Logistics & Warehousing Process

Start

Consignment Request (CR) From Management

Milestone # 1
Equipment On-Shore

Custom Clearance

Transportation to Lahore Warehouse


Equipment Inbound Process

N Is GRN Count
Milestone # 2

According to
MR

N
Any
Damaged
Good
Milestone # 3

Material Unload on Tagged


Markings (as per WH Grid System)

E-Tagging on Items
Milestone # 4

Bar Code Scanning & Input in


Inventory Software
Milestone # 5

Equipment Sorting &


Segregation(Type/Weight/Size)
Warehouse Processes

Unpacking of Required
Equipment

Milestone # 6
Mapping of Equipment With
Site ID’s/Regions

Creation of Packing list & item


coding

Equipment Inventory & Status Overdue Equipment Report


Report

Commented [NM1]: Count Down Start

Material Request (MR) from Project


Team
Milestone # 7
Equipment Outbound Processes

W/H team Verify the Stock Availability

W/H Team Prepare Delivery Note (DN)


as Per MR

W/H team Prepares 2 Copies of DN


(Equipment Ready to Pick)
Milestone # 8

Commented [NM2]: Timelines (1 Day)


Logistic Team Prepares Transportation

Loading in truck & Copy to W/H & 1


DN handover to Security Team
Equipment Transport to site
Equipment Outbound Processes

Commented [NM3]: Timelines (2 Days)


Installation Team Receive Equipment

Milestone # 9
Installation Team Sign the DN as POD

Logistics team Scan & Return POD in Warehouse

Commented [NM4]: Timelines (3 Days)