You are on page 1of 4

MEASUREMENT METHOD AND UNIT

ELECTRICAL WORK
FWBS CODE: 32-2100

GENERAL

(1) Unless otherwise noted, the following measurement methods and units shall be applied to
the electrical works which are defined in ANNEX-1.

(2) The quantities defined herein shall be "Net" based on JGC's preliminary drawings and/or
specifications unless otherwise noted.

(3) The quantities shall be re-measured on the construction drawing approved by JGC.

FWBS & DESCRIPTION UNIT OF BILL OF QUANTITY

32-2100 Electrical Work

32-2110 Generator
32-2111 Generator Set

This work item shall be enumerated per each complete set of generator irrespective of
number of auxiliary equipment such as line cubicles, NGRs (Neutral Grounding Resistors),
relay panels, generator control benchboards, etc.

This work item shall be measured when the following work activities are completed.

(1) Installation of Generators.

(2) Installation of line cubicles.

(3) Installation of NGRs.

(4) Installation of relay panels.

(5) Installation of generator control benchboards.

(6) Installation of DC system for the emergency lubrication oil pumps, including battery
installation work which consists of dissolving of powdered electrolyte, filling into
battery cells, setting of batteries on the racks and connection of links or wires
between batteries.

(7) Commissioning operation.

32-2112 Fuel Tank Set

32-2113 Fuel PIPELINE M

32-2114 Switch Board & Gear Set

This work item shall be enumerated per each complete set of switchgear, MCC or panel.
For MCC, each vertical section shall be deemed as one set.

This work item shall be measured when the following work activities are completed.
(1) Installation of switchgear, MCCs and panels .

(2) Inter-connection of bus bars and wires between switchgear, MCCs and panels.

(3) Tests and inspections.

(4) Energizing.

32-2115 LOW VOLTAGE DISTRIBUTION PANEL Set

32-2130 Distribution & Wiring

32-2130 Cabling and Wiring A ~ L M


This work shall be measured by linear meter of laid cables/wires irrespective of length
and size of cable trays, to be determined as follows:

(1) The length shall be measured from one side of termination point to the other side
as shown in construction drawings, not counting the cut off length.

(2) In case the cable length for laying is specified in a cable schedule, the measured
length shall be the specified length in the cable schedule less 6m.

(3) In case neither cable schedule nor construction drawing specifies the cable length
for laying, the length shall be measured in site from one side of termination point to
the other side, provided that no slack of cable shall be considered as measured
length.

This work item shall be measured when the following work activities are completed.

(1) Installation of cable trays

(2) Fabrication and installation of cable protection materials such as conduit pipes,
perforated cable trays, etc.

(3) Fixing of cable identification tags.

(4) Test and inspection including test reports.

32-2140 Lighting

32-2142 STREET LIGHT


32-2143 FENCE LIGHT
32-2144 SPORTS LIGHT

The above items of work (32-2142 through 32-2144) shall be measured in accordance
with the following sub-items, A through C :

32-2142A Pole/Support Set


32-2143A
32-2144A This work shall be enumerated per complete set of the pole mount type lighting
fixtures including foundations, cable laying (downstream of the lighting
panelboards).

This work item shall be measured when the following work activities are
completed.

(1) Installation of lighting fixtures including mounting pole/support.

(2) Cable laying.

(3) Installation of cable protection materials such as conduit pipes, cable trays,
etc.

32-2142B Lighting Fixture & Conv. Outlet Set


32-2143B
32-2144B This work shall be enumerated per complete set of stand, ceiling, pipe pendant
type lighting fixtures installed in plant including cable laying and/or wiring in
conduits (downstream of the lighting panelboards).

This work item shall be measured when the following work activities are
completed.

(1) Installation of lighting fixtures.

(2) Cable laying and/or wiring in conduit pipes.

(3) Termination of cables/wires.

(4) Installation of cable protection materials such as conduit pipes, cable trays,
etc.

32-2142C Cable and Wire M


32-2143C
32-2144C The same measurement method as "Cabling and Wiring" (FWBS 32-2130) shall
apply.

32-2150 Grounding

32-2151 Wiring of Grounding A~ C M

The laid grounding wire length shall be determined irrespective of size of wires by the
following method:

(1) In case the wire length is shown on the material take-off sheet, the laid length shall
be deemed to be 5% less than the value shown on the sheet.

(2) In case the wire length is not shown on the material take-off sheet, the length shall
be measured from the construction drawings.

This work item shall be measured when the following work activities are completed.

(3) Laying of grounding wires.

(4) Backfilling and compaction of trenches.

(5) Connection of wires to the equipment.

(6) Installation of protection pipes.

32-2152 Grounding Electrode A~ B Set


32-2170 Lightning System
32-2171 Wiring & Surge Arrestor
32-2171A Wiring M
32-2171B Surge Arrestor Set
32-2172 Lightning Rod Set