Date Prepared: September 01, 2022 Date Submitted: September 06, 2022
RESOURCES PERSON REMARK(S)/
ACTIVITIES/TASK STRATEGIES/OBJECTIVES TIMELINE
NEEDED RESPONSIBLE OUTCOME
Pre-implementation
Organize a SWT with at least To organize and Prepare October School School Principal Organized a
10 members the School Watching 10-11, Watching School DRRM School Watching
The moderator presents the Team. 2022 Checklist Coordinator Team.
guidelines of SW activity. To present the SW (Annex 1) Physical Facilities
Prepare the timeline and activity guidelines. Coordinator Set a schedule for
route for the conduct of SW To be prepared for the SPG Officers or school the school
and hazard mapping in conduct of the SW and students watching mapping.
school. hazard mapping in team.
Provide a SW Checklist to school.
Team members for guidance To be guided in the
in the observation of conduct of the SW.
hazards.
Actual-Implementation
Orient the SWT on the > To orient/inform the October White School Principal Accomplished
background and purpose of SWT about the 12-13, Cartolina, School DRRM School Watching
the activity. background and purpose 2022 Bondpaper/No Coordinator Checklist
of the activity. tebook Physical Facilities
Walk through each building, Ballpen Coordinator
classroom, office, garden, and >To find and identify the Marker/ Parents, Teachers Identified the
any open area of the school. hazardous/risky areas in Signages SPG Officers or school hazardous areas in
And observe and take down the school using the School students watching school.
notes for 3-5 minutes. checklist. Watching team.
Checklist
Process the information >To finalize the collected
noted by SWT to be led by the data and hazard map Illustrated a school
moderator. based on the SWT Hazard map.
discussion and prepare
for a presentation to the
School Planning Team.
Post implementation
Present and coordinate the result of >To present and coordinate
SW and Hazard map to the SPT. the result of the SW and October Printer School DRRM Coordinator Successfully
hazard map to the school 17-18, Laptop completed the
project team (SPT). 2022 School Map activity and reports.
APPROVED: