1) If 35 men can finish a work in 8 days, 16 men can finish the same work in 10 days. The number of men is 38.
2) If 40 men working 12 hours a day can complete a work in 8 days, 50 men working 4 hours a day can complete the same work in 16 days.
3) If it takes 40 cows 40 days to eat 40 bags of husk, it will take 1 cow 40 days to eat 1 bag of husk.
1) If 35 men can finish a work in 8 days, 16 men can finish the same work in 10 days. The number of men is 38.
2) If 40 men working 12 hours a day can complete a work in 8 days, 50 men working 4 hours a day can complete the same work in 16 days.
3) If it takes 40 cows 40 days to eat 40 bags of husk, it will take 1 cow 40 days to eat 1 bag of husk.
1) If 35 men can finish a work in 8 days, 16 men can finish the same work in 10 days. The number of men is 38.
2) If 40 men working 12 hours a day can complete a work in 8 days, 50 men working 4 hours a day can complete the same work in 16 days.
3) If it takes 40 cows 40 days to eat 40 bags of husk, it will take 1 cow 40 days to eat 1 bag of husk.
1) If 35 men can finish a piece of a day; in how many days will 16
work in 8 days then the number of pumps raise 1736 tonnes of water men who can do the same work in 10 working 9 hours a day? days is a) 6 a) 38 b) 7 b) 28 c) 8 c) 19 d) 9 d) 17
6) 21 binders can bind 1400 books in
2) If 40 men working 12 hours a day 15 days. How many binders will be can complete a work in 8 days, then required to bind 800 books in 20 how many men working 4 hours a days? day can complete the same work in a) 7 16 days ? b) 9 a) 50 c) 12 b) 60 d) 14 c) 54 d) 45 7) Running at the same constant rate, 6 identical machines can produce a 3) In a dairy farm 40 cow eat 40 bags total of 270 bottles per minute. At of husk in 40 days. In how many days this rate, how many bottles could 10 one cow will eat one bag of husk? such machines produce in 4 minutes? a) 1 a) 648 1 b) 40 b) 1800 c) 2700 c) 40 d) 10800 d) 80 8) 39 persons can repair a road in 12 days, working 5 hours a day. In how 4) 5 person can prepare an many days will 30 persons, working 6 admission list in 8 days working 7 hours a day, complete the work? hours a day. If two persons join them a) 10 so as to complete the work in 4 days b) 13 they need to work per day for c) 14 d) 15 a) 8 hours b) 9 hours 9) A man completes of a job in 10 c) 10 hours days. At this rate, how many more d) 12 hours days will it takes him to finish the job? a) 5 5) If 18 pumps can raise 2170 tonnes b) 6 of water in 10 days, working 7 hours c) 7 Chain Rule d) 7 2 1 a) 25 b) 50 c) 75 10) If 7 spiders make 7 webs in 7 d) Cannot be determined days, then 1 spider will make 1 web in how many days? a) 1 b) 7 7 c) 2 d) 49
11) An industrial loom weaves 0.128
metres of cloth every second. Approximately, how many seconds will it take for the loom to weave 25 metres of cloth? a) 178 b) 195 c) 204 d) 488
12) 36 men can complete a piece of
work in 18 days. In how many days will 27 men complete the same work? a) 12 b) 18 c) 22 d) 24 e) None of these
13) 4 mat-weavers can weave 4 mats
in 4 days. At the same rate, how many mats would be woven by 8 mat- weavers in 8 days? a) 4 b) 8 c) 12 d) 16
14) A contract under took a work to
complete in 60 days but just after 20 days we observe that only 1/5th of the project had been completed. To complete the work in time, minimum how many workers he had to increase, if there were initially 75 workers deployed for the task?