Professional Documents
Culture Documents
Unit title: Supervise The Planning of On-site Medium Rise Building or Construction Work
Assessment Number: 3
Teacher Name:
2
1. Introduction
1.1. Purpose
The purpose of this report is to perform a project review of all the project options and select the
most appropriate project based on the team’s experience. The team will continue their research
and planning the selected project to establish an effective construction program and contractual
arrangement.
1.2. Background
The project selected for this report is a school that will demolish and reconstructed again. It has a
gross area of not more than 3000 meter square. It has a single storey. The project is located in
Hawthorne area in Melbourne.
1.3. Method
This research used secondary and based on qualitative methodology. It used research articles,
books and grey literature such as government websites.
1.4. Scope
The scope of this report is to perform a project review and will not implement the statutory,
contractual or sub-contracting selection.
3. Demolition phase
Identify the hazards. This involves identifying all of the potential hazards that could
cause harm to workers. Hazards can be physical, chemical, biological, ergonomic, or
psychosocial.
Assess the risks. This involves assessing the likelihood and severity of each hazard. The
likelihood of a hazard occurring can be rated as high, medium, or low. The severity of a
hazard can be rated as high, medium, or low.
Control the risks. This involves implementing controls to reduce the likelihood and
severity of each hazard. Controls can be engineering controls, administrative controls, or
personal protective equipment (PPE).
4
Review the controls. The controls should be reviewed regularly to ensure that they are
still effective (Salgın, 2019)
The method that will be used is mechanical demolition. This method involves using heavy
machinery, such as excavators, bulldozers, and wrecking balls, to tear down the building. This
method is often used for larger buildings or buildings that are made of heavier materials. (Salgın,
2019)
5. Construction sequence
Demolition
building decontamination
building demolition
Digging foundation
Installation of plumbing
6
Building stairs
Installation of toilet
Landscaping
Cleaning
Final inspection
Final touch-up
Change in project scope: The scope of a project can change for a number of reasons, such
as changes in the client's requirements, changes in the regulatory environment, or changes
in the availability of materials.
Delays in permits and approvals: Some projects require permits and approvals from
government agencies or other third parties.
Weather delays: Weather can also delay a construction project. For example, if it rains or
snows, it can make it difficult to work on the site. (Megha and Rajiv, 2013)
Scaffolding
Cranes
Hoists
8
Tents
Demolishing structures
Portable buildings
Signage
Fencing
Shoring
Bracing (Community, 2020)
9. Plant requirement
a. Demolition
Type and size
Hydraulic excavator
Crane
Dozer
Skid steer loader
Wrecking ball
Concrete crusher
Roll-off container (Excavations, 2023)
OHS major risks
9
Falling objects
Crushing
Entanglement
Noise
Vibration
Dust flying debris
Hazardous materials
Structure instability
Confined spaces (Excavations, 2023)
b. Construction
Type and size
Earth moving equipment
Hydraulic excavator
Backhoe
Bulldozer
Graders
Wheel tractor scraper
Trenchers
Material handling equipment
Cranes
Loaders
Forklifts
Telehandlers
Power saws
Nail guns
Ladders
Scaffolding
Concrete equipment
Concrete mixer
Concrete Pumps
Concrete finishers (Team, 2021)
10
9.2. Plan for access issues associated with plant / equipment chosen
a. Delivery
Some of the access issues associated with the delivery of plant and equipment used for the
construction of a house are:
Size and weight of the equipment: The size and weight of the equipment may restrict
access to the site. For example, a large crane may not be able to fit through a narrow gate
or driveway.
Access roads: The access roads to the site may not be wide enough or strong enough to
support the weight of the equipment.
Parking: There may not be enough parking space for the equipment on the site.
(Machinery, Plant and Equipment (Labour Administration and Inspection), 2023)
b. Operation
Some of the access issues associated with the operation of plant and equipment used for the
construction of a house are:
11
Space requirements: The equipment may require a lot of space to operate. For example, a
concrete mixer needs a large area to mix and pour concrete.
Noise levels: The equipment may generate noise levels that are too high for residential
areas.
Vibration: The equipment may cause vibration that can damage nearby structures.
Dust: The equipment may generate dust that can be a nuisance to neighbors. (Machinery,
Plant and Equipment (Labour Administration and Inspection), 2023)
9.3. On your site plan locate the plant and equipment and plan for their installation or use.
Concrete pump: The concrete pump can be used to pump concrete to high places. It can
be positioned near the foundation to make it easy to pump the concrete.
Scaffolding: The scaffolding can be used to access high places. It can be positioned
around the foundation to make it easy to build the structure. (Facilitator, 2023)
Plant registration: In some cases, plant may need to be registered with a relevant
authority before it can be used. For example, cranes and hoists must be registered with
WorkSafe Australia.
Inspection and maintenance: Plant must be inspected and maintained regularly to ensure
that it is safe to use. The frequency of inspections and maintenance will vary depending
on the type of plant.
Training: Workers who operate plant must be trained in how to use it safely. The training
requirements will vary depending on the type of plant and the specific tasks that the
worker will be performing.
Labelling: Plant must be labelled with appropriate safety warnings. The warnings must be
clear and easy to understand. (Safeworkaustralia, 2012)
9.5. Procedures for the health and safety of workers with regards to plant and equipment
a. List documentation
Plant and equipment safety manual
Risk assessment
Risk assessment
Training records
13
a. Explain
Identify the need for plant: The first step is to identify the need for plant.
Obtain quotes from suppliers: Once the need for plant has been identified, quotes should
be obtained from suppliers.
Select a supplier: Once quotes have been obtained, a supplier should be selected..
Execute a lease or rental agreement: Once a supplier has been selected, a lease or rental
agreement should be executed. (Victoria University, 2018)
Payment schedules: Payment schedules should be agreed upon between the contractor
and the client at the start of the project.
Retentions: Retentions are sums of money that are withheld from payments to the
contractor until the project is complete.
Performance bonds: Performance bonds are guarantees that are issued by a third party.
Loss prevention plans: Loss prevention plans should be developed to identify and
mitigate the risks of losses.
Loss monitoring systems: Loss monitoring systems should be implemented to track and
report on losses. (Clough et al., 2015)
10.1. Systems you have to record materials entering and leaving the site.
a. Explain ownership
The ownership of materials entering and leaving a construction site is important for a number of
reasons, such as:
14
It helps to ensure that the materials are being used for the intended purpose and that they
are not being stolen.
It helps to track the materials throughout the construction process, which can be
important for quality control and cost management.
It can help to identify any potential liability issues in the event of an accident.
There are a number of different ways to track the ownership of materials on a construction site.
One common approach is to use a materials tracking system. This type of system typically
involves using barcodes or RFID tags to identify the materials, and then tracking their
movements through the construction process. (Melbourne.vic, 2021)
b. Explain contract
There are a number of different ways to track the ownership of materials on a construction site.
One common approach is to use a materials tracking system. This type of system typically
involves using barcodes or RFID tags to identify the materials, and then tracking their
movements through the construction process. In Australia, the following construction operations
systems are typically used to record materials entering and leaving a school demolition and
reconstruction site:
Materials tracking system: This is a computerised system that uses barcodes or RFID tags
to identify materials and track their movements through the construction process.
Materials log: This is a simple list of the materials that are entering and leaving the site,
along with the date and time of each entry or exit.
Contract: The contract between the owner of the site and the construction contractor
should also specify the ownership of materials entering and leaving the site
(Melbourne.vic, 2021)
The following are some of the construction operations OHS procedures for all site personnel in
Australia regarding school demolition and reconstruction:
Pre-start safety meeting: A pre-start safety meeting should be held before any demolition
or reconstruction work begins.
15
Safe work method statements (SWMS): SWMS should be developed for all demolition
and reconstruction work.
PPE: All personnel working on the demolition or reconstruction site must wear
appropriate PPE. PPE should include hard hats, safety glasses, steel-capped boots, etc.
Confined spaces: Any confined spaces on the demolition or reconstruction site must be
identified and assessed.
Moving machinery: All moving machinery on the demolition or reconstruction site must
be properly controlled.
Waste disposal: All waste materials must be disposed of in a safe and environmentally
friendly manner.
Emergency procedures: Emergency procedures must be in place in case of an accident or
other emergency. (Zou and Zhang, 2009)
Hazard identification and risk assessment: This is the first step in any risk management
process. It involves identifying the hazards and risks associated with the project, and then
assessing the likelihood and severity of each hazard.
Risk control: This involves implementing control measures to reduce the risks associated
with the project. Control measures can include engineering controls, administrative
controls, and personal protective equipment (PPE).
Monitoring and review: The risk management process should be monitored and reviewed
regularly to ensure that it is effective. This involves reviewing the hazards and risks, and
then adjusting the control measures as needed. (Managing Risks | Safe Work Australia,
2023)
11.1. Communication strategies with the subcontractors and the importance of the
following
a. Induction
All subcontractors should be given an induction that covers the company's safety procedures and
the specific hazards of the site. Inductions are an important part of any safety program. They
16
provide an opportunity to introduce new employees to the company's safety procedures and to
the specific hazards of the site. (Maliha et al., 2021)
b. Toolbox meeting
Toolbox meetings should be held regularly to discuss safety issues and to ensure that everyone is
aware of the latest changes. Toolbox meetings are an important way to communicate safety
information to employees. They are typically held on a weekly or monthly basis, and they
provide an opportunity to discuss the latest safety issues and to answer any questions that
employees may have. (Maliha et al., 2021)
c. Safety walks
Safety walks should be conducted regularly to identify and address any potential hazards. Safety
walks are an important way to identify and address potential hazards on the construction site.
They should be conducted regularly by a qualified person, such as a safety officer. (Maliha et al.,
2021)
d. Site diaries
Site diaries should be kept to document all safety-related activities. Site diaries are an important
way to document all safety-related activities. They should be kept by a qualified person, such as
a safety officer. (Maliha et al., 2021)
The Australian Work Health and Safety (WHS) Act 2011 sets out the requirements for
employers to have an emergency response plan in place. This plan should include:
Hazard and risk management is an ongoing process that involves identifying, assessing, and
controlling hazards in the workplace. This process should be documented and reviewed
regularly. The following steps can be used to manage hazards in the workplace:
Identify hazards. This can be done by conducting a hazard identification and risk
assessment.
Assess the risks associated with each hazard. This involves considering the likelihood
and severity of the hazard.
Implement control measures to reduce the risks. Control measures can include
engineering controls, administrative controls, and personal protective equipment (PPE).
Monitor and review the effectiveness of the control measures. (Law And Regulation |
Safe Work Australia, 2023)
a. Near miss
Near misses are accidents that did not result in injury or damage, but could have done.
They are still important to report because they can help identify hazards and risks in the
workplace.
Near misses should be reported to the employer as soon as possible. The employer should
then investigate the incident and take steps to prevent it from happening again.
b. Serious accident
Serious accidents are accidents that result in injury or damage. They are more serious
than near misses and require a more thorough investigation.
Serious accidents should be reported to the employer and the relevant authorities as soon
as possible. The employer should then investigate the incident and take steps to prevent it
from happening again.
c. Fatality
Fatalities are the most serious type of accident. They result in the death of an employee.
Fatalities must be reported to the employer and the relevant authorities as soon as
possible. The employer must then investigate the incident and take steps to prevent it
from happening again (Safeworkaustralia, 2012)
18
13. Conclusion
This report performed a review for a school project. The report performed a project review of all
the project options and selected the most appropriate project based on the team’s experience. The
team identified and evaluated the research and planning on the selected project and establish an
effective construction program and contractual arrangement.
19
14. References
Clough, R.H., Sears, G.A., Sears, S.K., Segner, R.O. and Rounds, J.L., 2015. Construction
contracting: A practical guide to company management. John Wiley & Sons.
Community, E. 2020. The different types of temporary structures. The Engineering Community.
https://www.theengineeringcommunity.org/the-different-types-of-temporary-structures/
Facilitator, C. 2023. Concrete pump evolution and applications in modern construction. Constro
Facilitator. https://constrofacilitator.com/concrete-pump-evolution-and-applications-in-
modern-construction/
Hamakareem, M. I. 2019. What are Permanent and Temporary Works at Construction Sites? The
Constructor. https://theconstructor.org/construction/const-management/permanent-
temporary-works-construction/36249/#:~:text=Examples%20of%20temporary%20site
%20works,site%2C%20and%20provide%20temporary%20paving.
Law and regulation | Safe Work Australia. 2023. Safe Work Australia.
https://www.safeworkaustralia.gov.au/law-and-regulation
Machinery, plant and equipment. Labour administration and inspection. 2023. ILO.
https://www.ilo.org/global/topics/labour-administration-inspection/resources-library/
publications/guide-for-labour-inspectors/machinery-plant-equipment/lang--en/index.htm
Maliha, M.N., Abu Aisheh, Y.I., Tayeh, B.A. and Almalki, A., 2021. Safety barriers
identification, classification, and ways to improve safety performance in the architecture,
engineering, and construction (AEC) industry: Review study. Sustainability, 13(6),
p.3316.
Megha, D. and Rajiv, B., 2013. A methodology for ranking of causes of delay for residential
construction projects in Indian context. International Journal of Emerging Technology
and Advanced Engineering, 3(3), pp.396-404.
Salgın, B., 2019. An Examination of the Development of the Construction and Demolition
Waste-Related Regulations in Turkey. Periodica Polytechnica Architecture, 50(2),
pp.169-177.
Victoria University. 2018. Health Safety and Wellbeing - Plant and Equipment Management
Procedure. https://policy.vu.edu.au/download.php?id=347&version=1
Zou, P.X. and Zhang, G., 2009. Comparative study on the perception of construction safety risks
in China and Australia. Journal of construction engineering and management, 135(7),
pp.620-627.
21