Professional Documents
Culture Documents
g~&Manage~
Safety Recommendations Founded 1863
IGE/SR/18 Edition 2 Royal Charter 1929
Communication 1678 Patron
Her Majesty The Queen
Price Code: T2
© The Institution of Gas Engineers and Managers
12 York Gate
London NW1 4QG
Tel: 020 74870650
Fax: 020 7224 476
Email: general@igem.org.uk
IGEjSR/18 Edition 2
CONTENTS
SECTION
PAGE
1 I ntrod uction 1
2 Scope 3
3 Legislation 4
APPENDIX
2 References 19
SECTION 1 : INTRODUCTION
1.1 These Recommendations supersede IGE/SR/18 Part 1 and IGE/SR/18 Part 2
(respectively Communications 1447 and 1599). They combine the scopes of the
former Parts 1 and 2.
Usually, work will be carried out with respect to a service other than gas plant,
for example water pipes, but may on occasion be with respect to another item
of gas plant.
1.4 It is now widely accepted that the majority of accidents in industry are in some
measure attributable to human as well as technical factors in the sense that
actions by people initiated or contributed to the accidents, or people might have
acted better to avert them.
The primary responsibility for compliance with legal duties rests with the
employer. The fact that certain employees, for example "responsible
engineers", are allowed to exercise their professional judgement does not allow
employers to abrogate their primary responsibilities. Employers must:
(c) Have systems and procedures in place to ensure that the exercise of
professional judgement by "responsible engineers" is subject to
appropriate monitoring and review.
1
IGEM, 12 York Gate, London NW1 4QG www.igem.org.uk
IGEjSR/18 Edition 2
Note: The responsible engineer is a suitably qualified, competent and experienced engineer or a
suitably qualified, competent and experienced person acting under his or her supervision,
appointed to be responsible for the application of all or part of these Recommendations.
1.5 These Recommendations do not attempt to make the use of any method or
specification obligatory against the judgement of the responsible engineer.
Where new and better techniques are developed and proved, they should be
adopted without waiting for modification of these Recommendations.
Amendments to these Recommendations will be issued when necessary and
their publication will be announced in the Journal of the Institution and other
publications as appropriate.
2
IGEM, 12 York Gate, London NW1 4QG www.igem.org.uk
IGEjSR/18 Edition 2
SECTION 2 : SCOPE
2.2 These Recommendations cover work in the vicinity of gas plant in easements,
under highways and on private land.
2.3 These Recommendations apply to gas plant of all materials and at any
maximum operating pressure (MOP).
3
IGEM, 12 York Gate, London NW1 4QG www.igem.org.uk
IGEjSR/18 Edition 2
SECTION 3 : LEGISLATION
These Recommendations are set out against a background of legislation in force in Great
Britain at the time of publication. Similar legal considerations are likely to apply in other
countries and reference to appropriate national legislation will be necessary.
HASAWA applies to all work activities. It places general duties on employers to ensure,
as far as is reasonably practical, the health, safety and welfare of their employees and
the health and safety of members of the public who may be affected by the activity,
are safeguarded.
NRSWA lays down standards of service and performance for all utilities in the execution
of their statutory rights to excavate within the public highway.
PSR require that no person shall cause damage to a pipeline which may give rise to
danger and that the pipeline operator must inform persons of the existence and
whereabouts of a pipeline.
4
IGEM, 12 York Gate, London NW1 4QG www.igem.org.uk
IGEjSR/18 Edition 2
This section provides gUidance on steps to be taken when work is to be carried out in the
vicinity of gas plant, irrespective of the location of the plant. Measures vary on occasion with
respect to notifications and contractor activities, dependent upon whether the work is being
carried out under NRSWA or whether the pipeline is in an easement.
4.1.1 Consultation
4.1.1.1 Contact should be made with any affected party, by the promoter at the
planning stage, to avoid interference and possible delays. Where appropriate,
consideration should be given to diverting any affected pipeline in advance of
starting work.
4.1.1.2 The operator should have in place a system to ensure that any interested
promoter or contractor can be made aware of the location of any gas plant in
the vicinity of works, and the protection measures required, prior to starting
work.
4.1.1.3 The operator should consider providing frequent promoters, for example
statutory undertakers and highways authorities, with information on the location
of gas plant on CD-ROM or similar format.
Where such information is not given, the operator should respond to any
notification of works as soon as practicable after the works have been classified
(see clause 4.1.5).
4.1.1.4 The contractor should be provided with contact telephone numbers and the gas
emergency telephone number.
4.1.1.5 Notes of any meetings and telephone conversations should be taken and
recorded. All relevant decisions taken should be confirmed and agreed in
writing.
4.1.1.6 Alterations to planned works and working practices should be reviewed in light
of current site conditions.
4.1.2 Notifications
Note 1: Practical guidance on compliance is presented in the "Code of Practice for the Co-ordination
of Street Works for Road Purposes and Related Matters".
Note 2: Many excavations are carried out where notices may not have been given to other utilities.
This may be a result of the works being carried out by a non-statutory body working in the
highway, such as a utility infrastructure provider (VIP) or a private developer making, for
example, a sewerage connection. Highways authorities grant street works licences to
undertake street works and, hence, NRSWA will apply.
5
IGEM, 12 York Gate, London NW1 4QG www.igem.org.uk
IGE/SR/18 Edition 2
4.1.3 Records
If works have not started by the expiry date of the notification, the
promoter/contractor should be contacted.
4.1.4.4 Landowner/tenantenqulf~s
6
IGEM, 12 York Gate, London NW1 4QG www.igem.org.uk
IGE/SR/18 Edition 2
Responses to land purchase enquiries should identify the gas plant name, MOP,
any easement width and building development recommendations.
4.1.5.1 Works should be classified according to the degree of risk involved. A risk
assessment should be carried out for each activity.
Note: The assessment needs to include the location of gas plant, its MOP, proximity to property
and the working methods being adopted.
4.1.5.2 Works undertaken where the probability of damage is high and where the
consequences are hazardous should be identified as higher risk.
Until the gas plant is accurately located on site, all works should be considered
as higher risk works.
Note: Pipelines of MOP exceeding 7 bar are subject to special consideration (see Section 5).
Works undertaken where the probability of damage is low and where the
consequences are not hazardous should be identified as lower risk.
4.1.5.4 For any discovered non-notified works found by the operator or where notified
works involve a change of activity compared to those initially notified, the works
should be classified or re-c1assified, as appropriate. If work is ongoing and a full
assessment cannot readily be carried out, consideration should be given to
stopping work until a proper evaluation can be completed.
4.1.6.1 Arrangements should be made for appropriate and scheduled inspection. The
level and frequency of inspection for each location should be scheduled taking
into consideration the type of work being undertaken and planned so that all
critical phases of the works are observed.
4.1.6.2 Consideration should be given to full time supervision at higher risk works (see
clause 4.1.5).
4.1.6.3 The operator should ensure that all protective measures, agreed with the
promoter/contractor, are in place.
If agreed protection measures have not been undertaken, the operator may
suspend work until such measures are applied. Such suspension should be
confirmed in writing.
4.1.6.4 The operator should make an individual record of each inspection visit. When
gas plant is exposed, details of its size, location, material and condition should
be recorded.
7
IGEM, 12 York Gate, London NW1 4QG www.igem.org.uk
IGEjSR/18 Edition 2
4.1.7.1 Where a request has been received from the contractor, the location of any gas
plant in the vicinity of the work should be determined by the operator and the
promoter/contractor should be advised within 7 days.
Route maps and gas plant records should be consulted to establish the presence
of any fittings or attachments on the gas plant at the location of the proposed
works.
Prior to site work commencing, the gas plant should be located by the operator
or by the contractor with prior agreement. For a steel pipeline, this should be
carried out using a locator with a pipe depth measurement accuracy of 5% of
depth for cover up to 5 m. For other metallic pipelines or PE pipelines
containing a metallic location strip, a suitable locating instrument should be
used.
When determining whether trial holes are required, and if so how many, the
operator should consider the need to prove the location and depth of a pipeline
based on information available from the pipeline records, site conditions,
recorded depth of cover, the proposed depth of the promoter's/contractor's
service and its construction method statement.
Note: These factors should be sufficient to enable assessment of the risk of damage to the
pipeline and, hence, the need for a trial hole.
If trial holing is to be carried out, the operator should be given the opportunity
to supervise the activity.
4.1.7.3 Where it is decided not to trial hole to locate a pipeline, hand dug trial holes
should be excavated to a depth of 600 mm below the depth of any proposed
new promoter's/contractor's service to prove adequate clearance.
4.1.7.4 Once located, the gas plant should be pegged out, or suitably marked, at
suitable intervals. A peg, or mark, should be positioned at the apex of every
bend, including field bends. There should not be any bend between pegs or
marks.
4.1.7.5 Previously agreed working practices should be reviewed based on actual site
conditions. This may be carried out at any time during the work.
4.1.8.1 Any risk to gas plant should be considered and, if deemed appropriate, the
operator should be present to monitor the excavation work.
4.2.1 General
8
IGEM, 12 York Gate, London NW1 4QG www.igem.org.uk
IGEjSRj18 Edition 2
4.2.1.2 Heavy construction plant and materials should not be permitted to cross over
gas plant unless appropriate provisions, such as timber, concrete or steel rafts,
have been agreed.
4.2.2 Demolition
4.2.2.1 Demolition should not be allowed within 150 m of gas plant, or 400 m for a
structure mass greater than 10000 tonnes, without an assessment of the
vibration levels at the plant. The measured distance extends from the edge of
the area affected by falling material to the plant.
Where the peak particle velocity is predicted to exceed 30 mm sec- i , the ground
vibration should be monitored (see also clause 4.2.2.2).
4.2.2.2 For a welded steel or PE pipeline, the peak particle velocity should not exceed
75 mm sec- i at the pipeline.
Where the peak particle velocity is predicted to exceed 50 mm sec- i , the ground
vibration should monitored.
4.2.2.3 For a cast iron or ductile iron pipeline, the peak particle velocity should not
exceed 25 mm sec- i at the pipeline. A leakage survey should be undertaken
before work starts and at appropriate intervals during the work.
4.2.2.4 Where ground conditions comprise submerged granular deposits of silt or sand,
an assessment of the effect of vibration on settlement and liquefaction at the
pipeline should be made.
4.2.3.1 Where the new service is cathodically protected and the gas plant is similarly
protected, the pipeline operator should request that interference tests be carried
out to determine whether its own system is adversely affected.
4.2.3.2 Should any cathodic protection posts or associated equipment need moving to
facilitate third party works, reasonable notice should be given to the operator.
9
IGEM, 12 York Gate, London NW1 4QG www.igem.org.uk
IGE/SR/18 Edition 2
When the operator's gas plant has been exposed, welding or other hot works on
the contractor's service, involving naked flames, should not be carried out in
proximity to the plant unless suitable protection has been agreed and provided.
Gas leak checks should be undertaken, by the operator, before and during such
operations.
The use of chain trenchers should not be permitted within 3 m of the pipeline.
The operator should consider the risk any work may have on the integrity of the
pipeline and, hence, determine the level of monitoring that is required to be
carried out by the operator.
4.2.7.2 Removal of the bituminous or concrete highway surface layer below 300 mm
deep should be by hand-held power assisted tools under the supervision of the
operator's responsible person unless, in exceptional circumstances, and
following a risk assessment, the operator relaxes these conditions.
4.2.7.3 Excavation with a powered mechanical excavator should not be carried out
closer than 3 m to a located pipeline and, with hand-held power assisted tools,
no closer than 1.5 m. Any fitting, attachment or connecting pipework should be
exposed by hand. All other excavation should be by hand.
4.2.7.4 "No dig" techniques should not be used to cross a pipeline, unless it has been
exposed to ena ble the safe passage of the new service to be observed.
4.2.7.5 Any new service running parallel to a pipeline should be laid no closer than
600 mm.
4.2.7.8 Contractors should give operators at least 48 hours of intent to backfill over,
under or alongside a pipeline. Any damage to the pipeline coating should be
reported immediately to the operator so that repairs can be made prior to
backfilling.
10
IGEM, 12 York Gate, London NW1 4QG www.igem.org.uk
IGEjSR/18 Edition 2
4.2.8.1 Hand dug trial holes should be undertaken to determine the exact location of
pipeline. All excavations within 500 mm of the pipeline should be by hand.
4.2.8.2 Where a new service crosses above or below a pipeline, or runs parallel, a
clearance of 1.5 times the diameter of the pipeline or 300 mm, whichever is the
greater, should be maintained.
Note: This distance may be reduced at the discretion of the operator and subject to adequate
protection being provided.
4.2.8.3 The effects of deep excavations around and below a pipeline should be
considered in conjunction with the pipe material and MOP.
4.2.8.5 Any scoring or marking of PE pipes should be reported to the operator who
should assess any damage to determine if replacement is required.
4.2.8.6 Work in proximity to a ductile iron pipeline should be reported to the operator
who should assess any damage to determine if replacement is required.
4.2.8.7 Care should be taken to ensure that any cast iron pipeline is SUitably protected
and supported during works (due to the susceptibility of the material to
fracture).
4.2.8.8 Extreme care should be taken when working in close proximity to any asbestos
or PVC pipeline (due to the susceptibility of the materials to fracture). It is
imperative that these are satisfactorily protected and supported.
4.2.8.9 All reinstatement materials and techniques must comply with NRSWA.
4.2.8.11 All unidentified or redundant plant should be considered live until proven
otherwise.
11
IGEM, 12 York Gate, London NW1 4QG www.igem.org.uk
IGEjSR/18 Edition 2
4.3.1.1 Excavation with a powered mechanical excavator should not be carried out
closer than 3 m to a located pipeline and, with hand-held power-assisted tools,
no closer than 1.5 m. Any fitting, attachment or connecting pipework should be
exposed by hand. All other excavation should be by hand.
Where sufficient depth of cover exists following evidence from hand dug trial
holes, light, tracked vehicles may be permitted by the operator to strip topsoil
to a depth of 250 mm.
4.3.1.2 Topsoil or other materials should not be stored within the easement without the
written permission of the operator. Topsoil or other materials should not be
stored over the pipeline.
4.3.1.4 Following works, the level of cover over a pipeline should be the same as that
prior to works commencing, unless agreed otherwise with the operator.
4.3.1.5 A new service should not be laid parallel to a pipeline, within an easement. In
special circumstances, and with the written permission of the operator, this may
be relaxed for short excursions in which case the service should be laid no closer
than 600 mm to the side of the pipeline.
12
IGEM, 12 York Gate, London NW1 4QG www.igem.org.uk
IGE/SR/18 Edition 2
4.3.4.1 Mechanical excavators should not be sited or moved above a pipeline unless
written authority has been given by the operator (see clause 4.2.1.2).
4.3.4.2 Mechanical excavators should not be sited or moved above a pipeline with the
cab positioned on the other side.
4.3.4.3 Mechanical excavators and other traffic should be positioned far enough away
from the trench to prevent trench wall collapse.
4.3.5.1 Where the new service is cathodically protected and the gas plant is similarly
protected, the operator should request that interference tests be carried out to
determine whether its own system is adversely affected.
4.3.5.2 Should any cathodic protection posts or associated equipment need moving to
facilitate third party works, reasonable notice should be given to the operator.
Note: The peak particle velocities indicated apply to all types of seismic and vibration inducing
activities.
4.3.6.1 Piling or boring should not be allowed within 15 m of buried gas plant without an
assessment of the vibration levels at the location of the gas plant.
4.3.6.2 For welded steel or PE plant, the peak particle velocity at the plant should be
limited to a maximum of 40 mm sec-I.
Where the peak particle velocity is predicted to exceed 30 mm sec-I, the ground
vibration should be monitored.
4.3.6.3 On a ductile or cast iron pipeline, the peak particle velocity should not exceed
25 mm sec- I and leakage surveys should be undertaken at appropriate intervals
during the works.
4.3.6.4 Where ground conditions are of submerged granular deposits of silt and sand,
an assessment of the effect of vibration on settlement and liquefaction at the
pipeline should be made.
13
IGEM, 12 York Gate, London NW1 4QG www.igem.org.uk
IGE/SR/18 Edition 2
4.3.7 Blasting
4.3.7.1 For MOP exceeding 7 bar, blasting should not be allowed within 250 m of buried
gas plant without an assessment of the vibration levels at the location of the gas
plant.
For MOP not exceeding 7 bar, blasting should not be allowed within 30 m of
buried gas plant without the written consent of the operator.
Where the peak particle velocity is predicted to exceed 30 mm sec- 1 , the ground
vibration should be monitored (see also clause 4.3.7.2).
4.3.7.2 For welded steel or PE plant, the peak particle velocity at the plant should be
limited to a level of 75 mm sec- 1 •
1
Where the peak particle velocity is predicted to exceed 50 mm sec- , the
ground vibration should be monitored.
4.3.7.3 On a ductile or cast iron pipeline, the peak particle velocity should not exceed
25 mm sec- 1 and a leakage survey should be undertaken at appropriate intervals
during blasting operations.
4.3.7.4 Where ground conditions are of submerged granular deposits of silt or sand, an
assessment of the effect of vibration on settlement and liquefaction at the
pipeline should be made.
Where mineral extraction extends up to the easement, a stable slope angle and
stand-off distance between the pipeline and slope crest should be determined.
The easement strip should be marked clearly by a suitable permanent boundary
such as a post and wire fence. Where appropriate, slope indicator markers
should be erected to facilitate the verification of the recommended slope angle
as the slope is formed.
The easement and slope should be inspected periodically to identify any signs of
developing instability. This may include any change of slope profile, including
bulging, the development of tension cracks on the slope or easement, or any
changes in drainage around the slope. The results of each inspection should be
recorded.
14
IGEM, 12 York Gate, London NW1 4QG www.igem.org.uk
IGE/SR/18 Edition 2
4.3.10 Demolition
4.3.10.1 Demolition should not be allowed within 150 m of the gas plant, or 400 m for a
structure mass greater than 10000 tonnes, without an assessment of the
vibration levels at the plant. The measured distance extends from the edge of
the area affected by falling material to the plant.
Where the peak particle velocity is predicted to exceed 30 mm sec- 1 , the ground
vibration should be monitored (see also clause 4.2.10.2).
4.3.10.2 For a welded steel or PE pipeline, the peak particle velocity should not exceed
75 mm sec- 1 at the pipeline.
Where the peak particle velocity is predicted to exceed 50 mm sec- 1 , the ground
vibration should monitored.
4.3.10.3 For a cast iron or ductile iron pipeline, the peak particle velocity should not
exceed 25 mm sec- 1 at the pipeline. A leakage survey should be undertaken
before work starts and at appropriate intervals during the work.
4.3.10.4 Where ground conditions comprise submerged granular deposits of silt or sand,
an assessment of the effect of vibration on settlement and liquefaction at the
pipeline should be made.
When the operator's gas plant has been exposed, welding or other hot works on
the contractor's service, involving naked flames, should not be carried out in
proximity to the plant unless suitable protection has been agreed and provided.
Gas leak checks should be undertaken, by the operator, before and during such
operations.
15
IGEM, 12 York Gate, London NW1 4QG www.igem.org.uk
IGEjSR/18 Edition 2
Note: No action is required for an existing pipeline buried at 2.4 m or more except where a
change in operating conditions, such as uprating, adding cover, etc. is proposed.
4.3.15 Landfilling
4.3.16 Backfilling
Third parties should provide the operator with at least 48 hours notice of intent
to backfill over, under or alongside the pipeline. Any damage to the pipeline or
main coating should be reported immediately to the operator so that repairs can
be made prior to backfilling.
Ground conditions, vehicle types and crossing frequency should determine the
type of raft required.
The operator should consider conducting a leakage survey over any susceptible
pipeline, for example over a cast iron main, before works commence and at
appropriate intervals during the work.
Details of all third party and operator's activities within the easement, together
with any activity outside of the easement, which could have a detrimental
influence on the integrity of a pipeline, should be recorded on an encroachment
form.
16
IGEM, 12 York Gate, London NW1 4QG www.igem.org.uk
IGE/SR/18 Edition 2
17
IGEM, 12 York Gate, London NW1 4QG www.igem.org.uk
IGE/SR/18 Edition 2
easement A strip of land in, upon and over which the undertaking
acquired the right to lay, construct, inspect, maintain,
protect, use, replace, remove, or render unusable a
pipeline or main for the transmission or storage of gas or
other materials connected with the exercise and
performance of the functions of the operator, and all
necessary apparatus ancillary thereto.
gas plant Includes gas pipelines and associated gas installations that
are the responsibility of the operator.
PE Polyethylene.
public highway A way over which all members of the public have a right to
pass and re-pass provided that the use of the way must be
as of right and not by permission.
18
IGEM. 12 York Gate, London NW1 4QG www.igern.org.uk
IGE/SR/18 Edition 2
APPENDIX 2 : REFERENCES
These Recommendations are set out against a background of legislation in force in Great
Britain at the time of publication. Similar considerations are likely to apply in other countries
where reference to appropriate national legislation is necessary.
All relevant legislation must be complied with and relevant Approved Codes of Practice
(ACoPs), official Guidance Notes and referenced codes, standards, etc. should be taken into
account.
Where British Standards, etc. are quoted, equivalent national or international standards, etc.
equally may be appropriate.
Care should be taken to ensure that the latest editions of the relevant documents are used.
A2.1 LEGISLATION
• Health and Safety at Work, etc. Act 1974
• New Roads and Street Works Act 1991
• Pipelines Safety Regulations 1996
• Street Works (Register, Notices, Directions and Designations) Regulations
1992
• Road Works (Register, Notices, Directions and Designations) (Scotland)
Regulations 1992.
19
IGEM, 12 York Gate, London NW1 4QG www.igem.org.uk
Published by the Institution of Gas Engineers and Managers
12, York Gate, London NW1 4QG
July 2002 Communication 1678 (IGE/SR/18 Edition 2) Copyright