Impact / Risk Assessment Form

Company: Marina Technology and Construction Pte Ltd RA Leader: Terrence Chan (Team Member) Reference
Approved By: Number:
Process: Probing water depth in reservoir RA Member 1: Hairuddin (Member)
Signature: IRA-04
Process/ Activity Location: Site RA Member 2: Dilaksan (Member)
Original Assessment Date: 01-Apr-2005 RA Member 3: Selvam (Member) Name: Vincent Mouille
Last Review Date: 31 Jul 2023 RA Member 4: David (Member) Designation: Managing Director
Next Review Date: 30 Jul 2026 RA Member 5: Elavarasan (Member) Date: 01-Aug-2023
Hazard Identification Risk Evaluation Risk Control
R R
Possible Injury Implementation
Ref Work Activity Hazard Existing Risk Controls S L P Additional Controls S L P Due Date Remarks
/ Ill health Person
N N
- Check weather and tidal information Provide lifebuoys at work area.
Check water depth in Project Manager
4a) Falling into water. Drowning before proceed. 5 1 5 Ensure there is a trained 5 1 5 On-going
reservoir. Supervisor
- Provide & use suitable life-jackets. lifeguard within the vicinity.
Exposure to
- Implement regular rest intervals.
weather elements
Dehydration, heat - Provide adequate supply of drinking
(e.g. sun, strong 2 1 2 NIL - - - - - -
injury / stress. water.
wind, rain, soak
- Provide adequate shade & ventilation.
in water)
- Provide and wear waterproof / cold wear
Shivering, / windbreaker.
Provide lifebuoys at work area.
tingling, - Check weather and tidal information Project Manager
5 1 5 Ensure there is a trained 5 1 5 On-going
numbness, frost before proceed. Supervisor
lifeguard within the vicinity.
bite. - Provide & use suitable life-jackets.
- Provide warm drinking water.

IRA-04 Probing water depth in reservoir Page 1 of 1