E05B ELECTRICAL SN6PX

Pre-Commissioning
LV Distribution Board
(Lighting & Small Power)

Tag No. F25-CP-01-X-1


Equipment Description: Control & Synchronization Panel
System No. ASP3-MJF25-81 Sub System No. ASP3-MJF25-8102
Location. Iraq
Data Sheet.
Drawing Reference. ASP3-4512952345-C03-0002
Area Classification Zone 1 / Zone 2 / Non Hazardous * Installation Indoor / Outdoor *
System Voltage / V, 3 Ph + N Rated Current A Freq’cy Hz Encl. Prot’n IP
Manufacturer: Model/Type no.:
Serial no.: PO No.:
Test Equipment Make Model Serial No. Cal. Expiry Date
IR Tester
Phase Rot’n tester
Multimeter
Punch
No. Items to be Checked OK N/A
List
Visual inspection of: nameplates, labelling, mounting, damage, completeness, cleanliness,
1
earthing, component ratings, cable entry & glanding, terminations, enclosure protection (IP).   
2 Connections are tight and correct.   
3 Check manual operation of Incoming switch, MCCB and/or RCCB   
4 Set Incoming MCCB and/or RCCB protection settings in accordance with Protection Study   
Perform IR Test on Busbar with all outgoing circuits and voltage indication circuits isolated
L1 – L2, L3, N, E L2 – L1, L3, N, E L3 – L1, L2, N, E N – L1, L2, L3, E
5   
MΩ MΩ MΩ MΩ
Confirm that the feeder circuit is checked and tested in accordance with ITR22B and that the
6
ITR is Completed and Accepted.   
Confirm that the feeder cable is checked and tested in accordance with ITR01A or ITR01B
7
and that the ITR’s are Completed and Accepted.   
8 Confirm outgoing circuits are isolated and energise the Switchboard   
9 Phase Rotation check, L1–L2–L3 measured at Incomer Expected CW Actual   
Voltage checks,
L1–L2 V L1–L3 V L2–L3 V
measured at Incomer.
10   
L1-N V L2-N V L3-N V L1-E V L2-E V L3-E V

11 Correct operation and indication of Panel metering devices   


12 Test MCCB and/or RCCB operation through manual Trip/Test button on the device   
13 Ensure all guards and protective covers are in place   
14 Red Line mark-up drawings are complete and attached   
15 Keysets and (special) tools are complete, available and handed-over   
Completed By Accepted By Comments / Remarks:

Signature:

Print Name:
Date:
Company:
Sheet 1 of 2
Sheet 2 of 2