INSPECTION AND TEST PLAN

PROJECT NAME/NO.: CORDOBA (PHASE 1) AT BLOOM LIVING, ZAYED CITY, ABU DHABI - MAIN WORKS PACKAGE

EMPLOYER: BLOOM DISTRICT PROPERTIES CONTRACTOR: Emirates Link Maltauro LLC

ENGINEER: DAR AL-HANDASAH CONSULTANT SUB-CONTRACTOR:

Doc. Submittal Reference: M-DT-ITP-033000-ST-006 Rev. No.: A

Description: Concrete Repairing Works Date: 27/2/2023


INSPECTION POINT
QUALITY INSPECTIONS REFERENCES
PROCESS CONTROL FORMS
SN FREQUENCY OF TEST (Mode of ACCEPTANCE CRITERIA (SPECIFICATION, METHOD
DESCRIPTION DATA SUB
measurement) STATEMENTS, OTHERS) COMPANY CONSULTANT CONTRACTOR TPI
CONTRACTOR

A Preliminary work / Document Review

1 Relevant Authority Requirements

1.1 NOC’s and permits Once at start of the project Relevant Authority As per Project As per requirements Authority Approval S R S

2 Shop Drawing & Method Statement Submittal

Specification Section #
2.1 Shop Drawings Once at start of the project Review Shop Drawings As per IFC / ADM DWG
033000
Check & Review R A R S

As per Project Specification Section #


2.2 Method Statement Once at start of the project Review Method Statement
Specifications 033000
Review R W/H S S

3 Material Submittal & Approval

Witness & Checked by


Repair Material EPDM CR 320 N Compliance as per Specification Section # Engineer's for
3.1 for Minor honey Combs
Once at start of the project Material Approval Request
Specification 033000 preparation,mixing &
S W/A R S
application
Witness & Checked by
Repair Material EPDM CR 310 N
Compliance as per Specification Section # Engineer's for
3.2 Smoothing for Edges & Corners Once at start of the project Material Approval Request
Specification 033000 preparation,mixing &
S W/A R S
Damages
application

4 Third Party Qualification Submittal & Approval (as required)

Sub-Contractor/Supplier Review and Submit Min 5 Years Experience in Specification Section # Review Prequalification
4.1 Prequalification
Once at start of the project
Prequalification Documents UAE or as per Vendor List 033000 Documents
R A R S

B Material Receiving Inspection and Testing

AD20164-0200S-FM-17 REV 00 1
INSPECTION AND TEST PLAN

PROJECT NAME/NO.: CORDOBA (PHASE 1) AT BLOOM LIVING, ZAYED CITY, ABU DHABI - MAIN WORKS PACKAGE

EMPLOYER: BLOOM DISTRICT PROPERTIES CONTRACTOR: Emirates Link Maltauro LLC

ENGINEER: DAR AL-HANDASAH CONSULTANT SUB-CONTRACTOR:

Doc. Submittal Reference: M-DT-ITP-033000-ST-006 Rev. No.: A

Description: Concrete Repairing Works Date: 27/2/2023


INSPECTION POINT
QUALITY INSPECTIONS REFERENCES
PROCESS CONTROL FORMS
SN FREQUENCY OF TEST (Mode of ACCEPTANCE CRITERIA (SPECIFICATION, METHOD
DESCRIPTION DATA SUB
measurement) STATEMENTS, OTHERS) COMPANY CONSULTANT CONTRACTOR TPI
CONTRACTOR

5 Material Inspection and Testing

Delivery Note &


Repair Material EPDM CR 320 N Once required material at Compliance as per Specification Section #
5.1 for Minor honey Combs site
Material Approval Request
Specification 033000
preparation,mixing & S W/A R S
application
Repair Material EPDM CR 310 N Delivery Note &
Once required material at Compliance as per Specification Section #
5.2 Smoothing for Edges & Corners
site
Material Approval Request
Specification 033000
preparation,mixing & S W/A R S
Damages application

C Construction Phase

6 Activity 1 (according to the subject)


Specification Section #
6.1 Minor Repair For each element Visual Check As per approved material
033000
Checked by Engineer's S W R S
Specification Section #
6.2 Major Repair For each element Visual Check As per approved material
033000
Checked by Engineer's S W R S
Smoothing of edges & corners Specification Section #
6.3 damages
For each element Visual Check As per approved material
033000
Checked by Engineer's S W R S
MEP Sleeves and Conduits Specification Section #
6.4 repairing
For each element Visual Check As per approved material
033000
Checked by Engineer's S W R S

D Post Construction Activities

7 Closeout Document Submittals

Review As Built Drawings & Specification Section #


7.1 As built records Once handover the project
Approval
As per site / As Built DWG
033000
Check & Review S H/A R S

LEGENDS: W – Witness H – Hold R – Review A – Approval S – Surveillance TPI – Third Party Inspection Agency

AD20164-0200S-FM-17 REV 00 2