ESTIMASI PEKERJAAN OVERLAY

Volume
No. Lokasi Pekerjaan A T BJ Keterangan Dokumentasi
Tack Coat ACWC Scrapping

1 Ramp 10 Kunciran (Bleding) 394.82 0.05 2.30 394.82 45.40 1.00

2 Ramp 10 Kunciran (Perbatasan 120.00 0.05 2.30 120.00 13.80 0.80


dgn JKC)

3 KM 14+200 L 229.50 0.05 2.30 229.50 26.39 1.53

4 KM 15+800 L 325.00 0.05 2.30 325.00 37.38 0.50

5 KM 16+000 L 150.00 0.05 2.30 150.00 17.25 1.00

6 KM 16+280 L 75.00 0.05 2.30 75.00 8.63 0.50

7 KM 16+360 L 200.00 0.05 2.30 200.00 23.00 1.00

8 KM 17+520 L 150.00 0.05 2.30 150.00 17.25 1.00

9 KM 19+000 L 153.00 0.05 2.30 153.00 17.60 1.53


Volume
No. Lokasi Pekerjaan A T BJ Keterangan Dokumentasi
Tack Coat ACWC Scrapping
10 KM 19+240 L 250.00 0.05 2.30 250.00 28.75 0.50

11 KM 19+760 L 75.00 0.05 2.30 75.00 8.63 0.50

12 KM 19+880 L 150.00 0.05 2.30 150.00 17.25 1.50

13 KM 20+300 L 180.00 0.05 2.30 180.00 20.70 1.20

14 Ramp 7 Parigi 59.05 0.05 2.30 59.05 6.79 0.80

15 KM 19+880 R 225.00 0.05 2.30 225.00 25.88 1.50

16 KM 19+240 R 135.00 0.05 2.30 135.00 15.53 0.90

17 KM 16+400 R 180.00 0.05 2.30 180.00 20.70 0.90

3,051.37 350.91 16.66