ld fy ψ t ψ e 60000 ×1.3 ×1
= = = 71.2
db 20 f′c 20 3000
ld = 71.2×1.128 = 80.31 in
Available length = (7.78+1.5)×12 – 3 = 108.36 in > ld (OK)
For cantilever portion
Mu = 272 k-ft
2Mu 2×272×12
a = d− d2 − = 37.5− 37.52 − = 0.489 in
0.765f′c b 0.765×3×6.5×12
Mu 272×12
As(req) = a = = 1.62 in2
ϕfy d − ൗ2 0.9×60× 37.5− 0.489ൗ12
As(min) = 9.75 in2 ; Use As = 9.75 in2 45
Check ld
ld fy ψ t ψ e 60000 ×1×1
= = = 54.77
db 20 f′c 20 3000
ld = 54.77×1.128 = 61.78 in
Available length = 3.5×12 – 3 = 39 in < ld
Thus, anchorage is required.
23
Prepared by - Dr. Kyaw Zeyar Win
1 1
Mu = ×qu B−c 2 ×Length = ×20.697× 6.5 − 2 2 ×36.75
8 8
= 1925.306 k−in
2Mu 2×1925.306
a = d− d2 − = 37.5− 37.52 − = 0.614 in
0.765f′c b 0.765×3×36.75
Mu 1925.306
As(req) = = = 0.959in2
ϕfy d − aൗ2 0.9×60× 37.5− 0.614ൗ
2
As(min) = ρminbd = 0.0033×36.75×37.5 = 4.55 in2
Use As = 4.55 in2
Use 8-No.7 bars. (As(prov) = 4.81 in2> As(req) = 4.59 in2)
47
Check ld
ld fy ψ t ψ e 60000 ×1×1
= = = 54.77
db 20 f′c 20 3000
ld = 54.77×0.875 = 47.9 in
6.5 − 2
Available length= ×12 − 3 = 24 in < ld
2
Thus, anchorage is required.
Transverse beam under interior column
Effective width = 61.5 in
1.2D+1.6L 620
qu = = = 18.61 ksf
A 6.5× 61.5ൗ12
1 1
Mu = ×qu B−c 2 ×Length = ×18.61× 6.5 − 2 2 ×61.5 = 2897.05 k−in 48
8 8
24
Prepared by - Dr. Kyaw Zeyar Win
d = 37.5 – 1 = 36.5
2Mu 2×2897.05
a = d− d2 − = 36.5− 36.5 2 − = 0.567 in
0.765f′c b 0.765×3×61.5
Mu 2897.05
As(req) = a = = 1.481in2
ϕfy d − ൗ2 0.9×60× 36.5− 0.567ൗ2
As(min) = ρminbd = 0.0033×61.5×36.5 = 7.41 in2
Use As = 7.41 in2
Use 13-No.7 bars. (As(prov) = 7.82 in2> As(req) = 7.41 in2)
Check ld
ld fy ψ t ψ e 60000 ×1×1
= = = 54.77
db 20 f′c 20 3000
49
ld = 54.77×0.875 = 47.9 in
6.5 − 2
Available length= ×12 − 3 = 24 in < ld
2
Thus, anchorage is required.
41"
23.25'
50
25
Prepared by - Dr. Kyaw Zeyar Win
18"×24" 24"×24"
18'-0"
51
150+100
Assume unit wt.of concrete and fill soil = =125 pcf
2
qe = 6000 – (6×125 + 100) = 5150 psf = 5.15 ksf
If the bottom of the strap is 6 in above the bottom of the footings to prevent
bearing on soil, the total depth to grade 5.5 ft.
Assume width of strap beam = 2′-6′′
Weight upon strap beam = 125×2.5×5.5 + 100×2.5 = 1968.75 lb/ft2 = 1.97 kips/ft
Assume the distance between footing = 8 ft
52
26
Prepared by - Dr. Kyaw Zeyar Win
18'-0"
1.97 kips/ft
6"
8'-0"
Remaining 8'-3"
Without strap beam (Take -0 ) Without strap beam
6'-9"×6'-9" 9'-6"×9'-6"
(Take -0 ) (Take -0 )
D+L 307.88
Required area for exterior footing = = = 59.78 ft2
qe 5.15
Take 15% increase for exterior footing area = 1.15×59.78 = 68.747 ft2
68.747
Take B = 6 ft, L = 11.46 ft Take 11.5 ft
6
27
Prepared by - Dr. Kyaw Zeyar Win
18'-0"
8'-3"
9'-0"
6'-0"
28
Prepared by - Dr. Kyaw Zeyar Win
12
11.5-2.5 d
-
2×425.86×12
2
= 20.5− 20.5 2 −
One way shear failure line
= 1.57 in d
0.765×3×6×12
11'-6" 18"×24" 2'-6"
Mu
As(req) =
ϕfy d − aൗ2
425.86×12
= = 4.80 in2
0.9×60× 20.5− 1.57ൗ2
6'-0"
57
Check ld
fy ψ t ψ e 60000 ×1×1
ld = db = ×0.75 = 32.86 in
25 f′c 25 3000
11.5−2.5
Actual available length = ×12 −3 = 51 in > required ld
2
58
29
Prepared by - Dr. Kyaw Zeyar Win
d 9-2 d
-
2 12
59
9'-0"
Vu ≤ ϕVc
9−2 d 1
7.01× − ×9= 0.75×2×1× 3000× 9×12 ×d×
2 12 1000
d = 15.62 in
30
Prepared by - Dr. Kyaw Zeyar Win
1
ϕVc = 0.75×4×1× 3000× 2×6.188+3.875 ×12×16.5× = 528.72 kips > Vu
1000
Thus, use h = 21 in and d = 16.5 in
16.5
4.5+1+ = 6.188'
2×12
=3.875'
d/2
16.5
12
2'-6" = 30" 24"×24" + 9'-0"
2.5+
d/2
punching shear
failure line d/2
61
9'-0"
2Mu 2×386.43×12
a = d− d2 − = 16.5 − 16.52 − = 1.18 in
0.765f′c b 0.765×3×9×12
Mu 386.43×12
As(req) = a = = 5.40 in2
ϕfy d − ൗ2 0.9×60× 16.5− 1.18ൗ
2
As(min) = ρminbd = 0.0033×9×12×16.5 = 5.88 in2
Use 14-No.6 (No.19) bars in X and Y directions. (As(prov) = 6.76 in2 > As(req)) 62
31
Prepared by - Dr. Kyaw Zeyar Win
Check ld
fy ψ t ψ e 60000 ×1×1
ld = db = ×0.75 = 32.86 in
25 f′c 25 3000
9 − 2.5
Actual available length = ×12 − 3= 36 in < required ld
2
Consider in Y direction due to the least length
The shear force and bending moment values can be obtained from shear force and
bending moment diagrams.
63
22.673 k-ft
Interior Footing
32
Prepared by - Dr. Kyaw Zeyar Win
2Mu 2×784.151×12
a = d− d2 − = 26.5 − 26.52 − = 5.79 in
0.765f′c b 0.765×3×30
Mu 784.151×12
As(reqd) = a = = 7.382 in2
ϕfy d− ൗ2 0.9×60× 26.5− 5.79ൗ
2
As(min) = ρminbd = 0.0033×30×26.5 = 2.624 in2
Use As(reqd) = 7.382 in2
Use 10-No.8 (No.25) bars. (As(provided) = 7.90 in2 > As(required) = 7.382 in2)
As 7.90
ρact = = = 0.0099 < 0.0181, OK, ϕ= 0.9 is valid.
bd 30×26.5
33
Prepared by - Dr. Kyaw Zeyar Win
18'-0"
2-No.4(No.13) Stirrups
@ 4"C/C 10-No.8 (No.25) bars
18"×24" (Main steel in strap) 24"×24"
Column Column
2-No.4(No.13)
Stirrups @ 6"C/C
11-No.5 (No.16 bars)
for distribution steel
24" 21"
6"
11-No.6 (No.19 bars) 14-No.6 (No.19 bars)
Stirrup support (Mesh)
6'-0" Steel in strap 9'-0"
23'-3"
68
34