ADMINISTRATIVE APPROVALS
PC-I of the Project was approved by ECNEC at a cost of Rs. 7,982 million on September 19, 2007 on
cost sharing of 50:50 between GoP and GoS. Revised PC-I for an overall cost of Rs. 36,117.459
Million is approved by ECNEC on February 7, 2018, as per following details;
Lyari River Basin: Rs. 21,317.493 Million
Malir River Basin: Rs. 14,799.966 Million
Administrative Approval of Revised PC-I is issued on 6th March 2018.
Executing Agency: Karachi Water and Sewerage Board
The Engineer: Techno Consult International (Pvt.) Ltd. (Lead Firm) in association with
WS Atkins International U.K and
NEC Consultants (Pvt.) Ltd, Karachi.
Contractor: Pak Oasis Industries (Pvt.) Ltd
Existing TP-III consists of Main Pumping Station, Raw Sewage Channels, Inlet Works, Secondary
Pumping Station, Anaerobic Lagoons, Facultative Lagoons, General Pumping Station and Sludge
Drying Lagoons.
Upon completion of Stage-I of works under S-III Project current treatment facility consisting of
lagoons have been upgraded from 54 MGD to 77 MGD, after completion of Stage-II works, another
103 MGD will be treated under new Trickling Filter process, thus making the overall treatment
capacity of 180 MGD at TP-III.
The Stage-I works at TP-III is completed well within the awarded cost of Rs. 1,512.60 Million.
Influent Sewage
Head Works
Fine Screens
Detritors
Anaerobic Ponds
Sludge Drying Beds
Facultative Ponds